Project Organization Structure

for the Acquisition & Implementation of


Core Insurance Solution

Bunna Insurance S.C

1
Introduction

 The Bunna insurance S.Co. Is intending to fully computerize its


core functions (Non-life insurance) through implementing the
core insurance solution
 The implementation of the project passes through different

phases
 Responsibilities of the Bunna Insurance S.Co. and Software

vendor.
 The document specifies different parties/stakeholders that

shall be involved in the implementation of the project and their


respective responsibilities

2
Project activities

 Pre Project activities before Selecting Core Insurance Software

Vendor

 Project activities after Selecting Core Insurance Software

Vendor

3
Pre Project activities

1. Information Technology Project structure formation (two


Weeks )
◦ IT Steering Committee formation
◦ IT Project Office formation
◦ User Group Formation
2. Requirement Specification Document (RFP)
Preparation( Two months)
◦ Establishing RFP Preparation Team
◦ Bid document preparation for Core Insurance Application project
◦ Bid document preparation for Hardware and network infrastructure
project
3. Bid Document Floating ( Two months )
4
Pre Project activities
4. Technical Evaluation ( One month )
◦ Forming Technical Evaluation Team
◦ Prepare bid evaluation Matrix
◦ Technical Evaluation on Document Level
◦ Demonstration guild line and test case or scenario preparation
◦ Technical Evaluation on Demonstration Level
5. Financial Evaluation ( One Week )
◦ Forming Financial Evaluation Team
◦ Finalizing Technical and Financial Evaluation
6. Conducting Site Visit on the selected vendor ( One Week )
◦ Prepare site visit interview Questioners
◦ Head office, Development site and Implementation site (both local
and international)
5
Pre Project activities
7. Inviting the selected Vendor for negotiation ( One week)

8. Contract document Preparation (Three Weeks )


9. Conducting Negotiation ( One Month )
◦ Technical Negotiation
◦ Financial Negotiation
◦ Contractual Negotiation
10. Awarding the contract ( One day )
11. Contract signing ( One day )

6
Project Activities(Major Milestones)

Phase 1 - Project kick-off Meeting


 is the first meeting between the project team of the vendor and

the client
 The meeting would define the major phases of the project and

introduces members of the project team of the client and the


vendor
 It provides the opportunity to discuss the role of each team

member
 the detailed project plan, project charter, risk plan, change

management procedure, status reporting format, quality


assurance procedure, responsibility matrix, etc., will be presented
and discussed.

7
Phase 2 - Hardware and software acquisition and implementation

 Refers to procurement, installation and configuration of the


required hardware, software, storage, tape library, etc., for the
implementation of core insurance system.

 This phase of the project need to be completed and ready


prior to the installation and deployment of the UAT ready
version of the Core insurance Application.

8
Phase 3 Requirement Specification Document
(RSD) Preparation
 Gathering and documenting the requirement specifications/
business process and rules of the functional, non-functional,
reporting, and data migration requirements through document
analysis and interview/discussion with each users group
 Conducting user workshop/discussion forum/ which helps to get
comments from business experts of the company on the
gathered requirement specifications (if required).
 Signoff the RSD
◦ including functional, non-functional, reporting and data migration
requirements
 Preparation of the GAP analysis

9
Phase 4 - System setup, configuration,
customization and internal testing
 This task will be performed by the vendor based on the RSD
 Internal testing by the vendor (unit testing, integration
testing, system testing, alpha and beta testing,)
 Quality assurance

10
 
Phase 5 - Preparation of acceptance test case / criteria and test data
 Test case shall be prepared for functional, non-functional,
reporting and data migration requirements stated in the
Requirement Specification Document.
 For each test case, the required test data shall be prepared

which either extracted from the actual file or using the


hypothetical data.
 The preparation of test case and test data is entirely the

responsibility of the BIC

11
Phase 6 – Arranging Training and Testing Venue

 refers to arranging and making ready the training and testing


environment/testing venue/ at BIC site

 including availing the required number of computers,


printers, servers, o/s, DBMS, etc., and network connectivity

12
Phase 7 Installation and Deployment of Core
insurance Application and ERP

 This refers to the installation and deployment UAT ready


version of Core insurance Application and ERP on training and
test servers.

13
Phase 8– Technical (IT) Staff and Super Users
Training

 refers to training of the IT staffs and Super users/users


group/ on UAT ready version of Core insurance Application
prior commencement of UAT testing.

