Professional Documents
Culture Documents
Construction Project:
Claim and Dispute Resolution
by
Melaku Tadesse (Civil Engineer), CM
melakutdsse@gmail com
Tel: 0911 232267
Feb. 2020
Discussion on Claim
2
consider
the entire requirement is well understood the terms and
conditions of the contract are clearly understood
16 Employer’s default
Disruption Claims
Losses resulting from delay not from contractor’s responsibility
idle or fall in productivity of resources
Cost incurred to execute a delayed activity
Difference in Cost = Cost of execution of unchanged
work at the changed date less cost of execution at
original scheduled date
Acceleration Claim (directed or constructive)
constructive acceleration, though difficult to get entitlement in
any case, approved schedule and contemporary records are
crucial
Finance Related Claim Issues
24
Prolongation Claims
Time related costs resulting from excusable and compensable
delays (contractor’s overhead costs).
Fluctuations
Adjustment to market price fluctuation, if provided in the
contract, as stated therein
What practice have participants in this?
legislation changes claim for the unanticipated additional
costs may arise
Finance Related Claim Issues
25
Variation
Change of circumstance
The varied work situation may be more difficult or easier
than the one in the bill hence the Bill rate should be
changed by adding/subtracting and then add overhead
Major Change in Quantity
If the change requires appreciably more or less overhead
than envisaged, then the overhead part of the rate may be
adjusted with respect to the rate in the bill. For
insignificant quantity of a bill item change may not be
initiated even if the change is significant as an item
Finance Related Claim Issues
26
Conditions required
Clause 53.1: notice of claim…continued
Clause 17.1. setting out is the responsibility of the
Engineer and the contractor is not required to give notice
Sub-clause 52.2 expressly require the contractor to give
notice within 14 days of the Engineer’s instruction to
vary
Give notice for both, to the Engineer with a copy to the
Employer; even if the requirement is for Clause 52.2
Requirements (procedure) for
Submission
34
Conditions required
Clauses for which notice requirement is stated in express
terms
Clause Situation Notice
6.4 Providing drawings & response to In advance
clarification questions
In-house approach
The PM foresees or encounters a claimable situation ( as well any
team member of the project can aware the PM). As a general purpose it is
advisable if the project records daily event.
Discuss with project and head office concerned staff members on the
Preparation of claims
Delay Claims may be presented:
based on work schedule demonstrating effects of each
claim event on the critical path of the approved schedule
Global y mainly using situations before and during the
occurrence of various claim events at a time
Delay analysis techniques
When desired to base delay claims on approved work
program it will be necessary to demonstrate the effect of
events by selecting appropriate one from the following
available methods. As any of these is not mandatory it helps,
if possible, to get consent of the Employer’s side staff. Other
wise the choice itself needs elaboration
Requirements for Submission
43
Preparation of claims
Delay analysis techniques commonly in use are:
Impacted as- planned: impact of delay events are shown
on approved CPM schedule. the difference b/n the schedule
dates without and with impact gives the delay
Collapsed as –built: only the as-built schedule is used and
only the contractor’s or employer's delay events are applied
As-planned vs. as built – the impacts of the delay events of
both parties are shown on the as-built schedule. the
difference b/n as-planned and as-built completion dates
gives the delay
Time impact or window Analysis- concentrate on specific
delay event for periodical updating of schedule
Requirements for Submission
44
Preparation of claims
Delay analysis techniques: the purpose of using the
different techniques is to respond to:
What was supposed to happen according to the schedule?
What did actually happen?
What variance resulted on the schedule affected?
How was the schedule affected?
The events with their respective durations are shown
Requirements for Submission
45
Preparation of claims
Cause –statement of fact which can be substantiated
adequately
E.g. late possession of site
Effect or consequence- what the event affected
Does the event affected operation of activities in the
sequence stated in the approved work program?
Does the event affect/already affected the work Program?
Demonstrate the effect of each activity including how they
are affected?
Are records being made and notice submitted?
Requirements for Submission
46
Preparation of claims
Entitlement–the merit of the case should be proved. Thus,
it is imperative for the claimant to state the basis of the
claim to the contract or relevant law. The questions are:
is there a remedy in the contract? Or in the Law? May be
in both.
Whose risk is the event in the contract?
Substantiation/justifying the claim
Projectrecord can be used
Correspondences, minutes of meeting, photographs,
any other document to use evidence
The occurrence of the event, the effect need justification
Requirements for Submission
47
Preparation of claims
Substantiation/justifying the claim
Documents doesn’t mean chronological correspondences
which do not substantiate cause-effect scenario and serving
of notice in the procedure stated in the contract
Follow contractual and legal requirements and consider
practical aspects of the issue raised
Use acceptable and appropriate method of analysis
Some which are referred as global claim are apprised in
more subjective manner than following cause-effect. In this,
the approach is to add up all delays and grant as one delay
ignoring the cause-effect
Assessment and Evaluation of Delay
48
Example Case 1:
A contractor’s request for extension due to a claim
event was rejected by the Engineer. The contractor
accelerated the works and completed after few weeks
delay. During dispute settlement process it was
discovered the contractor’s acceleration was forced.
Discuss on the contractor’s entitlement to time.
What if a contractor is delayed by a qualifying delay
event and as a result of which he was encountered with
another non-qualifying delay event?
Assessment and Evaluation of Delay
49
Example Case 2:
A construction project was due to be completed on 31
July, 2010. a variation work issued in April extended
the contract to Oct 31, 2010. from 10st Oct 2010 until
may 1st 2011 the work was suspended due to social
strike in the locality of the project for fear of the
situation and prolonged delay the contractor
demobilized his equipment. The Engineer instructed the
contractor to resume work from 15 May 2011
What can the contractor claim? How can he present
his claim?
What if these claims are rejected?
50
Thank you
for your Attention and Participation
melakutdsse@gmail.com
Tel: 0911 232267