Professional Documents
Culture Documents
3. DD - due date
• Jobs are processed according to due date,
earliest due date first.
Priority Rules
4. CR - critical ratio
• Jobs are processed according to smallest ratio of
time remaining until due date to processing time
remaining.
6. Rush – emergency
• Emergency or Preferred Customers first.
Assumptions to Priority Rules
1. Setup time is deterministic.
2. The set of jobs is known, no new jobs
arrive after processing begins and no jobs
are canceled.
3. Processing times are deterministic rather
than variables.
4. There will be no interruptions in
processing such as machine breakdowns ,
accidents or worker illnesses.
Definitions
1. Job Flow Time
2. Job Lateness
This is the length of time the job
completion date is expected to exceed
the date the job was due or promised
to a customer.
Definitions
3. Makespan
This is the total time needed to complete a
group of jobs. It is the length of time
between the start of the first job in the
group and the completion of the last job
in the group.
4. Average Number of Jobs
Jobs that are considered in a shop are
considered to be work in process
inventory. Mathematically
Average Number of Jobs= Total Flow Time / Makespan
Example
Determine the sequence of jobs,
average time flow, average days late
and average number of jobs at the
work center, for each of these rules:
1. FCFS
2. SPT
3. DD
4. CR
Example Data
JOB Processing Due Date
Time
A 2 7
B 8 16
C 4 4
D 10 17
E 5 15
F 12 18
FCFS
Assume Jobs arrived in the following
order: A-B-C-D-E-F
JOB Processing Flow Due 2-3
Sequences Time (1) Time Date
( cumulative
processing (3)
time)
(2)
A 2 2 7 0
B 8 10 16 0
C 4 14 4 10
D 10 24 17 7
E 5 29 15 14
F 12 41 18 22
41 120 54
FCFS
Average Flow time= Total Flow
Time/Number of Jobs=120/6=20
days
Average Tardiness=54/6=9
workstation=
120/41=2.93 jobs per workstation
SPT rule
SPT, the sequence is A-C-E-B-D-F
Average Tardiness=40/6=6.67days
Time/Number of Jobs=108/6=18
days
Summary Part A,B,C and D
JOB Average Average Average
Sequences Flow Lateness Number of
Rule Time (Days) Jobs of the
(Days) Work
Center
FCFS 20.00 9.00 2.93
SPT 18.00 6.67 2.63
DD 18.33 6.33 2.68
CR 26.67 14.17 3.9
Two Work Center Sequencing
Johnson’s Rule: Technique for
minimizing completion time for a
group of jobs to be processed on two
machines or at two work centers.
Minimizes total idle time
Several conditions must be
satisfied
Johnson’s Rule Conditions
1. Job time must be known and
constant.
2. Job times must be independent of
sequence.
3. Jobs must follow same two-step
sequence.
4. Job priorities cannot be used.
5. All units must be completed at the
first work center before moving to
second.