You are on page 1of 48

Example: MRP Schedule

LocoMopeds is a manufacturer of off-road


mopeds. The following product structure diagram
represents the bill of materials for its dual-carburetor
Model 442 moped.
Level 0 MOPED

WHEEL
ENGINE GAS
Level 1 ASSEMBLY TANK
ASSEMBLY FRAME
(2)

CARBURETOR HUB
Level 2 MOTOR
(2) ASSEMBLY
TIRE

1
Example: MRP Schedule

Bill of Material
Parent Component Level Compon.
Code Code Code Description Req’d
442 0 #442 Moped
442 EA 1 Engine Assem. 1
GT 1 Gas Tank 1
WA 1 Wheel Assem. 2
F 1 Frame 1
EA M 2 Motor 1
C 2 Carburetor 2
WA HA2 Hub Assem. 1
T 2 Tire 1

2
Example: MRP Schedule

Inventory Status Report
Item On- Safety Lot Lead Sched. Receipts
Code Hand Stock Size Time Qnty. Week
442 500 200 LFL 1 -- --
EA 300 100 500 1 1000 10
GT 600 200 LFL 2 900 10
WA 500 400 500 1 2000 10
F 600 0 2000 3 2000 10
M 250 0 LFL 1 -- --
C 150 100 2000+ 2 -- --
HA 100 0 LFL 1 2400 11
T 500 500 1000 3 3000,2000 11,12
3
Example: MRP Schedule

The company is currently planning production for


weeks 10 through 16. Based on existing orders and
demand forecasts, the master production schedule is
as follows:
Master Production Schedule: #442 Moped
WEEK 10 11 12 13 14 15 16
QUANTITY 0 1000 0 1300 800 1200 1400

Determine the MRP schedule required to support


the master production schedule for the Model 442
moped in weeks 10-16.
4
Example: MRP Schedule


MRP Schedule for #442 Mopeds for Weeks 10 - 16,
considering that:

Gross Requirements come from the moped MPS

There is an On-Hand balance of 500 mopeds at the
end of week 9

There are no Scheduled Receipts for mopeds

A lot-for-lot rule is used for ordering mopeds

Safety stock of 200 mopeds is desired

Lead time for mopeds is one week

5
Example: MRP Schedule


MRP Schedule for #442 Mopeds . . . Initially

ITEM: 442 MOPED LT: 1 WEEK


LOT SIZE: LFL SS:
10 20011 12 13 14 15 16
GROSS REQUIREMENTS 0 1000 0 1300 800 1200 1400
SCHEDULED RECEIPTS
AVAILABLE (ON-HAND = 500)
NET REQUIREMENTS
PLANNED ORDER RECEIPTS
PLANNED ORDER RELEASES

6
Example: MRP Schedule


MRP Schedule for #442 Mopeds . . . Completed

ITEM: 442 MOPED LT: 1 WEEK


LOT SIZE: LFL SS: 10
200 11 12 13 14 15 16
GROSS REQUIREMENTS 0 1300 0 1300 800 1200 1400
SCHEDULED RECEIPTS
AVAILABLE (ON-HAND = 500) 300 300 0 0 0 0 0
NET REQUIREMENTS 1000 1300 800 1200 1400
PLANNED ORDER RECEIPTS 1000 1300 800 1200 1400
PLANNED ORDER RELEASES 1000 1300 800 1200 1400

7
Example: MRP Schedule


MRP Schedule for Gas Tanks for Weeks 10 - 16,
considering that:

Gross Requirements come from moped Planned-
Order-Releases

There is an On-Hand balance of 600 gas tanks at
the end of week 9

There is a Scheduled Receipt for 900 tanks in
week 10

A lot-for-lot rule is used for ordering gas tanks

Safety stock of 200 gas tanks is desired

Lead time for gas tanks is two weeks

8
Example: MRP Schedule


MRP Schedule for Gas Tanks . . . Initially

ITEM: GAS TANK LT: 2 WEEK


LOT SIZE: LFL SS:10 20011 12 13 14 15 16
GROSS REQUIREMENTS 1000 0 1300 800 1200 1400 0
SCHEDULED RECEIPTS 900
AVAILABLE (ON-HAND = 600)
NET REQUIREMENTS
PLANNED ORDER RECEIPTS
PLANNED ORDER RELEASES

