Professional Documents
Culture Documents
WHEEL
ENGINE GAS
Level 1 ASSEMBLY TANK
ASSEMBLY FRAME
(2)
CARBURETOR HUB
Level 2 MOTOR
(2) ASSEMBLY
TIRE
1
Example: MRP Schedule
Bill of Material
Parent Component Level Compon.
Code Code Code Description Req’d
442 0 #442 Moped
442 EA 1 Engine Assem. 1
GT 1 Gas Tank 1
WA 1 Wheel Assem. 2
F 1 Frame 1
EA M 2 Motor 1
C 2 Carburetor 2
WA HA2 Hub Assem. 1
T 2 Tire 1
2
Example: MRP Schedule
Inventory Status Report
Item On- Safety Lot Lead Sched. Receipts
Code Hand Stock Size Time Qnty. Week
442 500 200 LFL 1 -- --
EA 300 100 500 1 1000 10
GT 600 200 LFL 2 900 10
WA 500 400 500 1 2000 10
F 600 0 2000 3 2000 10
M 250 0 LFL 1 -- --
C 150 100 2000+ 2 -- --
HA 100 0 LFL 1 2400 11
T 500 500 1000 3 3000,2000 11,12
3
Example: MRP Schedule
MRP Schedule for #442 Mopeds for Weeks 10 - 16,
considering that:
Gross Requirements come from the moped MPS
There is an On-Hand balance of 500 mopeds at the
end of week 9
There are no Scheduled Receipts for mopeds
A lot-for-lot rule is used for ordering mopeds
Safety stock of 200 mopeds is desired
Lead time for mopeds is one week
5
Example: MRP Schedule
MRP Schedule for #442 Mopeds . . . Initially
6
Example: MRP Schedule
MRP Schedule for #442 Mopeds . . . Completed
7
Example: MRP Schedule
MRP Schedule for Gas Tanks for Weeks 10 - 16,
considering that:
Gross Requirements come from moped Planned-
Order-Releases
There is an On-Hand balance of 600 gas tanks at
the end of week 9
There is a Scheduled Receipt for 900 tanks in
week 10
A lot-for-lot rule is used for ordering gas tanks
Safety stock of 200 gas tanks is desired
Lead time for gas tanks is two weeks
8
Example: MRP Schedule
MRP Schedule for Gas Tanks . . . Initially
9
Example: MRP Schedule
MRP Schedule for Gas Tanks . . . Completed
ITEM: GAS TANK LT: 2 WEEK
LOT SIZE: LFL SS:10 20011 12 13 14 15 16
GROSS REQUIREMENTS 1000 0 1300 800 1200 1400 0
SCHEDULED RECEIPTS 900
AVAILABLE (ON-HAND = 600) 1300 300 300 0 0 0 0
NET REQUIREMENTS 1000 800 1200 1400
PLANNED ORDER RECEIPTS 1000 800 1200 1400
PLANNED ORDER RELEASES 1000 800 1200 1400
10
Example: MRP Schedule
MRP Schedule for Frames for Weeks 10 - 16,
considering that:
Gross Requirements come from moped Planned-
Order-Releases
There is an On-Hand balance of 600 frames at the
end of week 9
There is a Scheduled Receipt for 2000 frames in
week 10
The firm uses a Lot Size (multiple) of 2000 for
ordering frames
No safety stock of frames is desired
Lead time for frames is 3 weeks
11
Example: MRP Schedule
MRP Schedule for Frames . . . Initially
ITEM: FRAME LT: 3 WEEK
LOT SIZE: 2000 SS:
10 011 12 13 14 15 16
GROSS REQUIREMENTS 1000 0 1300 800 1200 1400 0
SCHEDULED RECEIPTS 2000
AVAILABLE 600
NET REQUIREMENTS
PLANNED ORDER RECEIPTS
PLANNED ORDER RELEASES
12
Example: MRP Schedule
MRP Schedule for Frames . . . Completed
13
Example: MRP Schedule
MRP Schedule for Engine Assemblies for Weeks 10 -
16, considering that:
Gross Requirements come from moped Planned-
Order-Releases
There is an On-Hand balance of 300 engine
assemblies at the end of week 9
There is a Scheduled Receipt for 1000 engine
assemblies in week 10
The firm uses a Lot Size (multiple) of 500 for
ordering engine assemblies
Safety Stock of 100 engine assemblies is desired
Lead time for engine assemblies is 1 week
14
Example: MRP Schedule
MRP Schedule for Engine Assemblies . . . Initially
15
Example: MRP Schedule
MRP Schedule for Engine Assemblies . . . Completed
16
Example: MRP Schedule
MRP Schedule for Motors for Weeks 10 - 16,
considering that:
Gross Requirements come from engine assembly
Planned-Order-Releases
There is an On-Hand balance of 250 motors at the
end of week 9
There are no Scheduled Receipts for motors
A lot-for-lot rule is used for ordering motors
No Safety Stock of motors is desired
Lead time for motors is 1 week
17
Example: MRP Schedule
MRP Schedule for Motors . . . Initially
18
Example: MRP Schedule
MRP Schedule for Motors . . . Completed
19
Example: MRP Schedule
MRP Schedule for Carburetors for Weeks 10 - 16,
considering that:
Gross Requirements come from engine assembly
Planned-Order-Releases (times 2)
There is an On-Hand balance of 150 carburetors at
the end of week 9
There are no Scheduled Receipts for carburetors
A Lot Size of 200+ is used for ordering carburetors
Safety Stock of 100 carburetors is desired
Lead time for carburetors is 2 weeks
20
Example: MRP Schedule
MRP Schedule for Carburetors . . . Initially
21
Example: MRP Schedule
MRP Schedule for Carburetors . . . Completed
22
Example: MRP Schedule
MRP Schedule for Wheel Assemblies for Weeks 10 -
16, considering that:
Gross Requirements come from moped Planned-
Order-Releases (times 2)
There is an On-Hand balance of 500 wheel
assemblies at the end of week 9
There is a Scheduled Receipt for 2000 wheel
assemblies in week 10
A Lot Size (multiple) of 500 is used for ordering
wheel assemblies
Safety Stock of 400 wheel assemblies is desired
Lead time for wheel assemblies is 1 week
23
