You are on page 1of 34

QUANTITY

ESTIMATION AND
RATE ANALYSIS
Unit Weight Information Required for Rate Analysis
Material Rate List
Description UOM Rate in Rs
Thermo Mechanically Treated bars (TMT bars)
Tonne 44500.00
Mild steel q 4100.00

Teak wood cum 140000.00


Cum 1050.00
Coarse Aggregate 20 mm nominal size
Fine aggregate 2.36 mm nominal size Cum 750.00

Cement Kg 670.00

100 Nos. 700.00


Table moulded bricks class designation 50 (non modular)
Productivity Norms for Labour
Calculations
Productivity Norms for Labour
Calculations

General Productivity Norm for Plastering

1 Masor and 1 Helper can cover around 40 to 50 sqm of plastering in a Manday.


Labour Costs
• Highly Skilled – 600 / Man Day
• Skilled – 500 / Man Day
• Semi Skilled – 400 / Man Day
• Unskilled – 300 – 350 / Man Day