9
Example: MRP Schedule


MRP Schedule for Gas Tanks . . . Completed
ITEM: GAS TANK LT: 2 WEEK
LOT SIZE: LFL SS:10 20011 12 13 14 15 16
GROSS REQUIREMENTS 1000 0 1300 800 1200 1400 0
SCHEDULED RECEIPTS 900
AVAILABLE (ON-HAND = 600) 1300 300 300 0 0 0 0
NET REQUIREMENTS 1000 800 1200 1400
PLANNED ORDER RECEIPTS 1000 800 1200 1400
PLANNED ORDER RELEASES 1000 800 1200 1400

10
Example: MRP Schedule


MRP Schedule for Frames for Weeks 10 - 16,
considering that:

Gross Requirements come from moped Planned-
Order-Releases

There is an On-Hand balance of 600 frames at the
end of week 9

There is a Scheduled Receipt for 2000 frames in
week 10

The firm uses a Lot Size (multiple) of 2000 for
ordering frames

No safety stock of frames is desired

Lead time for frames is 3 weeks
11
Example: MRP Schedule


MRP Schedule for Frames . . . Initially
ITEM: FRAME LT: 3 WEEK
LOT SIZE: 2000 SS:
10 011 12 13 14 15 16
GROSS REQUIREMENTS 1000 0 1300 800 1200 1400 0
SCHEDULED RECEIPTS 2000
AVAILABLE 600
NET REQUIREMENTS
PLANNED ORDER RECEIPTS
PLANNED ORDER RELEASES

12
Example: MRP Schedule


MRP Schedule for Frames . . . Completed

ITEM: FRAME LT: 3 WEEK


LOT SIZE: 2000 SS: 10
0 11 12 13 14 15 16
GROSS REQUIREMENTS 1000 0 1300 800 1200 1400 0
SCHEDULED RECEIPTS 2000
AVAILABLE (ON-HAND = 600) 1600 1600 1600 300 1500 300 900
NET REQUIREMENTS 0 0 0 500 0 1100 0
PLANNED ORDER RECEIPTS 2000 2000
PLANNED ORDER RELEASES 2000 2000

13
Example: MRP Schedule


MRP Schedule for Engine Assemblies for Weeks 10 -
16, considering that:

Gross Requirements come from moped Planned-
Order-Releases

There is an On-Hand balance of 300 engine
assemblies at the end of week 9

There is a Scheduled Receipt for 1000 engine
assemblies in week 10

The firm uses a Lot Size (multiple) of 500 for
ordering engine assemblies

Safety Stock of 100 engine assemblies is desired

Lead time for engine assemblies is 1 week
14
Example: MRP Schedule


MRP Schedule for Engine Assemblies . . . Initially

ITEM: ENGINE ASSEM. LT: 1 WEEK


LOT SIZE: 500 SS: 10100 11 12 13 14 15 16
GROSS REQUIREMENTS 1000 0 1300 800 1200 1400 0
SCHEDULED RECEIPTS 1000
AVAILABLE (ON-HAND = 300)
NET REQUIREMENTS
PLANNED ORDER RECEIPTS
PLANNED ORDER RELEASES

15
Example: MRP Schedule


MRP Schedule for Engine Assemblies . . . Completed

ITEM: ENGINE ASSEM. LT: 1 WEEK


LOT SIZE: 500 SS: 10100 11 12 13 14 15 16
GROSS REQUIREMENTS 1000 0 1300 800 1200 1400 0
SCHEDULED RECEIPTS 1000
AVAILABLE (ON-HAND = 300) 200 200 200 400 100 400 0
NET REQUIREMENTS 1100 400 1100 1000
PLANNED ORDER RECEIPTS 1500 500 1500 1000
PLANNED ORDER RELEASES 1500 500 1500 1000

