manufacturing and plant facilities is called the fixed capital investments. • While that necessary for the operation of the plant is termed the working capital. • The sum of fixed capital and working capital is known as the total capital investment. • Fixed capital investment may be further subdivided into manufacturing fixed capital and non manufacturing fixed capital investments. • Manufacturing fixed capital investments represents the capital necessary for the installed process equipment with all auxiliaries that are needed for complete process operation. Expenses for piping , instruments, insulation, foundation and site preparation etc • Fixed capital required for construction overhead and for all plant components that are not directly related the process operation is designated as non manufacturing fixed capital investments. • Land , process building, administrative and other offices, ware houses, transportation, laboratories, utilities and waste disposal. Construction overhead costs consist of field office and supervision expenses, engineering expenses, miscellaneous construction costs, contractors fees and contingencies Working capital • The working capital for an industrial plant consist of total amount of money invested in • 1. Raw materials and supplies carried in stock • 2. Finished products in stock • 3. Accounts receivables • 4. Cash kept on hand for monthly payment of operating expenses such as salaries and raw material purchases • 5.Accounts payable • 6.Taxes payable. • The ratio of working capital to total capital investments varies with different companies, but most chemical plants use an initial working capital amounting to 10 to 20% of total capital investment. Estimation of Capital investments • 1. Direct Costs- • Purchased equipment cost • Purchased equipment installation • Instrumentation and control • Piping • Electrical equipment and materials • Buildings (including services) • Yard improvement • Service facilities- steam, water, power, refrigeration, compressed air, fuel, waste disposal. Office furniture, material handling equipments, distribution and packaging. • Land • 2. Indirect cost- • Engineering and supervision • Construction expenses • Contractors fee • Taxes ,insurance, interests • Contingency Types of capital cost estimates • 1. Order of magnitude estimates(Ratio estimate) – based on similar previous cost data, probable accuracy of estimate 70% • 2. Study estimates(Factored estimate) based on knowledge of major items of equipment. Probable accuracy of estimate up to70%. • 3. Preliminary estimates(Budget authorization estimate, Scope estimate)-based on sufficient data to permit the estimate to be budgeted. Probable accuracy is 80% • 4. Definitive estimate(Project control estimates)- based on almost complete data but before completion of drawing and specification. Probable accuracy of estimate with in 90%) • 5. Detailed estimates(contractors estimates)- based on complete engineering drawings, specification and site survey. Probable accuracy of estimate with in 95% • Order of magnitude estimate study estimate and preliminary estimates are called pre design cost estimates. They require much less details than the other two estimates. • However these three estimates are very important for determining if a proposed project should be given a further consideration or not. • When more and more details are added to the pre design estimates it becomes similar to the definitive and detailed estimates. Cost indexes • cost data which are available for immediate use in a preliminary or pre design estimate are based on conditions at some time in the past. Because prices may change considerably with time due to changes in economic conditions, some method must be used for updating cost data applicable at a past date to costs that are representative of conditions at a later time. This can be done by the use of cost indexes. • A cost index is merely an index value for a given point in time showing the cost at that time relative to a certain base time. • If the cost at some time in the past is known, the equivalent cost at the present time can be determined by multiplying the original cost by the ratio of the present index value to the index value applicable when the original cost was obtained. • Many different types of cost indexes are published regularly. Some of these can be used for estimating equipment costs; others apply specifically to labour, construction, materials etc. • The most common of these indexes are the 1.Marshall and Swift all-industry and process-industry equipment indexes • 2.The Engineering News-Record construction index • 3.The Nelson-Farrar refnery construction index • 4.The Chemical Engineering plant cost index. Cost