Professional Documents
Culture Documents
PROJECT MANAGEMENT
1
Index
1. DEFINITION
2. RISKS ELEMENTS IN PROJECT MANAGEMENT
3. THE PROCESS OF PROJECT RISK MANAGEMENT
4. RISK CONTINGENCY RESERVE
5. COMMUNICATING PROJECT RISKS
6. CONCLUSION
2
5. RISK
uncert
2. RISK ELEMENTS 3. PROCESS OF 5. RISK
ain
An
CONTINGENCY
1. DEFINITION IN PROJECT PROJECT RISK CONTINGENCY 7. CONCLUSION
MANAGEMENT MANAGEMENT RESERVE RESERVE
DEFINITION
RISK MANAGEMENT IN PROJECT MANAGEMENT
A process used by project managers to minimize any potential problems that may negatively impact
a project’s timetable.
Because of this uncertainty, project risk requires serious preparation in order to manage them
efficiently.
3
5. RISK
uncert
2. RISK ELEMENTS 3. PROCESS OF 5. RISK
ain
An
6. CONTINGENCY
COMMUNICATING
1. DEFINITION IN PROJECT PROJECT RISK CONTINGENCY PROJECT RISK
7. CONCLUSION
MANAGEMENT MANAGEMENT RESERVE
RESERVE
DEFINITION
RISK
Any unexpected event that might affect the people, processes, technology and resources involved in a
project.
In other words :Events that could occur and you may not be able to tell when.
ISSUE ≠ RISK
Issues are the things you know you’ll have to deal with. Risk is an event that has not happened yet but
there is a likelihood that it may happen in future, where as an issue is an event that has already
happened. 4
uncert
2. RISK ELEMENTS 3. PROCESS OF 5. RISK
2. RISK ELEMENTS IN RISK
ain
1.DEFINITION
DEFINITION
An
6. COMMUNICATING
7. CONCLUSION
1. IN PROJECT PROJECT
PROJECT MANAGEMENT 3.DEFINITION
CONTINGENCY 4.DEFINITION
PROJECT RISK 5. DEFINITION
MANAGEMENT MANAGEMENT RESERVE
RESOURCES PEOPLE
TECHNOLOGY PROCESSES
5
5. RISK
uncert
2. RISK ELEMENTS 3. PROCESS OF 6. COMMUNICATING
2. RISK ELEMENTS IN RISK
ain
1.DEFINITION
DEFINITION
An
1. IN PROJECT PROJECT
PROJECT MANAGEMENT
CONTINGENCY
3.DEFINITION
RESERVE
4.DEFINITION
PROJECT RISK 5. DEFINITION
7. CONCLUSION
MANAGEMENT MANAGEMENT
• Usually a risk is seen as a bad thing, something that will always have a negative impact. However,
the Project Management Body of Knowledge Guide treats risk as an uncertainty that may have a
positive or negative impact.
• The risks that produce negative outcomes are called “threats,” and risks that produce positive
outcomes are called “opportunities.”
• Example: A project management team controls the risk that a project will go over budget and the
positive risk that the project will be under budget. Being under budget is a good thing because
the company saves money. However, in the context of project management it's considered a
planning error. You didn't really save money — the project manager overestimated the project.
In other words, under budget projects are something project managers try to avoid. However,
when it happens it's an opportunity to reallocate resources.
• Identifying the two types of risks allows project managers and teams to not let opportunities
pass by while managing threats.
6
5. RISK
uncert
2. RISK ELEMENTS 3. PROCESS OF 5. RISK
2. RISK ELEMENTS IN
ain
1.DEFINITION
DEFINITION
An
6. CONTINGENCY
COMMUNICATING
7. CONCLUSION
1. IN PROJECT PROJECT RISK
PROJECT MANAGEMENT 3.DEFINITION
CONTINGENCY 4.DEFINITION
PROJECT
RESERVERISK 5. DEFINITION
MANAGEMENT MANAGEMENT RESERVE
PROJECT
MANAGEMENT
RISK ELEMENTS
Risk Time Frame
Impact -when is
-when is itit likely
likely to
to happen
happen
-what’s the
-what’s the expected
expected outcome
outcome
Probability
-what are
-what are chances
chances of
of itit happening
happening
7
uncert
2. RISK ELEMENTS 3. PROCESS OF 5. RISK
ain
An
6. COMMUNICATING 7. CONCLUSION
1. DEFINITION IN PROJECT PROJECT RISK CONTINGENCY PROJECT RISK
MANAGEMENT MANAGEMENT RESERVE
• Practice Standard for Project Risk describes a six-step process to effectively manage project
risks.