14
Phase 9– UAT (functional) testing-
 focus on the functionalities of the system thereby validating
the fitness-for-use of the system by the business users.
 Conducting user acceptance and data migration testing by

each respective users group


 Modification of the system based on UAT test result
 Signing off the user acceptance testing after all the reported

defects are cleared


 Issuance of UAT certificate

15
Phase 10 - Installation and deployment
 After completion of UAT testing, UAT certified/production/
version of the application shall be installed and deployed on
the production environment

16
Phase 11 – Operational and performance testing
( Non- functional testing)

 validates whether the system is ready for operation and this type
of test is usually performed by the IT team / system
administrators
 it includes testing of
 security vulnerability testing,
 performance/response time/ testing,
 flexibility testing including flexibility of the reporting tools and completeness of
published meta data, etc.,
 inter-operability testing,
 maintainability testing,
 reliability/correctness/testing,
 usability testing /ease of use
 recoverability testing,
 remote processing capability testing,
 completeness of query tools, etc., 17
Phase 12 - End users and Managers training
 Conducting end users and managers training on UAT certified
version of Core insurance Application and ERP

18
Phase 13 – Data migration
 refers to conducting of the actual data migration including
◦ Customer data
◦ Active policy
◦ Clam history
◦ Ledger balance
◦ Etc.

19
Phase 14 – Go live

 At this stage all branches or selected branches will be using


this application

20
Phase 15 – Handover

 User and technical manuals

 Application/object code of Core insurance Application written


on DVD

21
Phase 16 – Operational support –
 Refers to providing operational support for three months after
go live. During the three months operational period, the old
system shall run in parallel with the new system.

22
Phase 17– Issuance of Operational Acceptance
Certificate (OAC)
 OAC shall be issued after successful completion of all the
above stated phases.

23
Project Organization Structure

24
Automation Steering Committee (ASC)
 The Steering Committee, next to the Board of Directors, is
the highest approval body in the project organization and it
is composed of the following members

◦ Chef Executive Officer - Chairperson


◦ Deputy Chef Executive Officer - Member
◦ Manager, Business Development and planning - Member
◦ Manager, Finance Department - Member
◦ Manager, HRM and Property Administration - Member
◦ Manager, IT Department ` - Member
◦ Secretary

25
Project Management Office (PMO)
 The Project Management Office is composed of the following
member (working on full time bases) and led by the Project
Manager.
 The PMO is accountable to the steering committee.
 The PMO shall comprises of the followings

◦ IT Manager - Project Manager– Leader


◦ System Administration Member
◦ H/W and Network administrator Member
◦ Database administrator Member
◦ General Insurance Business Analyst Member

26
Users Groups
 The Users Groups are formed for each of the major units or
functionalities of the company.
 It shall constitute capable and experienced business experts

drawn from different work units.


 It is estimated that the project tasks may require the

participation of each users at least on half day basis.


 The users group that shall be formed, and members and

leaders assigned to each user groups are as listed hereunder.

27
28
Experts assigned to the pool
 The experts assigned to the pool are those experts that are
knowledgeable but cannot be assigned to the project due to
their work load.
 However they are instead assigned to the pool and shall be

involved in the project as required to get their comment and


advice from their product knowledge and experience
 The followings are those that are assigned to the pool
(1) Leader
(2) Member
(3) Member

29
Duties and Responsibilities of the Project Stakeholders

◦ Board of Directors
◦ The Steering Committee
◦ The Project Management Office (PMO)
 The Project Coordinator
 The General Insurance Business Analyst
 The System Analyst
◦ The Users Group
 Functional Users Groups
 Non-functional Users Group
◦ The User Group Leader
◦ The Logistics Team

30
Duties and Responsibilities( Cont. )_

(1) Board of Directors


 Get monthly project progress report from the Steering Committee
(2) Steering Committee
◦ Consists of seven members ( from top mang. Group)Responsible of
 Reviewing and approving the following project mang. Documents
 Detailed project plan
 Risk plan
 Communication protocol and format
 Change management procedure
 Project governance structure
 Quality assurance procedure
 Responsibility matrix
 Staff schedule
 Project progress reporting format 31
Duties and Responsibilities( Cont. )_

Steering Committee (Cont.)


 Review and approve completion of the milestones including
RSD(BSM) Preparation
Users Acceptance test plan and test data preparation
Users Acceptance Testing (UAT)
Operational and performance testing
Data migration
End users training
Go live and parallel run

32
Duties and Responsibilities( Cont. )_

 Steering Committee ( Cont)


◦ Responsible for
Review the progress of the project
Allocation of the required resource
Review and approve change request issues( if
any )
Resolve project conflicts, disputes, and
reconciling of differences of opinion

33
Duties and Responsibilities( Cont. )_

Steering Committee ( Cont. )


Steering Committee meeting shall be conducted on every two
weeks on ______________
Receive project status report every week on Monday from PMO
For the Steering Committee meeting, the following documents
shall be circulated at least two days before the meeting
 Agenda for the meeting
 Minutes of the last meeting
 Project progress report
 Activity plan and any other relevant documents

34
Duties and Responsibilities( Cont. )_

Steering Committee ( Cont.)