factors in capital investments • Capital investment is the total amount of money needed to supply the necessary plant and manufacturing facilities plus the amount of money required for the operation of the facilities. These are the proportional cost of each major component of total capital investments. • 1. Purchased equipment-20 to 40% of fixed capital investments. • 2. Purchased equipment installation-7 to 26% of fixed capital investments. • 3. Insulation cost- 8 to 9% of purchased equipment cost or 2% of total capital investments. • 4. Instrumentation and control- 3% of total capital investments.2.5 to 7 % of fixed capital investments. • 5. Piping-20% of fixed capital investments. • 6. Electrical installation-4 to 11% of fixed capital investments. • 7. Building and services- 3 to 18% of FCI • 8 . Yard improvement- 2 to 3% of fixed capital investments. • 9. Service facilities- 6 to 25 % of fixed capital investments with 13% considered as an average value. • Land- 1 to 2% of Total capital investments. • Engineering and supervision- 35% of purchased equipment cost or 10% of the total direct cost of the process plant. • Construction expense- 10% of the total direct cost of the process plant. • Contractors fee- 2 to 7% of the total direct cost of the process plant or 1.5 to 6% of the fixed capital investments. • Contingencies-8 to 20 % of direct and indirect plant costs. • Start up expense- 12% of fixed capital investments • Prepare a study estimate of the FCI for a process plant, if the purchased equipment cost is Rs 100,000 . Purchased equip 100000 % 0f FCI Purch.Equipment 36000 installation Instrumentation 28000 piping 32000 Electrical 20000 Building 20000 Yard improvement 8000 Service facilities 60000 Land 4000 Enggg.Supervision 40000 Construction Exp 48000 Contractors fee 8000 Contingency 32000 • Prepare a study estimate of the FCI for the process plant, if the delivered equipment cost is Rs 100,000 Delivered Equipment cost (E) 100000 Purchased Equipment installation 39% of E Instrumentation 28% of E Piping 31% 0f E Electrical 10% of E Building 22% of E Yard imp 10% of E Service facilities 55% of E Land 6% of E Engg. And supervision 32%E Construction expense 34%E Contractors fee 5% of (D+I) Contingency 10% of (D+I) • The purchased cost of equipment for a solid processing plant is Rs 500000. The plant is to be constructed as an addition to an existing plant. Estimate the total capital investment and the fixed capital investment. Working capital investment is 20% of the FCI. Purchased Equipment cost (E) 500000 Purchased Equipment installation 45% E Instrumentation 9% E Piping 16% E Electrical 10% E Building 25% E Yard imp 13% E Service facilities 40% E Land 6% E Engg. And supervision 33% E Construction expense 39% E Contractors fee 5% of (D+I) Contingency 10% of (D+I) Working capital 20 % of FCI Estimating Equipment Cost by Scaling • When no cost data is available for a particular piece of equipment, the cost of the equipment needs to be estimated. • If the new equipment is similar to one of another capacity for which cost data are available, the six-tenth factor rule can be used, which gives a fairly good estimate. • According to this rule, if the cost of a given unit at one capacity is known, the cost of a similar unit with X times the capacity of the first is approximately (X^ 0.6 ) times the cost of the initial unit. • This cost capacity concept should not be used beyond a ten fold range of capacity. Problems • The purchased cost of 200 lit of glass lined jacketed reactor was Rs 300000 in 2000. Estimate the purchased cost of similar equipment of 1000 litre capacity in 2006. Cost index for such type of equipment in 2000 was 511 and in 2006, 651. • The purchased cost of a Shell an tube heat exchanger with 100 ft^2 of heating surface was Rs 140000 in 1970. what will be the purchased cost of a similar equipment with 200 ft^2 of heating surface in 1970, if the purchased cost capacity exponent of this type of HE is 0.6 for surface area ranging from 100 to 400 ft^2. if the purchased cost capacity exponent for this type of HE is 0.81 for surface area ranging from 400 to 2000 ft^2, what will be the purchased cost of a HE with 1000 ft^2 of heating surface in 1970. • The 1990 cost for an Aluminium tank weighing 100,000 kg was Rs 188000. for a size range from 200000 to 1000000Kg, the cost weight exponent for Al tanks is 0.93. If an Al tank weighing 700000 kg is required, what is the capital investment needed in 1995 ?. Cost index in 1990 is 620 and in 1995 is 740. The cost of installation in 1995 may be taken as 40% of the purchased equipment cost. Methods for estimating capital investment • METHOD A- DETAILED-ITEM ESTIMATE • Requires careful determination of each