• Flow chart shows the entire process along with relationships and dependencies among the
six steps.
• The process starts with developing the risk management plan, followed by identifying risks,
performing qualitative analysis, performing quantitative analysis if required, and planning
8
risk responses.
uncert
2. RISK ELEMENTS 3. PROCESS OF 5. RISK
2. RISK ELEMENTS IN 6. COMMUNICATING
7. CONCLUSION
ain
1.DEFINITION
DEFINITION
An
1. IN PROJECT PROJECT RISK
PROJECT MANAGEMENT 3.DEFINITION
CONTINGENCY 4.DEFINITION
PROJECT RISK 5. DEFINITION
MANAGEMENT MANAGEMENT RESERVE
9
4. TOOLS FOR 5. RISK
uncert
2. RISK ELEMENTS 3. PROCESS OF 6. COMMUNICATING
ain
An
1. DEFINITION IN PROJECT PROJECT RISK PROJECT RISK CONTINGENCY 7. CONCLUSION
RESERVE PROJECT RISK
MANAGEMENT MANAGEMENT MANAGEMENT
ain
An
1. DEFINITION IN PROJECT PROJECT RISK CONTINGENCY 7. CONCLUSION
PROJECT RISK
MANAGEMENT MANAGEMENT RESERVE
• The probability-impact Matrix (P-I matrix) is created and risk thresholds are decided,
which will be used in the later steps to prioritize risks.
• The risk management-related roles and responsibilities are also decided and documented
in the risk management plan.
• The risk management plan is an important document because it is used as a guide to
carry out risk management activities throughout the life of the project.
11
12
4. TOOLS FOR 5. RISK
uncert
2. RISK ELEMENTS 3. PROCESS OF 6. COMMUNICATING
ain
An
1. DEFINITION IN PROJECT PROJECT RISK PROJECT RISK CONTINGENCY 7. CONCLUSION
RESERVE PROJECT RISK
MANAGEMENT MANAGEMENT MANAGEMENT
uncert
2. RISK ELEMENTS 3. PROCESS OF 6. COMMUNICATING
ain
An
1. DEFINITION IN PROJECT PROJECT RISK CONTINGENCY 7. CONCLUSION
RESERVE PROJECT RISK
MANAGEMENT MANAGEMENT
uncert
2. RISK ELEMENTS 3. PROCESS OF 6. COMMUNICATING
ain
An
1. DEFINITION IN PROJECT PROJECT RISK PROJECT RISK CONTINGENCY 7. CONCLUSION
RESERVE PROJECT RISK
MANAGEMENT MANAGEMENT MANAGEMENT
15
4. TOOLS FOR 5. RISK
uncert
2. RISK ELEMENTS 3. PROCESS OF 6. COMMUNICATING
ain
An
1. DEFINITION IN PROJECT PROJECT RISK PROJECT RISK CONTINGENCY 7. CONCLUSION
RESERVE PROJECT RISK
MANAGEMENT MANAGEMENT MANAGEMENT
16
4. TOOLS FOR 5. RISK
uncert
2. RISK ELEMENTS 3. PROCESS OF 6. COMMUNICATING
ain
An
1. DEFINITION IN PROJECT PROJECT RISK PROJECT RISK CONTINGENCY 7. CONCLUSION
RESERVE PROJECT RISK
MANAGEMENT MANAGEMENT MANAGEMENT
17
4. TOOLS FOR 5. RISK
uncert
2. RISK ELEMENTS 3. PROCESS OF 6. COMMUNICATING
ain
An
1. DEFINITION IN PROJECT PROJECT RISK PROJECT RISK CONTINGENCY 7. CONCLUSION
RESERVE PROJECT RISK
MANAGEMENT MANAGEMENT MANAGEMENT
18
4. TOOLS FOR 5. RISK
uncert
2. RISK ELEMENTS 3. PROCESS OF 6. COMMUNICATING
ain
An
1. DEFINITION IN PROJECT PROJECT RISK PROJECT RISK CONTINGENCY 7. CONCLUSION
RESERVE PROJECT RISK
MANAGEMENT MANAGEMENT MANAGEMENT
19
Risk Register
20
21
4. RISK 5. RISK
uncert
2. RISK ELEMENTS 3. PROCESS OF
ain
An
1. DEFINITION IN PROJECT PROJECT RISK CONTINGENCY CONTINGENCY 7. CONCLUSION
MANAGEMENT MANAGEMENT RESERVE
RESERVE
22
Developing Risk Reserve
• It is important to develop risk reserve and apply it carefully to a refined schedule and cost to
