You are on page 1of 61

Chapter 9

Project Management
Lecture Outline
• Project Planning
• Project Scheduling
• Project Control
• CPM/PERT
• Probabilistic Activity Times
• Microsoft Project
• Project Crashing and Time-Cost Trade-off

Copyright 2011 John Wiley & Sons, Inc. 9-2


Project Management Process
• Project
• unique, one-time operational activity or effort

Copyright 2011 John Wiley & Sons, Inc. 9-3


Project Management Process

Copyright 2011 John Wiley & Sons, Inc. 9-4


Project Management Process

Copyright 2011 John Wiley & Sons, Inc. 9-5


Project Elements
• Objective
• Scope
• Contract requirements
• Schedules
• Resources
• Personnel
• Control
• Risk and problem analysis

Copyright 2011 John Wiley & Sons, Inc. 9-6


Project Team and Project Manager
• Project team
• made up of individuals from various areas and
departments within a company
• Matrix organization
• a team structure with members from functional
areas, depending on skills required
• Project manager
• most important member of project team

Copyright 2011 John Wiley & Sons, Inc. 9-7


Scope Statement
• Scope statement
• a document that provides an understanding,
justification, and expected result of a project
• Statement of work
• written description of objectives of a project

Copyright 2011 John Wiley & Sons, Inc. 9-8


Work Breakdown Structure
• Work breakdown structure (WBS)
• Breaks a project into components,
subcomponents, activities, and tasks

Copyright 2011 John Wiley & Sons, Inc. 9-9


Work
Work Breakdown
Breakdown Structure
Structure for
for Computer
Computer Order
Order
Processing
Processing System
System Project
Project

Copyright 2011 John Wiley & Sons, Inc. 9-10


Responsibility Assignment Matrix
• Organizational Breakdown Structure (OBS)
• a chart that shows which organizational units are
responsible for work items
• Responsibility Assignment Matrix (RAM)
• shows who is responsible for work in a project

Copyright 2011 John Wiley & Sons, Inc. 9-11


Responsibility Assignment Matrix

Copyright 2011 John Wiley & Sons, Inc. 9-12


Global and Diversity Issues in Project
Management
• Global project teams are formed from different
genders, cultures, ethnicities, etc.
• Diversity among team members can add an
extra dimension to project planning
• Cultural research and communication are
important elements in the planning process

Copyright 2011 John Wiley & Sons, Inc. 9-13


Project Scheduling
• Steps • Techniques
• Define activities • Gantt chart
• Sequence activities • CPM/PERT
• Estimate time • Software
• Develop schedule • Microsoft Project

Copyright 2011 John Wiley & Sons, Inc. 9-14


Gantt Chart
• Graph or bar chart
• Bars represent the time for each task
• Bars also indicate status of tasks
• Provides visual display of project schedule

• Slack
• amount of time an activity can be delayed without
delaying the project

Copyright 2011 John Wiley & Sons, Inc. 9-15


Example of Gantt Chart
Month
0 | 2 | 4 | 6 | 8 | 10
Activity
Design house
and obtain
financing
Lay foundation
Order and
receive
materials

Build house

Select paint

Select carpet

Finish work

1 3 5 7 9
Month
Copyright 2011 John Wiley & Sons, Inc. 9-16
Project Control
• Time management
• Cost management
• Performance management
• Earned Value Analysis – standard procedure to
• numerically measure a project’s progress
• forecast its completion date and cost
• measure schedule and budget variation

Copyright 2011 John Wiley & Sons, Inc. 9-17


Project Control
• Quality management
• Communication
• Enterprise project management

Copyright 2011 John Wiley & Sons, Inc. 9-18


CPM/PERT
• Critical Path Method (CPM)
• DuPont & Remington-Rand
• Deterministic task times
• Activity-on-node network construction

• Project Evaluation and Review Technique (PERT)


• US Navy and Booz, Allen & Hamilton
• Probabilistic task time estimates
• Activity-on-arrow network construction

Copyright 2011 John Wiley & Sons, Inc. 9-19


Project Network
• Activity-on-node (AON)
• nodes represent activities Branch Node
• arrows show precedence
1 2 3
relationships
• Activity-on-arrow (AOA)
• arrows represent activities
• nodes are events for
points in time
• Event
• completion or beginning
of an activity in a project