16
Example: MRP Schedule


MRP Schedule for Motors for Weeks 10 - 16,
considering that:

Gross Requirements come from engine assembly
Planned-Order-Releases

There is an On-Hand balance of 250 motors at the
end of week 9

There are no Scheduled Receipts for motors

A lot-for-lot rule is used for ordering motors

No Safety Stock of motors is desired

Lead time for motors is 1 week

17
Example: MRP Schedule


MRP Schedule for Motors . . . Initially

ITEM: MOTOR LT: 1 WEEK


LOT SIZE: LFL SS:
10 011 12 13 14 15 16
GROSS REQUIREMENTS 1500 500 1500 1000
SCHEDULED RECEIPTS
AVAILABLE (ON-HAND = 250)
NET REQUIREMENTS
PLANNED ORDER RECEIPTS
PLANNED ORDER RELEASES

18
Example: MRP Schedule


MRP Schedule for Motors . . . Completed

ITEM: MOTOR LT: 1 WEEK


LOT SIZE: LFL SS:
10 011 12 13 14 15 16
GROSS REQUIREMENTS 1500 500 1500 1000
SCHEDULED RECEIPTS
AVAILABLE (ON-HAND = 250) 250 250 0 0 0 0 0
NET REQUIREMENTS 1250 500 1500 1000
PLANNED ORDER RECEIPTS 1250 500 1500 1000
PLANNED ORDER RELEASES 1250 500 1500 1000

19
Example: MRP Schedule


MRP Schedule for Carburetors for Weeks 10 - 16,
considering that:

Gross Requirements come from engine assembly
Planned-Order-Releases (times 2)

There is an On-Hand balance of 150 carburetors at
the end of week 9

There are no Scheduled Receipts for carburetors

A Lot Size of 200+ is used for ordering carburetors

Safety Stock of 100 carburetors is desired

Lead time for carburetors is 2 weeks

20
Example: MRP Schedule


MRP Schedule for Carburetors . . . Initially

ITEM: CARBURETOR LT: 2 WEEK


LOT SIZE: 2000+ SS:10 10011 12 13 14 15 16
GROSS REQUIREMENTS 3000 1000 3000 2000
SCHEDULED RECEIPTS
AVAILABLE (ON-HAND = 150)
NET REQUIREMENTS
PLANNED ORDER RECEIPTS
PLANNED ORDER RELEASES

21
Example: MRP Schedule


MRP Schedule for Carburetors . . . Completed

ITEM: CARBURETOR LT: 2 WEEK


LOT SIZE: 2500+ SS:10 10011 12 13 14 15 16
GROSS REQUIREMENTS 3000 1000 3000 2000
SCHEDULED RECEIPTS 3000
AVAILABLE (ON-HAND = 150) 50 3050 50 1550 1050 1550 1550
NET REQUIREMENTS 950 1450 950
PLANNED ORDER RECEIPTS 2500 2500 2500
PLANNED ORDER RELEASES 2500 2500 2500

22
Example: MRP Schedule


MRP Schedule for Wheel Assemblies for Weeks 10 -
16, considering that:

Gross Requirements come from moped Planned-
Order-Releases (times 2)

There is an On-Hand balance of 500 wheel
assemblies at the end of week 9

There is a Scheduled Receipt for 2000 wheel
assemblies in week 10

A Lot Size (multiple) of 500 is used for ordering
wheel assemblies

Safety Stock of 400 wheel assemblies is desired

Lead time for wheel assemblies is 1 week
23
Example: MRP Schedule


MRP Schedule for Wheel Assemblies . . . Initially

ITEM: WHEEL ASSEM. LT: 1 WEEK


LOT SIZE: 500 SS: 10400 11 12 13 14 15 16
GROSS REQUIREMENTS 2000 0 2600 1600 2400 2800 0
SCHEDULED RECEIPTS 2000
AVAILABLE (ON-HAND = 500)
NET REQUIREMENTS
PLANNED ORDER RECEIPTS
PLANNED ORDER RELEASES

