Professional Documents
Culture Documents
& Budgeting
Lecture 6
2
Project Schedule
The Project Schedule is a description (often a picture/gantt) of the
sequence of activities and tasks that must be undertaken to produce
the project outputs.
3
Project Schedule
The schedule provides a day to day control mechanism for Project
Managers, a detailed work plan for team members and feeds into the
reporting framework feeding up to higher level control.
Scheduling involves specifying:
The tasks - you need to do in order to produce your products
When you will do it – the duration required for the tasks and their
relationship with each other
Who will do it – the resources required to undertake the tasks.
The schedule should detail tasks, timeframes and resources.
4
Scheduling Activities
Task Definition
Task Sequencing
Schedule Development
Schedule Control
5
Understanding Tasks
Tasks are defined as the activities required to undertake and complete your
project.
The planning of tasks is critical as they form the steps that make up your project.
If you omit one of these tasks it won't be scheduled, possibly invalidating your
whole project.
Determining the tasks is usually best done in combination with other project
members. It can take the form of brainstorming to work out the steps needed to
complete the project.
Once the ideas have been jotted down they can be refined until everyone is
satisfied that the necessary tasks and their order has been correctly worked out.
Utilise your WBS, identify the tasks required to complete each deliverable.
7
The next step is to develop the activity sequence & identify linked
tasks
The linking of tasks creates task dependencies.
Ask yourself:
Task Dependencies
When you first identify tasks they are not linked in any way.
In the real world tasks are inter-dependent, and most tasks in
your project will relate to one another in some way.
Example:
Make A Birthday Cake
Make Icing
9
10
Types of Relationships
Finish to Start (FS) – One task must finish before a dependent task can start.
Example:
Mix Ingredients Bake Cake
Start to Start (SS) One task must start before a dependent task can start
Mix Ingredients
Types of Relationships
Start to Finish (SF) A task must start prior to its dependent task
being completed
Heating Oven
Mixing
Ingredients
12
Types of Relationships
Lag vs Lead
Lag: a deliberate gap or pause between tasks e.g.
One hour lag: Time to Cool
Make Icing
13
Summary Tasks
Resource Estimating
Duration Estimating
Duration Estimating
17
Estimations
Cost estimates are a ‘guess’ but they should be best guesses. You have
information to help make them as close to reality as possible.
18
PERT Estimating
o + 4e + p
Estimate =
6
Example: Attendees at Christmas party
o = optimistic or best case
e = 150 attendees
e = expected or likely case
p = 25 (last year party was boring, no food or drinks
p = pessimistic or worst case provided free, venue too far away, hungover from other
Christmas parties,)
o = 230 (food and drink provided free, last year was great,
great venue, social club is very active)
Estimate =
230 + 600 + 25
4(150)
855 + 25
6
Estimate = 143 attendees
19
Schedule Development
• Vacation times
Schedule Development
Milestone Development
Milestones
Must be SMART
Regularly spaced
Critical Path
Task B
7 days
Task A Task E
2 days 2 days
Task C Task D
2 days 3 days
Reducing the Critical Path
Eliminate tasks on the Critical Path
Convert serial paths to parallel when possible
Overlap sequential tasks
Shorten the duration on critical path tasks
Shorten:
− early tasks
− longest tasks
− easiest tasks
− tasks that cost the least to speed up
09-24
Crashing
10-25
Project Activities: Budget v Crashed Costs
Activity Normal Crashed Difference
Duration Cost Duration Cost Days Cost
A 5 days 1,000 3 days 1,500 -2 +500
B 7 days 700 6 days 1,000 -1 +300
C 3 days 2,500 2 days 4,000 -1 +1,500
D 5 days 1,500 5 days 1,500 0 0
E 9 days 3,750 6 days 9,000 -3 +5,250
F 4 days 1,600 3 days 2,500 -1 +900
G 6 days 2,400 4 days 3,000 -2 +600
H 8 days 9,000 5 days 15,000 -3 +6,000
Totals: $22,450 34 $37,500 -13 $15,050
10-26
Copyright © 2013 Pearson Education Table 10.1
Managerial Considerations
Determine fixed and variable costs for each activity
The crash point is the fully expedited activity
Optimize time-cost tradeoffs
Shorten activities on the critical path
Cease crashing when either one of the following occurs:
− the target completion time is reached
− the crashing cost exceeds the penalty cost
10-27
28
Project Contingency
The grey bars depict the planned baseline, the blue/red bars show ‘actual’ and
schedule work. Note the ‘slippage’
30
Cost Management
Why do we need a budget?
To provide an estimate of size (a ‘straw man’)
To provide context to sponsors and stakeholders and manage expectations
To obtain funds to invest in the deliverables
To be able to rank competing projects
− Assess cost versus benefit
− To choose the best investment
− This is the economist’s concept of ‘opportunity cost’
So that there are no surprises
The budget validates the schedule, and vice versa, as you account for time and
resource-cost
To provide a ‘baseline’ for monitoring and communicating progress
The project budget is a plan that identifies the allocated resources, the
project’s goals and the timeline. Typically it involves one of three
approaches:
Top-Down budgeting uses the opinions and experiences of top
management regarding estimated project costs as a start point and
passes these down the hierarchy adding more information as it goes
until costs are reflected at a task-by-task basis.
Bottom-Up budgeting begins with the Work Breakdown Structure and
aggregates costs at the deliverable level and then at the whole-of-
project level.
Activity-based costing assigns costs first to activities and then to the
project’s use of resources
8-
34
Contingency funding
Project contingency is the allocation of extra funds to cover uncertainties and
improve the chance of finishing on time; Task Contingency at a work package
level, Managerial Contingency at a whole-of-project level and Insurance e.g.
for construction projects. It offers three benefits:
1. Recognises the future contains unknowns
2. Adds provision for company plans for an increase in project cost
3. Applies contingency fund as an early warning signal to potential
overdrawn budget
8-
36
Reference
Horine, G.M. (2005). Absolute beginner’s guide to project management. Indianapolis, IN: Que Publishing.
Once you have a budget and have used the baseline schedule to create
a phased budget (a cashflow plan):
You need to ensure that you have access to sufficient funds at the
right time to keep the project financially afloat (liaise with sponsor)
As project manager you must ensure that you can meet your
financial commitments
Continual re-forecasting and performance measurement help you
to control costs
Budget by Resources
Budget By Resources
INCOME
Attendence Fees 2000
TOTAL INCOME 2000
EXPENSES
Labour
Speaker 1 1000
Speaker 2 1000
Caterers
Waiters 180
Chef 180
Kitchen Hands 360
Total Labour Cost 2720
Resources
Food 200
Facilities
Venue Hire 500
Disbursements
Photocopying 50
Accomodation and Meals 250
Total Disbursements 300
2000
Assumptions
One handout per person
Venue hire includes cleaning and setup
46
Cash Flow
Mar Apr May
Opening Balance 0 -200 -970
INCOME
Attendence Fees 2000
EXPENSES
Labour
Speaker 1 1000
Speaker 2 1000
Caterers
Waiters 180
Chef 180
Kitchen Hands 360
Resources
Food 200
Facilities
Venue Hire 500
Disbursements
Photocopying 50
Accomodation and Meals 250
Cost/Benefit Analysis
Cost/Benefit Analysis
Costs Benefits
Labour Costs 2720 Attendence Fees 2,000
Resources 200
Facilities 500
Disbursements 300