Copyright 2011 John Wiley & Sons, Inc. 9-20


AOA Project Network for a House

3
Lay Dummy
foundation
2 0 Build Finish
3 1 house work
1 2 4 6 7
Design house Order and 3 1
and obtain receive 1 1
Select Select
financing materials paint carpet
5

Copyright 2011 John Wiley & Sons, Inc. 9-21


Concurrent Activities
• Dummy
• two or more activities cannot share same start and
end nodes

3
Lay foundation Lay
Dummy
foundation
2 0
2 3
1
Order material 2 4
Order material
(a) Incorrect precedence (b) Correct precedence
relationship relationship

Copyright 2011 John Wiley & Sons, Inc. 9-22


AON Network for House Building
Project
Lay Build
foundation house
Activity Number
2 4
Activity Time
2 3

Start 1 7
3 1
Finish work
Design house 3 5 6
and obtain
1 1 1
financing
Order &receive Select Select
materials paint carpet

Copyright 2011 John Wiley & Sons, Inc. 9-23


Critical Path
2 4
2 3

Start 1 7
3 1
3 5 6
1 1 1

A: 1-2-4-7
3 + 2 + 3 + 1 = 9 months  Critical path
B: 1-2-5-6-7  Longest path through a
3 + 2 + 1 + 1 + 1 = 8 months network
C: 1-3-4-7
3 + 1 + 3 + 1 = 8 months
 Minimum project
D: 1-3-5-6-7 completion time
3 + 1 + 1 + 1 + 1 = 7 months

Copyright 2011 John Wiley & Sons, Inc. 9-24


Activity Start Times

Start at 5 months
2 4
2 3 Finish at 9 months

Start 1 7
Finish
3 1
3 5 6
1 1 1
Start at 3 months Start at 6 months

Copyright 2011 John Wiley & Sons, Inc. 9-25


Node Configuration

Activity Earliest Earliest


number start finish

1 0 3

3 0 3

Activity Latest Latest


duration start finish

Copyright 2011 John Wiley & Sons, Inc. 9-26


Activity Scheduling
• Earliest start time (ES)
• earliest time an activity can start
• ES = maximum EF of immediate predecessors
• Forward pass
• starts at beginning of CPM/PERT network to determine
earliest activity times
• Earliest finish time (EF)
• earliest time an activity can finish
• earliest start time plus activity time
• EF= ES + t

Copyright 2011 John Wiley & Sons, Inc. 9-27


Earliest Activity Start and Finish Times
Lay foundation
Build house
2 3 5
4 5 8
2
3 Finish work

1 0 3 7 8 9
Start
1 1
Design house
and obtain 6 6 7
financing 3 3 4
1
1 5 5 6
Select carpet
Order and 1
receive materials
Select paint

Copyright 2011 John Wiley & Sons, Inc. 9-28


Activity Scheduling
• Latest start time (LS)
• Latest time an activity can start without delaying critical
path time
• LS= LF - t
• Latest finish time (LF)
• latest time an activity can be completed without delaying
critical path time
• LF = minimum LS of immediate predecessors
• Backward pass
• Determines latest activity times by starting at the end of
CPM/PERT network and working forward

Copyright 2011 John Wiley & Sons, Inc. 9-29


Latest Activity Start and Finish Times
Lay foundation
Build house
2 3 5
4 5 8
2 3 5
3 5 8 Finish work

1 0 3 7 8 9
Start
1 0 3 1 8 9
Design house
and obtain 6 6 7
financing 3 3 4
1 6 7
1 4 5 5 5 6
Select carpet
Order and 1 6 7
receive materials
Select paint

Copyright 2011 John Wiley & Sons, Inc. 9-30


Activity Slack
Activity LS ES LF EF Slack S
*1 0 0 3 3 0
*2 3 3 5 5 0
3 4 3 5 4 1
*4 5 5 8 8 0
5 6 5 7 6 1
6 7 6 8 7 1
*7 8 8 9 9 0
* Critical Path

Copyright 2011 John Wiley & Sons, Inc. 9-31


Probabilistic Time Estimates
• Beta distribution
• probability distribution traditionally used in CPM/PERT

a + 4m + b
Mean (expected time): t =
6
2
b-a
Variance:  =
2
6
where
a = optimistic estimate
m = most likely time estimate
b = pessimistic time estimate

Copyright 2011 John Wiley & Sons, Inc. 9-32


Examples of Beta Distributions
P(time)