24
Example: MRP Schedule


MRP Schedule for Wheel Assemblies . . . Completed

ITEM: WHEEL ASSEM. LT: 1 WEEK


LOT SIZE: 500 SS: 10400 11 12 13 14 15 16
GROSS REQUIREMENTS 2000 0 2600 1600 2400 2800 0
SCHEDULED RECEIPTS 2000
AVAILABLE (ON-HAND = 500) 2100 100 100 0 400 0 200
NET REQUIREMENTS 2500 1600 2000 2800
PLANNED ORDER RECEIPTS 2500 2000 2000 3000
PLANNED ORDER RELEASES 2500 2000 2000 3000

25
Example: MRP Schedule


MRP Schedule for Hub Assemblies for Weeks 10 - 16,
considering that:

Gross Requirements come from wheel assembly
Planned-Order-Releases

There is an On-Hand balance of 100 hub assemblies
at the end of week 9

There is a Scheduled Receipt of 2400 hub
assemblies in week 11

A lot-for-lot rule is used for ordering hub assemblies

No Safety Stock of hub assemblies is desired

Lead time for hub assemblies is 1 week

26
Example: MRP Schedule


MRP Schedule for Hub Assemblies . . . Initially

ITEM: HUB ASSEM. LT: 1 WEEK


LOT SIZE: LFL SS:
10 0 11 12 13 14 15 16
GROSS REQUIREMENTS 0 2500 2000 2000 3000 0 0
SCHEDULED RECEIPTS 2400
AVAILABLE (ON-HAND = 100)
NET REQUIREMENTS
PLANNED ORDER RECEIPTS
PLANNED ORDER RELEASES

27
Example: MRP Schedule


MRP Schedule for Hub Assemblies . . . Completed

ITEM: HUB ASSEM. LT: 1 WEEK


LOT SIZE: LFL SS:
10 0 11 12 13 14 15 16
GROSS REQUIREMENTS 0 2500 2000 2000 3000 0 0
SCHEDULED RECEIPTS 2400
AVAILABLE (ON-HAND = 100) 100 2500 0 0 0 0 0
NET REQUIREMENTS 2000 2000 3000
PLANNED ORDER RECEIPTS 2000 2000 3000
PLANNED ORDER RELEASES 2000 2000 3000

28
Example: MRP Schedule


MRP Schedule for Tires for Weeks 10 - 16,
considering that:

Gross Requirements come from wheel assembly
Planned-Order-Releases

There is an On-Hand balance of 500 tires at the
end of week 9

There are Scheduled Receipts for 3000 and 2000
tires weeks 11 and 12, respectively

A Lot Size (multiple) of 1000 is used for ordering
tires

Safety Stock of 500 tires is desired

Lead time for tires is 3 weeks
29
Example: MRP Schedule


MRP Schedule for Tires . . . Initially

ITEM: TIRE LT: 3 WEEK


LOT SIZE: 1000 SS: 10500 11 12 13 14 15 16
GROSS REQUIREMENTS 0 2500 2000 2000 3000 0 0
SCHEDULED RECEIPTS 3000 2000
AVAILABLE (ON-HAND = 500)
NET REQUIREMENTS
PLANNED ORDER RECEIPTS
PLANNED ORDER RELEASES

30
Example: MRP Schedule


MRP Schedule for Tires . . . Completed

ITEM: TIRE LT: 3 WEEK


LOT SIZE: 1000 SS: 10500 11 12 13 14 15 16
GROSS REQUIREMENTS 0 2500 2000 2000 3000 0 0
SCHEDULED RECEIPTS 3000 2000
AVAILABLE (ON-HAND = 500) 0 3000 2500 500 500 500 500
NET REQUIREMENTS 1500 2500
PLANNED ORDER RECEIPTS 2000 3000
PLANNED ORDER RELEASES 2000 3000