individual item. • Equipment and material needs are determined from completed drawing and specifications. • They are priced either from current cost data or preferably from firm delivered quotations. • Estimates of installation cost are determined from accurate labour rates and employee hour calculations. • Accurate estimates of engineering, drafting, field supervision, field expenses etc are also detailed. • Site survey and soil data must be available to minimize errors in site development and construction cost estimates. • Large amount of engineering time is required to prepare such detailed item estimate. • This type of estimate is prepared by contractors bidding on lumpsom work from finished drawing and specification. • Accuracy is 95%. • METHOD B- UNIT-COST ESTIMATE. • gives good estimating accuracies for FCI, provided accurate records of previous cost experience are available. • This method is used for preparing definitive and preliminary estimates. • This estimate requires detailed estimates of purchased price obtained either from quotations or from index corrected cost records. • Equipment installation labour is evaluated as a fraction of the delivered equipment cost. • Costs for concrete, steel, pipes, electrical, instrumentation, insulation etc are obtained by applying unit costs to the material and labour. • Unit cost is also applied to engineering hours. • A factor for construction expenses, contractors fee and contingency is assumed based on previous experience. • Less accurate than Method A. • METHOD C- PERCENTAGE OF DELIVERED- EQUIPMENT COST- This method for estimating the fixed or total-capital investment requires determination of the delivered-equipment cost. The other items included in the total direct plant cost are then estimated as percentages of the delivered-equipment cost • This method is commonly used for preliminary and study estimates. • Less accurate than method B. • The additional components of the capital investment are based on average percentages of the total direct plant cost, total direct and indirect plant costs, or total capital investments. • Method D- Lang Multiplication factor for FCI and Total capital investment • Factor x delivered-equipment cost = fixed-capital investment or total capital investment. • Cost of a process plant may be obtained by multiplying the basic equipment cost by some factor to approximate the capital investment. • Separate factors may be used for errection of equipment, foundation, utilities, piping etc. • Accuracy generally less than Method A, B& C. Type of plant FCI TCI Solid processing plant 3.9 4.6 Solid fluid processing plant 4.1 4.9 Fluid processing plant 4.8 5.7 • METHOD E- POWER FACTOR APPLIED TO PLANT- CAPACITY RATIO- This method for study or order- of-magnitude estimates relates the fixed-capital investment of a new process plant to the fixed- capital investment of similar previously constructed plants by an exponential power ratio. • Six- tenth rule – if the cost of a given unit at one capacity is known, the cost of a similar unit with X times capacity of the first is approximately XO.6 Times the cost of the initial unit. • This power ratio varies from 0.2 to 1.0 • METHOD F- INVESTMENT COST PER UNIT OF CAPACITY- it is possible to determine the unit investment costs which apply for average conditions. An order-of-magnitude estimate. of the fixed-capital investment for a given process can then be obtained by multiplying the appropriate investment cost per unit of capacity by the annual production capacity of the proposed plant. • It is a rapid evaluation method. • Suitable for order of magnitude estimate. • Problem. • 1.Estimate by turn over ratio method, the FCI of a sulphuric acid plant of capacity 140000 MT of 100% acid per year. The selling price of Sulphuric acid is Rs 9000/MT. Assume a turn over ratio of 2. • 2. The TCI for a chemical plant is Rs 100 crores. If the plant can produce an average of 80 MT/ day of final product, during a 365 day per year, what selling price in Rs of product would be necessary to give a turn over ratio of 2. Total product cost • It is divided into two categories • 1. manufacturing cost • 2. General expenses • Manufacturing cost is known as the operating cost or the production cost. • Total product cost are commonly calculated in one of the three ways. • 1. daily basis • 2. unit of product basis • 3. annual basis Manufacturing cost • Direct production cost- raw material, labour, Maintenance, power, utilities. • Fixed charges- depreciation, insurance, taxes, rent • Plant overhead cost-medical, safety, pension, life insurance, ware house, storage, recreation General expenses • Administrative expenses • Marketing • R&D • Financing expense • Gross earning expense