P(time)
a m t b a t m b
Time Time
P(time)

a m=t b
Time

Copyright 2011 John Wiley & Sons, Inc. 9-33


Project with Probabilistic Time Estimates

Equipment Equipment testing


installation and modification

1 4 System Final
6,8,10 2,4,12 training debugging
System 10
development 8
Manual 3,7,11 1,4,7
Start 2 testing Finish
3,6,9
5 11
Position 2,3,4 9 1,10,13
recruiting 2,4,6
Job Training System
3 6 System changeover
1,3,5 3,4,5 testing

Orientation
7
2,2,2

Copyright 2011 John Wiley & Sons, Inc. 9-34


Activity Time Estimates

TIME ESTIMATES (WKS) MEAN TIME VARIANCE


ACTIVITY a m b t б2
1 6 8 10 8 0.44
2 3 6 9 6 1.00
3 1 3 5 3 0.44
4 2 4 12 5 2.78
5 2 3 4 3 0.11
6 3 4 5 4 0.11
7 2 2 2 2 0.00
8 3 7 11 7 1.78
9 2 4 6 4 0.44
10 1 4 7 4 1.00
11 1 10 13 9 4.00

Copyright 2011 John Wiley & Sons, Inc. 9-35


Activity Early, Late Times & Slack
ACTIVITY t б ES EF LS LF S
1 8 0.44 0 8 1 9 1
2 6 1.00 0 6 0 6 0
3 3 0.44 0 3 2 5 2
4 5 2.78 8 13 16 21 8
5 3 0.11 6 9 6 9 0
6 4 0.11 3 7 5 9 2
7 2 0.00 3 5 14 16 11
8 7 1.78 9 16 9 16 0
9 4 0.44 9 13 12 16 3
10 4 1.00 13 17 21 25 8
11 9 4.00 16 25 16 25 0

Copyright 2011 John Wiley & Sons, Inc. 9-36


Earliest, Latest, and Slack
Critical Path 2-5-8-11
1 0 8 4 8 13
8 1 9 5 16 21
10 13 17

16
1 0 3
8 9
2 0 6 Finish
Start 7 9 16
6 0 6 9
5 6 11 16 25
3 6 9 9 9 13
9 16 25
4 12 16
3 0 3 6 3 7
3 2 5 4 5 9

7 3 5
2 14 16

Copyright 2011 John Wiley & Sons, Inc. 9-37


Total Project Variance

s2 = б22 + б52 + б82 + б112


s = 1.00 + 0.11 + 1.78 + 4.00
= 6.89 weeks

Copyright 2011 John Wiley & Sons, Inc. 9-38


CPM/PERT With OM Tools

Copyright 2011 John Wiley & Sons, Inc. 9-39


Probabilistic Network Analysis

Determine probability that project is


completed within specified time
x-
Z= 
where
= tp = project mean time
= project standard deviation
x= proposed project time
Z= number of standard deviations that
x is from the mean

Copyright 2011 John Wiley & Sons, Inc. 9-40


Normal Distribution of Project Time

Probability

Z

 = tp x Time

Copyright 2011 John Wiley & Sons, Inc. 9-41


Southern Textile

What is probability that project is completed within 30 weeks?

P(x  30 weeks)
x-
 2 = 6.89 weeks Z= 
 = 6.89 30 - 25
= 2.62
 = 2.62 weeks
= 1.91
 = 25 x = 30 Time (weeks)

From Table A.1, (appendix A) a Z score of 1.91 corresponds to a


probability of 0.4719. Thus P(30) = 0.4719 + 0.5000 = 0.9719

Copyright 2011 John Wiley & Sons, Inc. 9-42


Southern Textile
What is probability that project is completed within 22 weeks?
P(x  22 weeks) 0.3729
= 0.1271 x-
 2 = 6.89 weeks Z= 
 = 6.89 22 - 25
= 2.62
 = 2.62 weeks
= -1.14
x = 22  = 25 Time (weeks)

From Table A.1, (appendix A) a Z score of 1.14 corresponds to a


probability of 0.3729. Thus P(22) = 0.5000 - 0.3729 = 0.1271

Copyright 2011 John Wiley & Sons, Inc. 9-43


Microsoft Project
• Popular software package for project
management and CPM/PERT analysis
• Relatively easy to use

Copyright 2011 John Wiley & Sons, Inc. 9-44


Microsoft Project

Click on “Tasks”

First step;
Start Date

Copyright 2011 John Wiley & Sons, Inc. 9-45


Microsoft Project

Click on “Format” then ”Timescale”


to scale Gantt chart.

