Professional Documents
Culture Documents
Capital Budgeting Decisions: Should We Build This Plant?
Capital Budgeting Decisions: Should We Build This Plant?
Should we
build this
plant?
1
SEEMA CHAKRABARTI
CAPITAL BUDGETING DECISIONS
The investment decisions of a firm are generally known
as the capital budgeting, or capital expenditure
decisions.
3
AN EXAMPLE OF MUTUALLY
EXCLUSIVE PROJECTS
4
TYPES OF CASH FLOWS
Normal or Conventional Cash Flow :
One change of signs.
Cost (negative CF) followed by a series of positive
cash inflows.
5
CAPITAL BUDGETING DECISIONS
These are generally:
MIRR DPBP
7
NET PRESENT VALUE
NPV of a project is the sum of the present values
of all the cash flows positive as well as negative
that are expected to occur over the life of the
project.
The formula for NPV is:
C1 C2 C3 Cn
NPV n
C0
(1 k ) (1 k ) (1 k ) (1 k )
2 3
n
Ct
NPV C0
t 1 (1 k )
t
8
NET PRESENT VALUE
Where,
Ct = cash flow at the end of year t
n = Life of the project
k = discount rate (given by the projects opportunity
cost of capital which is equal to the required rate of
return expected by investors on investments of
equivalent risk).
C0 = Initial investment
1 / (1 + k )t = known as discounting factor or PVIF
i.e present value interest factor. 9
CALCULATING NET PRESENT VALUE
Assume that Project X costs Rs 2,500 now and is
expected to generate year-end cash inflows of Rs
900, Rs 800, Rs 700, Rs 600 and Rs 500 in years 1
through 5. The opportunity cost of the capital may
be assumed to be 10 per cent.
Rs 900 Rs 800 Rs 700 Rs 600 Rs 500
NPV 2
3
4
5
Rs 2,500
(1+0.10) (1+0.10) (1+0.10) (1+0.10) (1+0.10)
NPV [Rs 900(PVF1, 0.10 ) + Rs 800(PVF2, 0.10 ) + Rs 700(PVF3, 0.10 )
+ Rs 600(PVF4, 0.10 ) + Rs 500(PVF5, 0.10 )] Rs 2,500
NPV [Rs 900 0.909 + Rs 800 0.826 + Rs 700 0.751 + Rs 600 0.683
+ Rs 500 0.620] Rs 2,500
NPV Rs 2,725 Rs 2,500 = + Rs 225 10
ACCEPTANCE RULE OF NPV
Accept the project when NPV is positive
NPV > 0
Reject the project when NPV is negative
NPV < 0
May accept or reject the project when NPV is zero
NPV = 0
( A project will have NPV = 0, only when the project generates
cash inflows at a rate just equal to the opportunity cost of
capital)
The NPV method can be used to select between
mutually exclusive projects; the one with the higher
NPV should be selected.
11
ADVANTAGES OF NPV METHOD
It considers time value of money.
It is a true measure of profitability as it uses the
present values of all cash flows (both outflows &
inflows) & opportunity cost as discount rate rather than
any other arbitrary assumption or subjective
consideration.
The NPVs of individual projects can be simply added to
calculate the value of the firm . This is known as
“Principle of value additivity”.
It is consistent with the shareholders wealth
maximization principle as whenever a project with
positive NPV is undertaken, it results in positive cash
flows and hence the increase in the value of the firm.
12
DISADVANTAGES OF NPV METHOD
It is difficult to estimate the expected cash flows
from a project.
Discount rate to be used is very difficult to
determine.
Since this method does not consider the life of the
projects, in case of mutually exclusive projects
with different life, the NPV rule, tends to be
biased in favour of the longer term project.
Since NPV is expressed in absolute terms rather
than relative terms it does not consider the scale
of investment.
13
BENEFIT COST RATIO
It is calculated as:
Where,
PVB = present value of benefits
I = Initial investments
14
ACCEPTANCE RULE FOR BCR
BCR = 1 = Indifferent
15
EVALUATION OF BCR METHOD
Advantages of BCR method:
16
Internal Rate of Return: IRR
0 1 2 3
17
INTERNAL RATE OF RETURN
METHOD
The internal rate of return (IRR) is the rate that
equates the investment outlay with the present
value of cash inflow received after one period. This
also implies that the rate of return is the discount
rate which makes NPV = 0.
The formula for calculating IRR is:
C1 C2 C3 Cn
C0
(1 r ) (1 r ) 2 (1 r )3 (1 r ) n
n
Ct
C0 t 1 (1 r )t
n
Ct
t 1 (1 r ) t
C0 0
18
INTERNAL RATE OF RETURN
METHOD
Where,
19
CALCULATION OF IRR
Level or even Cash Flows:
Let us assume that an investment would cost Rs
20,000 and provide annual cash inflow of Rs 5,430
for 6 years.