Discussion carried out on
Accomplishment against last meeting plans
Completed
Delayed
Not yet started
Upcoming weekly activity plan
New issues
Milestones review
Outstanding issues, open points, and project conflicts
Any other business

35
Duties and Responsibilities( Cont. )_

 Steering Committee
The minutes of the meeting shall circulate in less than 3
days
Summary of the decision and action plan shall be
circulated in less than 2 days
Submit project progress report to Board of Directors
within five days after end of every month
Obtain company experts opinion on each milestones

36
Duties and Responsibilities( Cont. )_

(3) Project Management Office (PMO)


Accountable to the Steering Committee
Consists of five members of both IT, and business experts
Members are full time assigned to the project
Responsible of
 Act as single point of contact for communication with the vendor
 Coordinate the preparation of project management documents
 Coordinate and assist the users group in the preparation of the
RSD and confirm its completeness

37
Project Organization (Cont.)
PMO ( Cont.)
◦ Assist the users group in the preparation of the test case
and review its completeness
◦ Follow up the acquisition, installation and readiness of the
network, servers and storage infrastructure before UAT
◦ Coordinate the business users and IT staffs training
◦ Coordinate the user acceptance testing
◦ Coordinate the data migration activities

38
Project Organization (Cont.)
PMO ( Cont. )
Undertake operational and performance testing on the
basis of the non-functional requirements
Coordinate the parallel run
Propose the policy, procedure and job descriptions that
need to be modified due to the IT implementations
Follow-up the project progress and report weekly to the
Steering Committee
Request the required resources

39
Project Organization (Cont.)
PMO ( Cont. )

 Provide orientation to the users groups on each milestones

 Compile the up coming week activity plan of each users group


on every Friday and discuss on it on every Saturday

 Communicate the up coming weekly activity plan to each users


group on every Monday

 Compile weekly project progress report of each users group on


every Friday

40
Project Organization (Cont. )
PMO ( Cont. )
 Conduct weekly project meeting with the vendor representative on every Saturday
 In the project meeting, discuss on the status of each project tasks
 Completed tasks
 On schedule tasks
 Behind schedule tasks
 Cancelled tasks
 In the meeting the following document shall be discussed
 Minutes of the last meeting
 Previous week activity plan
 Progress report
 Upcoming week activity plan, and any other documents

41
Project Organization (Cont. )

PMO (Cont. )

Leader of each users group shall attend the weekly PMO project
meeting

Submit the weekly progress report along with the PMO minutes to
the Steering Committee on every Monday

Sign a protocol with the vendor for the delayed activity

42
Project Organization (Cont. )
 Functional Users Group
 Functional and non-functional users groups
 Each users groups are accountable to the PMO
 Each users group shall have a group leader
 Each members of the users group shall have a job
assigned from the group leader
 Assigned on half day basis
 The following user groups will be formed
 Underwriting and intermediary users groups (8 )
 Claim and Engineering Users Groups (4)
 Reinsurance users groups (2)
 Finance and shareholder account users groups (4)
 MIS users group (3)
 ERP users group (3)
 Non-functional/software quality /users group(4)

43
Project Organization
Users Groups ( Cont. )
 Audit Users Group (5)
 Logistics Team ( 3)
◦ Duties and responsibilities
 Explain the business rules of each product and functionalities
 Compiling the requested documents
 Capturing the functional requirements as per given template
 Reviewing the completeness of the requirement specification by the peer and
the group leader before forwarded to the PMO
 Each members of the users group shall be assigned to prepare the test case and
test data for the specific product or functionalities
 The test case and test data prepared by each members shall be review by its
peers and also by the group leader

44
Project Organization
Duties and responsibilities ( Cont. )
Each members of the users group shall conduct UAT
( validation 1, and validation 2) on the specific product or
functionalities
The PMO office shall assist each users groups during the
UAT
Submitting the user acceptance test result and follow-up
clearing of any defects if any
Signing a protocol at completion of each milestone
( including RSD, Acceptance test plan and test data, UAT,
Data migration, etc. )
Providing training to end users
45
Project Challenges
 Forgetting major requirements during RFP & RSD preparation
 Foreign Currency
 Delay of Hardware
 Staff turnover
 Delay in decision
 Office building
 Lack of Motivation
 Vendor may liquidate

46
Thank You