Gantt chart;
Precedence click on “View”
Create precedence relationships to activate
relationships;
click on predecessor
activity, then
holding “Ctrl” Key,
click on successor
activity.

Copyright 2011 John Wiley & Sons, Inc. 9-46


Microsoft Project
Click on “View” then
Network Diagram

Critical path
in red

Copyright 2011 John Wiley & Sons, Inc. 9-47


Microsoft Project – Zoom View

Copyright 2011 John Wiley & Sons, Inc. 9-48


Microsoft Project – Task Information

Enter % completion

Copyright 2011 John Wiley & Sons, Inc. 9-49


Microsoft Project – Degree of Completion

Activities 1, 2 and 3 Black bars show


100% complete degree of completion

Copyright 2011 John Wiley & Sons, Inc. 9-50


PERT Analysis with Microsoft Project
Click on PERT Entry
Sheet to enter 3
time estimates

Click on PERT
calculator to compute
activity duration

Copyright 2011 John Wiley & Sons, Inc. 9-51


PERT Analysis with Microsoft Project

Copyright 2011 John Wiley & Sons, Inc. 9-52


PERT Analysis with Microsoft Project

Copyright 2011 John Wiley & Sons, Inc. 9-53


Project Crashing
• Crashing
• reducing project time by expending additional
resources
• Crash time
• an amount of time an activity is reduced
• Crash cost
• cost of reducing activity time
• Goal
• reduce project duration at minimum cost

Copyright 2011 John Wiley & Sons, Inc. 9-54


Project Network – Building a House

2 4
12
8
7
1 4
12
6
3 5 4
4 4

Copyright 2011 John Wiley & Sons, Inc. 9-55


Normal Time and Cost
vs. Crash Time and Cost
$7,000 –

$6,000 –
Crash cost

$5,000 – Crashed activity

Slope = crash cost per week


$4,000 –

$3,000 – Normal activity

Normal cost
$2,000 –

$1,000 –
Crash time Normal time
| | | | | | |

0 2 4 6 8 10 12 14 Weeks
Copyright 2011 John Wiley & Sons, Inc. 9-56
Project Crashing
TOTAL
NORMAL CRASH ALLOWABLE CRASH
TIME TIME NORMAL CRASH CRASH TIME COST PER
ACTIVITY (WEEKS) (WEEKS) COST COST (WEEKS) WEEK

1 12 7 $3,000 $5,000 5 $400


2 8 5 2,000 3,500 3 500
3 4 3 4,000 7,000 1 3,000
4 12 9 50,000 71,000 3 7,000
5 4 1 500 1,100 3 200
6 4 1 500 1,100 3 200
7 4 3 15,000 22,000 1 7,000
$75,000 $110,700

Copyright 2011 John Wiley & Sons, Inc. 9-57


$500 $7000
4
2
$7000
FROM …
8 12
7 Project Duration:
1 4
12
36 weeks

$400 3 6
4 5 4
4 $200
$3000
$200

$500 $7000
2 4
$7000
TO… 8 12
7
Project Duration: 1 4
31 weeks 7
Additional Cost:
$400 3 6
$2000 5 4
4
4 $200
$3000
$200
Copyright 2011 John Wiley & Sons, Inc. 9-58
Time-Cost Relationship
• Crashing costs increase as project duration
decreases
• Indirect costs increase as project duration
increases
• Reduce project length as long as crashing costs
are less than indirect costs

Copyright 2011 John Wiley & Sons, Inc. 9-59


Time-Cost Tradeoff

Minimum cost = optimal project time


Total project cost

Indirect cost
Cost ($)

Direct cost

Crashing Time
Project duration

Copyright 2011 John Wiley & Sons, Inc. 9-60


Copyright 2011 John Wiley & Sons, Inc.
All rights reserved. Reproduction or translation of this
work beyond that permitted in section 117 of the 1976
United States Copyright Act without express permission
of the copyright owner is unlawful. Request for further
information should be addressed to the Permission
Department, John Wiley & Sons, Inc. The purchaser
may make back-up copies for his/her own use only and
not for distribution or resale. The Publisher assumes no
responsibility for errors, omissions, or damages caused
by the use of these programs or from the use of the
information herein.

Copyright 2011 John Wiley & Sons, Inc. 6-61

You might also like