The document summarizes 12 case studies related to construction contract claims and disputes. Some key points covered in the case studies include: defective workmanship is not a material breach unless the contractor fails to correct it after notice; a contractor can be held liable for safety issues if the contract incorporates a safety manual; owners waive the right to claim defects that were apparent prior to final acceptance; ambiguous contract clauses are interpreted against the drafter; and contractors must be given a reasonable opportunity to address workmanship issues before an owner can claim breach of contract.
The document summarizes 12 case studies related to construction contract claims and disputes. Some key points covered in the case studies include: defective workmanship is not a material breach unless the contractor fails to correct it after notice; a contractor can be held liable for safety issues if the contract incorporates a safety manual; owners waive the right to claim defects that were apparent prior to final acceptance; ambiguous contract clauses are interpreted against the drafter; and contractors must be given a reasonable opportunity to address workmanship issues before an owner can claim breach of contract.
The document summarizes 12 case studies related to construction contract claims and disputes. Some key points covered in the case studies include: defective workmanship is not a material breach unless the contractor fails to correct it after notice; a contractor can be held liable for safety issues if the contract incorporates a safety manual; owners waive the right to claim defects that were apparent prior to final acceptance; ambiguous contract clauses are interpreted against the drafter; and contractors must be given a reasonable opportunity to address workmanship issues before an owner can claim breach of contract.
of Contractor’s workmanship. Owner took the position that the poor workmanship was a material breach of contract which justified a change in the payment terms of the contract. • The Court of Appeals of Indiana disagreed. Given the complexity of a construction project, it would be unfair to treat every workmanship as a material breach of contract. Contractor was entitled to notice of the problem and a reasonable opportunity to correct it. • Defective workmanship is an immaterial breach of contract unless and until Contractor fails to correct the problem after a reasonable opportunity to do so. At that point it becomes a material breach of contract. Case Study 2
Owner awarded Contractor a contract for
construction of an apartment building. The contract stated that Contractor would comply with the provisions of the “Manual of Accident Prevention in Construction” of the Associated General Contractors of America (AGC). An employee of a subcontractor was injured when he fell from an upper floor. Contractor said it was not responsible for the safety of subcontractor’s employees. The Court of Appeals of Iowa ruled that the AGC manual had been incorporated by reference into Contractor’s agreement. The manual gave Contractor overall responsibility for job site safety and required Contractor to erect and maintain proper barricades. Contractor had failed to do this, so Contractor was liable for the injury. Case Study 3
Owner’s on-site representative inspected
Contractor’s installation of a roof. Contractor’s work was later accepted and final payment was made. After final acceptance and payment, Owner sued contractor for defective workmanship in the roof installation. Contractor responded that Owner’s claim had been waived by final acceptance. The California Court of Appeal agreed. The Court said that Owner’s on-site representative knew or should have known of the defects prior to final acceptance. The knowledge of Owner’s agent is imputed to Owner. Therefore, Owner accepted the project with imputed knowledge of patent, or apparent, defects and thereby waived the right to bring a claim against Contractor for those defects. Case Study 4 Contractor awarded subcontract using Contractor’s standard, preprinted subcontract form. Subcontract stated that payment to Subcontractor would be due 10 days after Contractor received payment from owner. Owner didn’t pay Contractor, so Contractor refused to pay Subcontractor. Subcontractor argued that clause in subcontract was intended only to give Contractor a reasonable time to make payment, not to excuse payment altogether if Contractor didn’t get paid by Owner. The Court of Appeal of Louisiana ruled that the intended meaning of the payment clause was ambiguous. The preprinted subcontract form had obviously been drafted by Contractor. Therefore, the clause was construed against Contractor and Subcontractor’s interpretation prevailed. Case Study 5
Owner awarded Contractor a lump-sum