achieve greater predictability in meeting project deadlines and/or staying within the budgeted
cost. At the same time, it is very difficult to accurately determine the probability and impact for
each of the risks. This exercise requires an enormous amount of time to be executed properly.
Some form of quantitative analysis is required before an estimate of risk reserve can be
determined.
• For most business/commercial projects where the impact is mainly monetary, an 80/20 rule-
based approach can be implemented. This approach may need about 20 percent of the effort to
achieve about 80 percent of the result or about 80 percent accuracy, which may be good enough
for a commercial project. Much more sophisticated and costly techniques may be needed for
better accuracy for other types of projects where a lot more could be at stake (such as
environment, culture, animals, or human life).
• For most commercial projects, the EMV technique is the most cost effective and easy to
implement to determine an estimate for risk reserve that is almost 80 percent accurate. The first
step would be to estimate the probability and impact for each of the risks using “expert
judgment” or the Delphi technique. This should be done after taking into account the risk
response plan, which may have a significant impact on these numbers. The total project EMV is
simply the sum of the individual EMVs. The total project EMV is then used as the estimate for the
risk reserve needed for the project.
23
Using Risk Reserve
• Like other contingency reserves, risk reserve can be used when a risk event occurs. Normally
once the risk reserve has been approved, a project manager is authorized to use the risk reserve.
• In case of a schedule reserve, the project manager will update the schedule and re-baseline it.
• Since a part of the total risk reserve has been used to deal with the impact caused by a particular
risk event, the total risk reserve is reduced by that amount. This process is followed every time a
risk event occurred.
• It is interesting to note that total risk reserve was based on impact multiplied by probability, but
when risk occurs, it may use 100 percent of the impact amount, not what was calculated by
multiplying it by probability. For example if a risk event has a probability of 30 percent and an
impact of 10 days schedule delay, the EMV for this risk event will be 3 days, which goes as part of
developing the total risk reserve (not 10 days).
• If this risk event occurred, the schedule may have to be delayed by 10 days (not 3 days), and total
risk reserve reduced by 10 days to arrive at remaining risk reserve for the rest of the risks.
• At the surface level, it seems like a problem, but in the real world, it is not. If there were 10 risks
that were used to create the total risk reserve, it is highly unlikely that all 10 will occur. The
portion of risk reserve for non-occurring risks will generally cover the impact for the risks that
occur.
24
4. RISK
uncert
2. RISK ELEMENTS 3. PROCESS OF 5. COMMUNICATING
ain
An
1. DEFINITION IN PROJECT PROJECT RISK CONTINGENCY PROJECT RISK 7. CONCLUSION
MANAGEMENT MANAGEMENT RESERVE
Who ? How ?
What ? When ?
