Professional Documents
Culture Documents
Chapter 16
Given
Giventhe
theproduct
productstructure
structuretree
treefor
for“A”
“A”and
andthe
thelead
leadtime
timeand
and
demand
demandinformation
informationbelow,
below,provide
provideaamaterials
materialsrequirements
requirements
plan
planthat
thatdefines
definesthe
thenumber
numberof ofunits
unitsof
ofeach
eachcomponent
componentandand
when
whenthey
theywill
willbe
beneeded
needed
Product Structure Tree for Assembly A Lead Times
A 1 day
A B 2 days
C 1 day
D 3 days
E 4 days
B(4) C(2) F 1 day
First,
First, the
the number
number of of units
units of
of “A”
“A” are
are scheduled
scheduled
backwards
backwards to to allow
allow for
for their
their lead
lead time.
time. So,
So, in
in the
the
materials
materials requirement
requirement plan plan below,
below, wewe have
have to
to place
place
an
an order
order forfor 50
50 units
units of
of “A”
“A” on
on the
the 99th day
th
day to
to receive
receive
them
them onon day
day 10.
10.
Day: 1 2 3 4 5 6 7 8 9 10
A Required 50
Order Placement 50
LT = 1 day
18-6
Next,
Next,we
weneed
needto
tostart
startscheduling
schedulingthe
thecomponents
componentsthat
thatmake
makeupup
“A”.
“A”. In
Inthe
thecase
caseof
ofcomponent
component“B”“B”we
weneed
need44B’s
B’sfor
foreach
eachA.
A.
Since
Sincewe
weneed
need50
50A’s,
A’s,that
thatmeans
means200
200B’s.
B’s. And
Andagain,
again,weweback
back
the
theschedule
scheduleupupfor
forthe
thenecessary
necessary22days
daysof
oflead
leadtime.
time.
Day: 1 2 3 4 5 6 7 8 9 10
A Required 50
Order Placement 50
B Required 20 200
Order Placement 20 200
LT = 2
Spares
A 4x50=200
B(4) C(2)
Finally,
Finally,repeating
repeatingthe
theprocess
processfor
forall
allcomponents,
components,we
wehave
havethe
the
final
finalmaterials
materialsrequirements
requirementsplan:
plan:
Day: 1 2 3 4 5 6 7 8 9 10
A Required 50
LT=1 Order Placement 50
B Required 20 200
LT=2 Order Placement 20 200
C Required 100
LT=1 Order Placement 100
D Required 55 400 300
LT=3 Order Placement 55 400 300
E Required 20 200
LT=4 Order Placement 20 200
F Required 200
LT=1 Order Placement 200
A
Part D: Day 6
B(4) C(2) 40 + 15 spares
MPS
(Specific End Items)
18-9
• Frozen
– No schedule changes allowed within
this window
• Moderately Firm
– Specific changes allowed within
product groups as long as parts are
available
• Flexible
– Significant variation allowed as long
as overall capacity requirements
remain at the same levels
18-10
Exhibit
Exhibit15.5
15.5
Example of Time Fences
Moderately
Frozen Firm Flexible
Capacity
Forecast and available
capacity
Firm Customer Orders
8 15 26
Weeks
18-11
Aggregate Forecasts
Firm orders product of demand
from known
plan from random
customers
customers
Material
planning
Bill of (MRP Inventory
material computer record file
file program)
Secondary reports
Primary reports
Exception reports
Planned order schedule for Planning reports
inventory and production Reports for performance
control control
18-13
• Materials
• Parts
• Components
• Production sequence
• Modular BOM
– Subassemblies
• Super BOM
– Fractional options
18-14
• Pegging
– Identify each parent item that created
demand
18-15
• Gross Requirements
• Scheduled receipts
• Net requirements
MRP Example
Requirements
Requirementsinclude
include95
95units
units(80
(80firm
firmorders
ordersand
and15
15forecast)
forecast)of
ofXX
in
inweek
week10
10
18-17
Day: 1 2 3 4 5 6 7 8 9 10
X Gross requirements 95
X LT=2 Scheduled receipts
Proj. avail. balance 50 50 50 50 50 50 50 50 50 50
On- Net requirements 45
hand Planned order receipt 45
50 Planner order release 45
A Gross requirements 90
A(2) LT=3 Scheduled receipts
Proj. avail. balance 75 75 75 75 75 75 75 75
On- Net requirements 15
hand Planned order receipt 15
75 Planner order release 15
B Gross requirements 45
ItIttakes
takes
LT=1 Scheduled receipts
Proj. avail. balance 25 25 25 25 25 25 25 25
22A’s
A’sfor
for On-
hand
Net requirements
Planned order receipt
20
20
each
eachXX 25
C
Planner order release
Gross requirements 45
20
40
LT=2 Scheduled receipts