construction contract. Contract called for Owner to make a monthly progress payments to Contractor based on Architect’s certification of Contractor’s percentage of completion. Architect certified a particular percentage of completion, but Owner refused to make a progress payment for that amount unless certain changes were made in the terms of contract. Contractor sued Owner for breach of contract. The Missouri Court of Appeals ruled that Owner did breach the contract. When a contract establishes Architect as the party responsible for determining Contractor percentage of completion, that determination is binding on both Owner and Architect. Owner was not entitled to ignore Architect’s certification or to impose additional preconditions before making the progress payment. Case Study 6 Owner awarded Contractor a contract for construction of bridges over a canal. Contract included construction of concrete barrier rail at a unit price of $42 or linear foot. Rather than using fixed forms, as Owner expected, Contractor used slip forms to build the barrier rail. Owner claimed it was entitled to a price reduction, because the use of slip forms save Contractor a great deal of money. The Court of Appeals of North Carolina ruled that the Owner had no right to take a credit. The contract simply referred to the use of “forms”. When a contract does not specify a particular method of performance, the contractor is free to choose any method as long as it achieves compliance with the specifications. If the contractors complies with the specifications, the owner cannot treat the contractor’s method of performance as a deductive change in the work. Case Study 7
Owner awarded highway construction
contract to Contractor. Owner made irregular progress payments, violating the terms of the contract. Contractor experienced severe cash-flow problems and went out of business. Contractor sued Owner for the destruction of the business. The Commonwealth Court of Pennsylvania denied the claim, saying that the destruction of an entire business is simply not a foreseeable result of the failure to make timely progress payments. Therefore, these were not recoverable consequential damages. Case Study 8
Owner rejected completed industrial
building because the metal siding had an uneven finish when view from an angle in strong sunlight. Owner relied on contract clause giving its architect the final decision regarding “artistic effect”. In response to Contractor’s suit, the U.S. Court of Appeals ruled that Owner was not entitled to reject the building on these grounds. The court said that aesthetic factors must be considered in a reasonable commercial context. The building was intended as a functional, industrial facility, not a thing of beauty. When considered in that context, Owner’s rejection due to an uneven finish was unreasonable. Case Study 9
Contractor awarded subcontract calling for
monthly progress payments. Contractor then refused to pay Subcontractor until Subcontractor’s work was complete.
Subcontractor refused to perform any more
work on the grounds that was not being paid. Contractor claimed the refusal to work was a breach of the subcontract. • The Appellate Court of Connecticut ruled that the Contractor’s failure to make progress payments was a material breach of the subcontract, as payment was fundamental to the purpose of the agreement. • Contractor material breach justified Subcontractor’s refusal to perform. Subcontractor was not liable for breach of the subcontract. Case Study 10
• Contract for construction of
condominium project included clause requiring prior written authorization from the project owner before the contractor performed any extra work. • Owing to errors in Owner’s plans, it was necessary for Contractor to make changes in the roof and trusses. • Owner’s superintendent orally directed Contractor to proceed and assured Contractor that the extra work will be paid for. No written change order was issued, however. • When Contractor sought to recover payment for the extra work, Owner argued that it was not obligated to pay in absence of a written change order. The Supreme Court of Nevada disagreed. By issuing an oral directive and standing by while Contractor followed that directive, Owner waived the contract requirement that all changes be authorized in writing in advance. Case Study 11 • Contractor completed a project. Owner inspected and accepted the project and made final payment to Contractor. • Contractor then brought a claim against Owner for additional compensation due to unforeseen site conditions encountered during construction. Owner responded that under the terms of the contract, acceptance of final payment operated as a waiver and release by Contractor of any claim relating to the contract. The Court of Appeals of Ohio agreed with Owner. The contract made it clear that acceptance of final payment precluded Contractor from asserting any new claims. The clause, which is quite standard, is enforceable. Once Contractor accepted final payment, it could not claim any additional compensation. Case Study 12
• Contract contained an express warranty
of the Contractor’s materials and workmanship. Owner informed Contractor that it was dissatisfied with the quality of Contractor’s work and would be forced to withhold future progress payments. • Contractor treated this as a breach of contract and walked off the job. Owner argued that Contractor breached the contract first by breaching the express warranty of the workmanship. The Court of Appeals of Indiana ruled that Owner breached the contract. Before a workmanship warranty problem becomes a material breach of contract, the contractor must be given a reasonable opportunity to correct the problem. Owner never gave Contractor that opportunity. Therefore, Owner was not justified in unilaterally changing payment terms of the contract. Owner, rather than Contractor, breached the contract.