Example: MRP Schedule
MRP Schedule for Wheel Assemblies . . . Initially
24
Example: MRP Schedule
MRP Schedule for Wheel Assemblies . . . Completed
25
Example: MRP Schedule
MRP Schedule for Hub Assemblies for Weeks 10 - 16,
considering that:
Gross Requirements come from wheel assembly
Planned-Order-Releases
There is an On-Hand balance of 100 hub assemblies
at the end of week 9
There is a Scheduled Receipt of 2400 hub
assemblies in week 11
A lot-for-lot rule is used for ordering hub assemblies
No Safety Stock of hub assemblies is desired
Lead time for hub assemblies is 1 week
26
Example: MRP Schedule
MRP Schedule for Hub Assemblies . . . Initially
27
Example: MRP Schedule
MRP Schedule for Hub Assemblies . . . Completed
28
Example: MRP Schedule
MRP Schedule for Tires for Weeks 10 - 16,
considering that:
Gross Requirements come from wheel assembly
Planned-Order-Releases
There is an On-Hand balance of 500 tires at the
end of week 9
There are Scheduled Receipts for 3000 and 2000
tires weeks 11 and 12, respectively
A Lot Size (multiple) of 1000 is used for ordering
tires
Safety Stock of 500 tires is desired
Lead time for tires is 3 weeks
29
Example: MRP Schedule
MRP Schedule for Tires . . . Initially
30
Example: MRP Schedule
MRP Schedule for Tires . . . Completed
31
Issues in MRP
Management Commitment
User involvement
Education and training
Selection of S/W packages
Data accuracy
Realistic MPS
Realistic lead times
Maintaining accurate BOM files
32
Lot-Sizing in MRP
Lot-size is the quantity ordered/produced at one time
Large lots are preferred because:
Changeovers cost less and capacity greater
Annual cost of purchase orders less
Price breaks and transportation breaks can be
utilized
Small lots are preferred because:
Lower inventory carrying cost
Reduced risk of obsolescence
Shorter cycle time to produce customer order
33
Lot-Sizing Methods in MRP
Economic Order Quantity (EOQ)
does not consider quantity discounts
does not always provide the most economical
approach with lumpy demands
Lot-for-Lot (LFL)
accommodates lumpy demand
Period Order Quantity (POQ)
Many others
34
Lot-Sizing Methods in MRP
35
Lot-Sizing in MRP
Lot-size is the quantity ordered/produced at one time
Large lots are preferred because:
Changeovers cost less and capacity greater
Annual cost of purchase orders less
Price breaks and transportation breaks can be
utilized
Small lots are preferred because:
Lower inventory carrying cost
Reduced risk of obsolescence
Shorter cycle time to produce customer order
36
Lot-Sizing Methods
Economic Order Quantity (EOQ)
does not consider quantity discounts
does not always provide the most economical
approach with lumpy demand
Lot-for-Lot (LFL)
accommodates lumpy demand
Period Order Quantity (POQ)
The best method, resulting in least cost,
depends on cost and demand patterns.
37
Evaluation of MRP
Most beneficial to process-focused systems that have
long processing times and complex multistage
production steps
Lead times must be reliable
Must freeze MPS for some time before actual
production... certain demand
Difficult to implement
38
Closed Loop MRP
Production Planning
Master Production Scheduling
Material Requirements Planning
Capacity Requirements Planning
No
Feedback
Realistic?
Feedback
Yes
Execute:
Capacity Plans
Material Plans
39
Closed Loop MRP
40
Manufacturing Resource Planning (MRP II)
Goal: Plan and monitor all resources of a
manufacturing firm (closed loop):
Manufacturing
Marketing
Finance
Engineering
Shop-floor control
Simulation capability of the manufacturing system
41
Enterprise Resource Planning (ERP)
ERP systems available today integrate
manufacturing with other functional areas in an
organization
ERP systems make it easier for management to
obtain local information about performance of
specific processes, bottlenecks resources, and
products (or product groups), etc.
Class I ERP software packages (for large
companies) include BAAN, SAP, and Oracle
42
MRP II System
MRP II System
43
MRP I to MRP II
MRP I simply exploded demand (MPS) into required
materials
MRP II became Manufacturing Resource Planning
which provides a closed-loop business management
system
Financial management
Shop floor control
Operations management
Simulation capability
44
Capacity Requirements Planning (CRP)
45
Capacity Requirements Planning (CRP)
Tests MPS for feasibility
Utilizes routings to determine labor/machine loads
If schedule feasible, recommends freezing
If schedule overloads resources, points out processes
that are overscheduled
46
Load Schedules
Compares actual labor and machine hours against
available hours
Offsets schedules between successive stages of
production by lead times
Provides feasible MPS and economically loaded work
centers
Promotes system operating efficiency ... lowers costs!
47
World-Class Practice
Lead times respond to conditions
Product development as levels of product structure
tree
Lead times that adjust to load
MRP reports shared with customers and suppliers
48