The IRR of the investment can be found out as
follows:
NPV Rs 20,000 + Rs 5,430(PVAF6,r ) = 0
Rs 20,000 Rs 5,430(PVAF6, r )
Rs 20,000
PVAF6, r 3.683
Rs 5,430
IRR = 16% approx.( Refer to PVAF table @ 3.685 for 6 yrs
20
NPV Profile and IRR
A B C D E F G H
1 NPV Profile
Discount
2 Cash Flow rate NPV
3 -20000 0% 12,580
IR
4 5430 5% 7,561
R
5 5430 10% 3,649
6 5430 15% 550
7 5430 16% 0
8 5430 20% (1,942)
9 5430 25% (3,974)
Figure 8.1 NPV Profile
21
CALCULATION OF IRR
Uneven or non–normal Cash Flows: Calculating
IRR by Trial and Error
The approach is to select any discount rate to
compute the present value of cash inflows. If the
calculated present value of the expected cash
inflow is lower than the present value of cash
outflows, a lower rate should be tried. On the other
hand, a higher value should be tried if the present
value of inflows is higher than the present value of
outflows. This process will be repeated unless the
net present value becomes zero.
22
CALCULATION OF IRR
A project costs Rs.16000 and is expected to generate
cash inflows of Rs. 8000, Rs.7000 & Rs.6000 at the
end of each year for next 3 years.
23
ACCEPTANCE RULE FOR IRR
Accept the project when r (IRR) > k (WACC).
Reject the project when r (IRR) < k (WACC).
May accept the project when r = k.
In case of independent projects, IRR and NPV rules
will give the same results if the firm has no shortage
of funds.
In case of projects with equal IRR & different NPV,
select project with higher NPV as it is consistent with
firm’s wealth maximisation objective.
24
ADVANTAGES OF IRR METHOD
It considers time value of money.
It is a true measure of profitability as it uses the
present values of all cash flows(both outflows &
inflows) rather than any other arbitrary assumption or
subjective consideration.
In case of conventional independent projects NPV &
IRR methods gives the same decision.
Whenever a project with higher IRR than WACC is
undertaken, it results in the increase in the
shareholder’s return. Hence, the value of the firm also
increases.
25
PROBLEMS WITH IRR
Lending & Borrowing projects: Project with initial outflow
followed by inflows is a lending type project whereas a project
with initial inflow followed by outflows is a borrowing project.
Since IRR does not differentiate between lending and
borrowing projects, a higher IRR may not always be a desirable
thing.
26
PROBLEMS WITH IRR
Different short term & Long term interest rates: Since
the cash flows are discounted at the opportunity cost
of capital, there arises a confusion regarding what
rate is to be used for discounting, if the short term
and long term lending rates are different.
27
LENDING & BROWING PROJECTS
Lending projects: Project with initial outflow
followed by inflows is a lending type project.
30
Case of Ranking Mutually Exclusive Projects
Investment projects are said to be mutually exclusive
when only one investment could be accepted and
others would have to be excluded.
Two independent projects may also be mutually
exclusive if a financial constraint is imposed.
The NPV and IRR rules give conflicting ranking to the
projects under the following conditions:
The cash flow pattern of the projects may differ.
That is, the cash flows of one project may increase
over time, while those of others may decrease or
vice-versa.
The cash outlays of the projects may differ.
The projects may have different expected lives.
31
RANKING MUTUALLY EXCLUSIVE PROJECTS
(Timing of Cash Flows)
Cash Flows (Rs) NPV
Project C0 C1 C2 C3 at 9% IRR
M – 1,680 1,400 700 140 301 23%
N – 1,680 140 840 1,510 321 17%
-400
Discount Rate
34
RANKING MUTUALLY EXCLUSIVE PROJECTS
(Project Life Span)
Cash Flows (Rs)
Project C0 C1 C2 C3 C4 C5 NPV at 10% IRR
35
Modified Internal Rate of Return
(MIRR)
The modified internal rate of return (MIRR) is
the compound average annual rate that is calculated
with a reinvestment rate different than the project’s
IRR.
Both NPV & IRR methods assume that the entire
cash flow generated during the life time of the
project is reinvested at project cost of capital (i.e k)
& internal rate of return (i.e r) respectively in each of
the above two methods.
But, in MIRR the cashflows are assumed to be
reinvested at cost of capital ( k) instead of internal
rate of return ( r )as in IRR method. 36
PAY BACK PERIOD
It is the number of years required to recover a
project’s cost, or how long does it take to get the
business’s money back?
37
PAY BACK PERIOD
0 1 2 2.4 3
CF -100 10 60 100 80
Cumulative -100 -90 -30 0 50
38
PAY BACK PERIOD
Strengths of Payback:
Weaknesses of Payback:
CFt -100 10 60 80
Discounted
payback = 2 + 41.32/60.11 = 2.7 yrs
40
ACCOUNTING RATE OF RETURN
The accounting rate of return is the ratio of the
average after-tax profit divided by the average
investment.
41
ACCEPTANCE RULE OF ARR
This method will accept all those projects whose ARR
is higher than the minimum rate established by the
management and reject those projects which have
ARR less than the minimum rate.
42
ACCOUNTING RATE OF RETURN
43
ACCOUNTING RATE OF RETURN
The disadvantages of ARR include: