Professional Documents
Culture Documents
construction industry
Goals:
• Formulate a system that has less dependency on manual work and can be accessed from
various locations without a need to be physically present at site
• Ensure transparency in the end to end system of verification which involves multi
department co-ordination and reporting to client
• Eliminate time lags between processes by putting in place a robust application that updates
checklist verifications in real time so that handovers between departments is smooth
• Formulate a system that helps in efficient record keeping of processes that is not
lost/damaged during project progress
Scope of Work: Process flow
Project manager will Site engineer Project starts. Site Finally Quality dept
make a work allocates himself to engineer sends approves checklist on
breakdown structure particular project and inspection requests to app and notification
and schedule and notifications are sent safety department is sent to client and
upload on to formwork and which happens at the batching plant to
application. reinforcements start. Post “safe to decide on the amount
Notification of this department for pre start card” update, of concrete. Post pour
will be sent to project prep. Once formwork, checklist is also
formwork, done, they approve reinforcements and approved by quality
reinforcements, project start on the MEP and sent to client for
safety, MEP, application (mech,elec&plumb) final verification
plumbing update checklists
Scope of Work: Stakeholders
Key Stakeholders Description
Project Manager Plans the schedule of the project
and work breakdown structure
Department Head Each department has its head who
can view updates of all engineers in
that department
Site Engineer As representative of execution
department, they co-ordinate
checklists with other departments
and monitor work progress on site
Department Engineer Safety, MEP, Quality all have their
respective engineers for inspection
Client Builders for whom construction
would be done
Batching Plant Engineer Concrete pouring is done by them
Scope of Work: Software/Hardware
Software Requirement
OS Microsoft® Windows® 8/7/10(64-bit) ,
MacOS( Elcaption )
Hardware Requirement
RAM 8 GB
Hard-Disk Space 15 GB
Scheduling Project – Project manager updates the project schedule and work
breakdown structure and overall timeline on the app. He also allocates a site engineer to
the project.
Checklist Update and Approvals – Before Project start, formwork, reinforcements and safety
update their pre project checklists, post structure formation, formwork, reinforcements and
MEP update and approve their checklists post which quality updates its pre pour checklist
which is then send to batching plant and finally post pour checklists are updated and sent to
project manager as well as client
Non functional requirements
• Mobile application • The app should be • Database queries • Records cannot be • 99% uptime of
should be accessible visible to leadership, should be real time tampered with and application
on personal phones department heads, and updation of data integrity across • Application should
on personal project managers. checklists should be all sites and projects
not crash under
networks so that • Any changes made sent as notifications should be
multiple
engineers aren’t by any department to respective maintained
simultaneous logins
required to be to the workflow departments • Login access to
immediately • Application should
present on site to should be visible to Project manager,
be able to work
approve and send others • Throughput of the leadership,
decently well under
to next department • Different users have app should be able department heads
moderate networks,
different login to support around and engineers,
since connectivity is
access like view/ 500 users logged in clients should all
not always strong in
edit etc at a time have different sets
construction sites
of access
Statement Of Work
Project analysis slide 7
Detailed deliverables list (Work Intermediate deliverables Referred Task in Estimated Efforts
Product) Project schedule involved
Design
Design Workflow Integrated design
9
Work break down structure
Project analysis slide 7
Requirement Developmen
Design Testing / QA Deployment Maintenance
s Analysis t
3.1 Database
2.1 Data 4.1 Create Test 5.1 Create 6.1 Create Training
1.1 Project Scope architecture
architecture design Cases Contingency Plan Modules for users
Creation
2.2 Design
1.2 Stakeholder's 3.3 App 5.2 Signoff from all 6.2 Bug Fix after
Application for 4.2 Unit testing
Identification Development stakeholders deployment
Android and iOS
1.3 Joint
6.3 Identify
Requirement 2.3 Technical 3.4 Integration 4.3 Integration 5.3 Deployment resources to
Development(JRD) design document Development Testing
support the system
sessions
1.4 Identify key 2.4 Flow of 4.4 User 6.4 Regular Health
milestones processes Acceptance Testing check of system
11
Assembled effort estimation
(Using Delfi Estimation)
Project Manager ₹ 18,00,000 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 24.0 ₹ 34,615.4 ₹ 8,30,769.2
Project Leader ₹ 10,00,000 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 24.0 ₹ 19,230.8 ₹ 4,61,538.5
Analysts ₹ 8,00,000 1.0 1.0 1.0 1.0 1.0 1.0 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 19.0 ₹ 15,384.6 ₹ 2,92,307.7
Programmers ₹ 5,50,000 2.0 2.0 2.0 2.0 2.0 2.0 5.0 5.0 5.0 5.0 5.0 4.0 2.0 2.0 1.0 1.0 1.0 1.0 1.0 50.0 ₹ 10,576.9 ₹ 5,28,846.2
System-testers ₹ 4,50,000 2.0 2.0 2.0 2.0 2.0 2.0 4.0 4.0 4.0 4.0 4.0 4.0 2.0 2.0 1.0 1.0 1.0 1.0 1.0 45.0 ₹ 8,653.8 ₹ 3,89,423.1
13
Client Billing
(Using Delfi Estimation)
Customer Support
Software Technical Support 910 4 145600
Infrastructure Support 1470 4 235200
Total 380800
Software Tools
Operating System 700 per 5 users 6500
Database 5000 per 15 users 19500
Others 50% of OS cost 3250
Total 29250
Total(₹) 5632050
14
Work Schedule & Resource
Working
USE CASE 1
Project analysis slide 3
Name Progress Monitoring
Summary Progress of the project can be monitored at different levels from PMs, to site engineers
Rationale Instead of calling each site engineer individually for individual progress, management can get a centralized progress report daily, weekly and
monthly and can directly compare it with scheduled objectives through in app tools. Site Engineers can track their progress against work
schedule
User Project Manager, Department Heads, Site Engineer,Client
Summary Physical records can be eliminated saving considerable costs and efforts at the same time bringing enhanced transparency.
Rationale For every concrete process, there are on an average 5 checklists, resulting in huge inventories of records which are expensive to hold and
maintain but is also susceptible to tempering. All this cost and efforts can be saved by having a centralized database in which the records
can be stored directly form the app.
User Internal and External Audit Teams, Site Management
Precondition 1. No concrete shall be done without following SOP including the app.
MARKET TECHNICAL FINANCIAL ECONOMIC ECOLOGICAL
2. Batching of concrete shall be done only after getting all necessary authorization from the app
ANALYSIS ANALYSIS ANALYSIS ANALYSIS ANALYSIS
Basic course of 1. Site Engineer fill the respective checklist properly before raising request to respective department
action 2. Upon authorization, checklist will be saved in a central database
Lorem ipsum dolor
3. sit
While doing Lorem ipsum
audits, dolor
records cansitbe fetched
Lorem
fromipsum
centraldolor sit with convenience
database, Lorem ipsumand dolor sit
maintaining Lorem
the ipsum
integrity of dolor
data sit
amet, consectetur
Alternate Path amet, in
Checklists can be stored consectetur amet,
hard copies in designated consectetur
rooms. amet, consectetur amet, consectetur
adipiscing elit, sed do adipiscing elit, sed do adipiscing elit, sed do adipiscing elit, sed do adipiscing elit, sed do
Post Condition Ease of creating, maintaining
eiusmod tempor and fetching the dataeiusmod tempor
eiusmod tempor eiusmod tempor eiusmod tempor
Integrity
incididunt ut labore et of the data is ensured
incididunt ut labore et incididunt ut labore et incididunt ut labore et incididunt ut labore et
dolore magna aliqua. dolore magna aliqua. dolore magna aliqua. dolore magna aliqua. dolore magna aliqua.
USE CASE 3
Project analysis slide 3
Name Placing order in Batching Plant
Summary The quantity of concrete required can be calculated in-app and can be directly notified to the batching plant present.
Rationale 1. Huge time saving can be achieved if batching plant can be directly notified instead of taking slip the concrete requirement in person.
2. Concrete quantity can be calculated using in app algorithms eliminating the scope of human error.
User Batching Plant, Site Engineer
Precondition All previous checklists should be authorized before placing order for concrete
Summary Summary of workforce and machinery distribution can be accessed through app by department heads to optimize the distribution
Rationale Often specialized workforce and machinery is limited, hence, to ensure optimum utilization of both, it is necessary to keep track of their
distribution on the site. App can provide a single stop allocation reports to the department heads and site management.
User Department Head, Site Management
Precondition All site engineers should fill in correct numbers of workmen required in their areas
Documentation of the data and changes done is equally important during the process of change management.
Benefit Analysis
Benefits Concerns
• Tracking ability for the management. • Stable Network infrastructure is
• Reliable and accurate database. needed.
• Time saving in execution of tasks. • Battery and power backup is needed.
• Reduction in Time Lag/Delay. • Need to handle employee resistance in
• Environment Friendly. adopting to the new technology.
• Removal of Interdependency.
• Easier to develop an analytics platform
to monitor the data.
Thank You