31
Issues in MRP


Management Commitment

User involvement

Education and training

Selection of S/W packages

Data accuracy

Realistic MPS

Realistic lead times

Maintaining accurate BOM files

32
Lot-Sizing in MRP


Lot-size is the quantity ordered/produced at one time

Large lots are preferred because:

Changeovers cost less and capacity greater

Annual cost of purchase orders less

Price breaks and transportation breaks can be
utilized

Small lots are preferred because:

Lower inventory carrying cost

Reduced risk of obsolescence

Shorter cycle time to produce customer order

33
Lot-Sizing Methods in MRP


Economic Order Quantity (EOQ)

does not consider quantity discounts

does not always provide the most economical
approach with lumpy demands

Lot-for-Lot (LFL)

accommodates lumpy demand

Period Order Quantity (POQ)

Many others

34
Lot-Sizing Methods in MRP

The best lot-sizing method,


resulting in least cost,
depends on cost
and demand patterns

35
Lot-Sizing in MRP


Lot-size is the quantity ordered/produced at one time

Large lots are preferred because:

Changeovers cost less and capacity greater

Annual cost of purchase orders less

Price breaks and transportation breaks can be
utilized

Small lots are preferred because:

Lower inventory carrying cost

Reduced risk of obsolescence

Shorter cycle time to produce customer order

36
Lot-Sizing Methods


Economic Order Quantity (EOQ)

does not consider quantity discounts

does not always provide the most economical
approach with lumpy demand

Lot-for-Lot (LFL)

accommodates lumpy demand

Period Order Quantity (POQ)
The best method, resulting in least cost,
depends on cost and demand patterns.

37
Evaluation of MRP


Most beneficial to process-focused systems that have
long processing times and complex multistage
production steps

Lead times must be reliable

Must freeze MPS for some time before actual
production... certain demand

Difficult to implement

38
Closed Loop MRP

Production Planning
Master Production Scheduling
Material Requirements Planning
Capacity Requirements Planning

No
Feedback
Realistic?
Feedback

Yes
Execute:
Capacity Plans
Material Plans

39
Closed Loop MRP

Materials Management at Washburn Guitar, Inc.

40
Manufacturing Resource Planning (MRP II)

Goal: Plan and monitor all resources of a
manufacturing firm (closed loop):
Manufacturing
Marketing
Finance
Engineering
Shop-floor control

Simulation capability of the manufacturing system

41
Enterprise Resource Planning (ERP)


ERP systems available today integrate
manufacturing with other functional areas in an
organization

ERP systems make it easier for management to
obtain local information about performance of
specific processes, bottlenecks resources, and
products (or product groups), etc.

Class I ERP software packages (for large
companies) include BAAN, SAP, and Oracle

42
MRP II System

MRP II System

43
MRP I to MRP II


MRP I simply exploded demand (MPS) into required
materials

MRP II became Manufacturing Resource Planning
which provides a closed-loop business management
system

Financial management

Shop floor control

Operations management

Simulation capability

44
Capacity Requirements Planning (CRP)

45
Capacity Requirements Planning (CRP)


Tests MPS for feasibility

Utilizes routings to determine labor/machine loads

If schedule feasible, recommends freezing

If schedule overloads resources, points out processes
that are overscheduled

46
Load Schedules


Compares actual labor and machine hours against
available hours

Offsets schedules between successive stages of
production by lead times

Provides feasible MPS and economically loaded work
centers

Promotes system operating efficiency ... lowers costs!

47
World-Class Practice


Lead times respond to conditions

Product development as levels of product structure
tree

Lead times that adjust to load

MRP reports shared with customers and suppliers

48

You might also like