Professional Documents
Culture Documents
CONSTRUCTION MANAGEMENT
Michelle G. Galarion
INTRODUCTION
A critical element of a successful cost control is timely and accurate payments to the contractor for
the completed contract work and completed change order work.
Monthly progress payments to the contractor throughout the construction period shall be
administered in accordance with the contract documents.
PROBLEMS DURING
CONSTRUCTION
Construction is a dusty, dirty and multi-faceted operation. Material is delivered daily at the same time
that hundreds of works must come together to complete their assignments. As construction proceeds,
the site becomes congested.
Despite the fact that the estimate and plans were made with a large factor of safety in each and every
task, many activities consume more than their estimated time and cost. This is because trades tend to
delay their start to the last minute, thus wasting float time. (THIS IS ALSO CALLED THE
STUDENT SYNDROME.)
In the midst of the work, some trades proceed slower than desired whereas others proceed faster than
desired, and in both cases, delays occur.
Applied to activities that involve repeated production of easily measured units of work
For example, total volume of concrete poured or total number of windows installed
Completed means installed. There are a few instances that the owner or the construction manager
may consider to include delivered (not yet installed) items as a part of accomplishment.
MEASURING WORK PROGRESS
INCREMENTAL MILESTONE
Applies to activities that are budgeted based on a bulk allocation of money and involve a long
time or are continuous during the life of a project
Applies to activities that are composed of two or more overlapping subtasks, each with a different
unit of work measurement
These are used in computing for the overall accomplishment of a certain project
All elements are converted into an equivalent amount of a unified measurement unit.
S-CURVES
COST CONTROL
S-CURVES
• Graphical tool which displays the cumulative progress of a project
• A tool which construction companies use to track a project’s accomplishment to make
sure that what is being done is according to what was planned
• It is called an “S-curve” because the shape generated typically resembles the letter S.
Because projects are usually ”slow to start”, ramps up with all types of activity during
the middle part of the whole duration and slows down towards the end.
• This is plotted on top of a bar chart to particularly show a project’s accomplishment
over time
This is an example of an S-curve
The first column contains the scopes of work of the project with their corresponding amounts.
The third column contains the weight of each scope of work with respect to the totality of the project. Its sum should be
equivalent to 100%.
How is this computed? Amount per line item (per scope of work) is divided by the total amount.
𝑃h𝑝 600,000.00
𝑃h𝑝 24,800,000.00
How are the bar charts being done?
All stakeholders must be consulted first in order to properly schedule each of the scopes of work.
It is important that the planner knows how to project the accomplishment per month.
General Requirements:
For discussion purposes only,
we can ASSUME that an equal
Month 1: 2.42% / 8 = 0.3025%
amount of accomplishment can
Month 2: 2.42% / 8 = 0.3025%
be targeted each month.
Month 3: 2.42% / 8 = 0.3025%
Month 4: 2.42% / 8 = 0.3025%
Month 5: 2.42% / 8 = 0.3025%
Month 6: 2.42% / 8 = 0.3025%
Month 7: 2.42% / 8 = 0.3025%
Month 8: 2.42% / 8 = 0.3025%
Let’s take a look at the “General Requirements” that will run from the first month to the last month.
It is important that the planner knows how to project the accomplishment per month.
Again, for discussion purposes only, we can ASSUME that an equal amount of accomplishment can be targeted for
each month.
Again, for discussion purposes only, we can ASSUME that an equal amount of accomplishment can be targeted for
each month.
Again, for discussion purposes only, we can ASSUME that an equal amount of accomplishment can be targeted for
each month.
These are the just the sum of all the accomplishments per month.
Aside from its purpose as a cost and schedule control, it serves as a basis for the progress payments of the
contractor. It usually forms part of the billing submitted by the contractor to the owner to collect payment.
There are no standard formats for the accomplishment reports. It usually depends on the owner, construction
manager or the contractor.
Shown below is an example of an accomplishment report.
Assumptions:
1. This accomplishment report is generated for the contractor’s second quarter billing.
2. The contractor was paid already for the first quarter accomplishment.
The accomplishment to date is the sum of the previous and present accomplishment.
The first three columns were already discussed in slides 14 and 15.
The percentage per scope are based on on-site accomplishment or installed items. Unless stated in the contract,
delivered items cannot be considered as an accomplishment.
The percentage accomplishment per scope was already discussed in slides 6 to 10. In this example, only a summary
of the scopes of work were shown. The subtasks should be assessed per line item of work.
For example, in Item III (Elevator Shear Wall), it is composed of the following scopes of work:
1. Structural works
2. Waterproofing works
3. Painting works
These scopes of work are needed to be evaluated one by one to get their line item accomplishment and the total
project accomplishment
The weights are computed simply by multiplying the % scope and the % weight of the scope of work.
Continue computing the weighted accomplishments for all the scopes of work to get the overall accomplishment
The accomplishment to date is the sum of the previous and the present accomplishments.
Continue computing the weighted accomplishments for all the scopes of work to get the overall accomplishment