25
4. RISK
uncert
2. RISK ELEMENTS 3. PROCESS OF 5. COMMUNICATING 6. COMMUNICATING
ain
An
1. DEFINITION IN PROJECT PROJECT RISK CONTINGENCY PROJECT RISK PROJECT RISK 7. CONCLUSION
MANAGEMENT MANAGEMENT RESERVE
• It is important that everyone be informed about project risks on a regular basis. The
frequency and level of detail may depend on the nature of the risk, its impact, and the
role that a person or group is playing on the project.
• The communication plan developed during the planning process should clearly identify
all stakeholders who should receive risk communication, and the content and frequency
of communication.
• Normally, project managers have the primary responsibility of communicating risks and
all information related to risks to all the stakeholders.
26
4. RISK
uncert
2. RISK ELEMENTS 3. PROCESS OF 5. COMMUNICATING 6. COMMUNICATING
ain
An
1. DEFINITION IN PROJECT PROJECT RISK CONTINGENCY PROJECT RISK PROJECT RISK 7. CONCLUSION
MANAGEMENT MANAGEMENT RESERVE
At minimum, the status of all risks should be communicated to all stakeholders. For every
risk, the current status should include
a) timeframe of occurrence;
b) probability of occurrence;
c) the impact if the risk does occur;
d) the response plan to manage the risk if it does occur.
In addition, the remaining risk reserve, need for additional risk reserve (if any) and current baselines for
schedule and cost may be very valuable information for the sponsors or stakeholders who approve the budget.
The status and additional risk information should be communicated on a regular basis.
The frequency of communication will depend on the nature and size of the project. For projects that are
small but critical, a weekly risk update may be needed. For projects extending beyond six months, a monthly
risk update may be sufficient. The project manager and stakeholders should make this decision and the project
manager should document it in the communication plan.
27
4. RISK
uncert
2. RISK ELEMENTS 3. PROCESS OF 5. COMMUNICATING 6. COMMUNICATING
ain
An
1. DEFINITION IN PROJECT PROJECT RISK CONTINGENCY PROJECT RISK PROJECT RISK 7. CONCLUSION
MANAGEMENT MANAGEMENT RESERVE
• Graphs and charts are the best ways to communicate project risk information.
• In addition, the risk register maintained in a spreadsheet and the current version
of schedule in MS Project format may be more than sufficient for the purpose.
28
4. RISK
uncert
2. RISK ELEMENTS 3. PROCESS OF 5. COMMUNICATING 6. COMMUNICATING
ain
An
1. DEFINITION IN PROJECT PROJECT RISK CONTINGENCY PROJECT RISK PROJECT RISK 7. CONCLUSION
MANAGEMENT MANAGEMENT RESERVE
uncert
2. RISK ELEMENTS 3. PROCESS OF 5. COMMUNICATING 6. COMMUNICATING
ain
An
1. DEFINITION IN PROJECT PROJECT RISK CONTINGENCY PROJECT RISK PROJECT RISK 7. CONCLUSION
MANAGEMENT MANAGEMENT RESERVE
• This type of graph is very helpful for sponsors and senior executives to
understand the risk impact and its behavior over time.
• As the project progresses if the two lines show a downward trend that would be
an indication the project risks are being managed effectively and project is likely
to meet milestones of time and cost.
• If the two lines, especially the blue total EMV line, show unstable trends with
several ups and downs or an upward trend, it would indicate ineffective risk
management, which may lead to the project getting off the rails at some point of
time.
• The power of the graph lies in the advance warnings that it provides about
possible delays, overruns, and failures.
30
4. RISK
uncert
2. RISK ELEMENTS 3. PROCESS OF 5. COMMUNICATING
ain
An
1. DEFINITION IN PROJECT PROJECT RISK CONTINGENCY PROJECT RISK 7. CONCLUSION
MANAGEMENT MANAGEMENT RESERVE
CONCLUSION
• Project risk management is one of the tools in a project manager's toolkit.
• A project manager can utilize this tool to improve the predictability of completing the
project on time and within budget.
• This predictability will help project managers develop stronger relationships with
sponsors, stakeholders, and team members as he or she regularly communicates risks
information using graphs and charts, a language well understood by senior management
or executives in a company.
31