Kaizen Theme : To increase productivity by reduce Wastage in Target Completion
(WHAT& WHICH) Welding process Date : 28/12/2010 Date : 27/12/2010
Counter measure : Benefits/Results after
Problem Status: SMAW Process eliminated And Implementation : Less Productivity in weld tacking operation. GMAW(Co2 Gas) process introduced for Tacking operation of all welding parts 1. Chipping operation eliminated. wastage of Arc electrodes. 2. Manpower reduced. More time consumption in changing Before Counter Measure : 3. Productivity increased to electrodes. Extra Man power required 350 Nos / 8 Hrs for chipping operation. 4.No fatigue on operator & Helper Analysis : [Mention Statistical tools Used / Why Why Analysis] In SMAW welding it is not possible to consumption of full electrode. More time required for changing After counter measure : electrode. (10 sec / 1 Electrode) Scope & plan for horizontal Extra man & time require for deployment : Sr Item Tgt.Dt Impl.Dt: chipping process. In other Sister Less production (200 Nos / 8 Hrs) concern 11/02/11 1 company Root Cause : 2 SMAW process not suitable 3 4 for Mass production & to increase Standardization : 5 productivity. While designing welding process GMAW 6 Idea : 7 process to be used for mass production to To increase productivity we have increase productivity. to reduce waste by implementing Implemented by : Krishna, Parmeshwar , Sharma. Kaizen no. : PM/KZ/001 atomization Date : 28/12/2010 Dept. : WELDING KAIZEN SHEET Machine : WELDING M/Cs
Kaizen Theme : To increase productivity by reduce Wastage in Target Completion
(WHAT& WHICH) Welding process Date : 30/12/2010 Date : 30/12/2010
Counter measure : Benefits/Results after
Problem Status: Co2 Gas banking system introduced for Implementation : Less Productivity in full welding Welding operation Co2 gas cylinder changing time operation. More time consumption in changing Co2 gas Cylinders. Before Counter Measure : reduced (2min/Cylinder) More Co2 Gas consumption. Co2 gas consumption reduced Unsafe Handling of Co2 cylinders (2 Cylinder/1Day). 1 manpower reduced. Productivity increased to Analysis : [Mention Statistical tools 200 Nos/8 Hrs Used / Why Why Analysis] No fatigue on operator and Helper More time consumption for changing co2 gas cylinders. After counter measure : Scope & plan for horizontal (15 Min/ 1 Cylinder) deployment : More gas consumption per machine Sr Item Tgt.Dt Impl.Dt: (1cylinder/1Day/ M/C) In other Sister Less Productivity (100 Nos / 8 Hrs) concern 15/2/2011 1 company Root Cause : 2 3 Co2 Gas cylinders using 4 for Individual welding M/C 5 Standardization : 6 Idea : To reduce time required for While welding Co2 Gas bank system to be 7 changing Co2 cylinders by used for mass production to increase Introducing Co2 gas Banking System productivity. for productivity improvement & Implemented by : Krishna, Shaikh , Chauhan. Kaizen no. : PM/KZ/00 avoid unsafe handling Date : 30/12/2010 Dept. : WELDING KAIZEN SHEET Machine : WELDING M/Cs
Kaizen Theme : To increase productivity by eliminating Target Completion
(WHAT& WHICH) unnecessary movements of welders . Date : 04/01/2011 Date : 03/01/2011
Counter measure : Benefits/Results after
Problem Status: Welding trolley modified to make space for Implementation : Keeping loose parts & avoid waste movement Less Productivity in Tack welding Before Counter Measure : Cycle Time reduced: 100 Sec/1No Operation due to unnecessary movement during taking of child Parts and welding torch movement Productivity increased to 270 Nos/8 Hrs Analysis : [Mention Statistical tools No fatigue on operator. Used / Why Why Analysis] Unnecessary waste movements for taking child parts for tacking. After counter measure : Scope & plan for horizontal More Cycle Time for Tacking i.e, deployment : 111.7Sec/1 No Job Less Productivity (242 Nos /8 Hrs) Sr Item Tgt.Dt Impl.Dt: 1 0118 CM 15/2/2011 Root Cause : 2 0107 CM 18/02/2011 3 No arrangement provided to keep 4 nut plate & welding torch in 5 welding trolley. 6 Standardization : 7
Idea : While welding all welding trolleys to be
Increase productivity by making provide necessary arrangements for user arrangements to welding trolley for friendly requirements. keeping parts & welding torch Implemented by : Rajesh, Parmeshwar. Kaizen no. : PM/KZ/00