Proj. avail. balance 10 10 10 10 10
On- Net requirements 35 40
hand Planned order receipt 35 40
10 Planner order release 35 40
D Gross requirements 100
LT=2 Scheduled receipts
Proj. avail. balance 20 20 20 20 20 20 20
On- Net requirements 80
hand Planned order receipt 80
20 Planner order release 80
18-18
Day: 1 2 3 4 5 6 7 8 9 10
X Gross requirements 95
X LT=2 Scheduled receipts
Proj. avail. balance 50 50 50 50 50 50 50 50 50 50
On- Net requirements 45
hand Planned order receipt 45
50 Planner order release 45
A Gross requirements 90
A(2) B(1) LT=3 Scheduled receipts
Proj. avail. balance 75 75 75 75 75 75 75 75
On- Net requirements 15
hand Planned order receipt 15
75 Planner order release 15
B Gross requirements 45
LT=1 Scheduled receipts
ItIttakes
takes Proj. avail. balance 25 25 25 25 25 25 25 25
On- Net requirements 20
11BBforfor hand Planned order receipt 20
each
eachXX
25
C
Planner order release
Gross requirements 45
20
40
LT=2 Scheduled receipts
Proj. avail. balance 10 10 10 10 10
On- Net requirements 35 40
hand Planned order receipt 35 40
10 Planner order release 35 40
D Gross requirements 100
LT=2 Scheduled receipts
Proj. avail. balance 20 20 20 20 20 20 20
On- Net requirements 80
hand Planned order receipt 80
20 Planner order release 80
18-19
Day: 1 2 3 4 5 6 7 8 9 10
X Gross requirements 95
X LT=2 Scheduled receipts
Proj. avail. balance 50 50 50 50 50 50 50 50 50 50
On- Net requirements 45
hand Planned order receipt 45
50 Planner order release 45
A Gross requirements 90
A(2) B(1) LT=3 Scheduled receipts
Proj. avail. balance 75 75 75 75 75 75 75 75
On- Net requirements 15
hand Planned order receipt 15
75 Planner order release 15
C(3) B Gross requirements 45
LT=1 Scheduled receipts
Proj. avail. balance 25 25 25 25 25 25 25 25
On- Net requirements 20
hand Planned order receipt 20
25 Planner order release 20
ItIttakes
takes33
C
LT=2
Gross requirements
Scheduled receipts
45 40
C’s
C’sforfor On-
Proj. avail. balance
Net requirements
10 10 10 10 10
35 40
each
eachAA
hand
10
Planned order receipt
Planner order release 35
35
40
40
Day: 1 2 3 4 5 6 7 8 9 10
X Gross requirements 95
X LT=2 Scheduled receipts
Proj. avail. balance 50 50 50 50 50 50 50 50 50 50
On- Net requirements 45
hand Planned order receipt 45
50 Planner order release 45
A Gross requirements 90
A(2) B(1) LT=3 Scheduled receipts
Proj. avail. balance 75 75 75 75 75 75 75 75
On- Net requirements 15
hand Planned order receipt 15
75 Planner order release 15
C(3) C(2) B Gross requirements 45
LT=1 Scheduled receipts
Proj. avail. balance 25 25 25 25 25 25 25 25
On- Net requirements 20
hand Planned order receipt 20
25 Planner order release 20
ItIttakes
takes22
C
LT=2
Gross requirements
Scheduled receipts
45 40
C’s
C’sforfor On-
Proj. avail. balance
Net requirements
10 10 10 10 10
35 40
each
eachBB
hand
10
Planned order receipt
Planner order release 35
35
40
40
Day: 1 2 3 4 5 6 7 8 9 10
X Gross requirements 95
X LT=2 Scheduled receipts
Proj. avail. balance 50 50 50 50 50 50 50 50 50 50
On- Net requirements 45
hand Planned order receipt 45
50 Planner order release 45
A Gross requirements 90
A(2) B(1) LT=3 Scheduled receipts
Proj. avail. balance 75 75 75 75 75 75 75 75
On- Net requirements 15
hand Planned order receipt 15
75 Planner order release 15
C(3) C(2) D(5) B Gross requirements 45
LT=1 Scheduled receipts
Proj. avail. balance 25 25 25 25 25 25 25 25
On- Net requirements 20
hand Planned order receipt 20
25 Planner order release 20
ItIttakes
takes55
C
LT=2
Gross requirements
Scheduled receipts
45 40
D’s
D’sforfor On-
Proj. avail. balance
Net requirements
10 10 10 10 10
35 40
each
eachBB
hand
10
Planned order receipt
Planner order release 35
35
40
40
Production Planning
Master Production Scheduling
Material Requirements Planning
Capacity Requirements Planning
No
Realistic? Feedback
Feedback
Yes
Execute:
Capacity Plans
Material Plans
18-23
Question Bowl
Question Bowl
Question Bowl
Question Bowl
Question Bowl
Question Bowl
Question Bowl
Question Bowl
End of Chapter 18
1-32