Professional Documents
Culture Documents
Certificate in Process
Safety Management
PP/HSE/NEB255/005/NEBOSH
(Rev.0 – 19.04.2015)
Personal Safety vs Process Safety
Personal Safety
– Prevention of incidents causing injuries
to individuals.
– Applicable in all workplaces.
Process Safety
– Blend of engineering and management
skills.
– Prevention or mitigation of catastrophic
failures.
– High-hazard industries.
PP/HSE/NEB255/005/NEBOSH
(Rev.0 – 19.04.2015)
Process Safety Objectives and Targets
1. Establish overall
objectives
2. Set targets
4. Review regularly
(stepping stones)
3. Monitor progress
of indicators
Leading Success
PP/HSE/NEB255/005/NEBOSH Lagging Failure
(Rev.0 – 19.04.2015)
Lessons Learnt and Benchmarking
Detailed Understand
Sets direction and
understanding of consequences
determines
process hazards before changes
culture.
and risks. are made.
Under all
conditions
Ongoing training.
including start-up
PP/HSE/NEB255/005/NEBOSH
(Rev.0 – 19.04.2015)
and maintenance. (Continued)
Key Elements of PSMS
Control of Emergency
Asset integrity
contractors response
Performance
Incident recording
monitoring and
and investigation management review
Leading and
Investigation to
lagging indicators
learn lessons.
PP/HSE/NEB255/005/NEBOSH
reviewed.
(Rev.0 – 19.04.2015)
Key Elements of PSMS - PDCA
PLAN
• Policy.
• Planning.
DO
• Implementation and operation.
CHECK
• Checking and corrective action.
ACT
• Management review.
• Continual improvement.
PP/HSE/NEB255/005/NEBOSH
(Rev.0 – 19.04.2015)
Leading and Lagging Process Safety Performance
Indicators (PSIs)
Qualitative
– Determined as low, medium or
high.
Semi-Quantitative
– Determined within ranges.
Quantitative
– Fully calculated based on data.
PP/HSE/NEB255/005/NEBOSH
(Rev.0 – 19.04.2015)
Hierarchy of Risk Controls
Inherent safety
Build safety in at design stage.
Elimination
Remove a hazard, minimise inventories.
Substitution
Lower hazard alternative.
Engineering controls
Segregation/spacing of process plant.
Administrative controls
Procedural/behavioural.
PP/HSE/NEB255/005/NEBOSH
(Rev.0 – 19.04.2015)
Purpose and Effective Use of a
Permit-to-Work (PTW)
PP/HSE/NEB255/005/NEBOSH
(Rev.0 – 19.04.2015)
Element 3: Summary
1.1 Process safety management meaning.
1.2 Process safety leadership.
1.3 Organisational learning.
1.4 Management of change.
1.5 Worker engagement.
1.6 Competence.
PP/HSE/NEB255/005/NEBOSH
(Rev.0 – 19.04.2015)
Types of Start-Up and Shut-Down
• Follows pre-determined, controlled sequence
Planned • Includes a risk assessment
• Partial or complete
Unplanned • Can be dangerous in any event
PP/HSE/NEB255/005/NEBOSH
Delayed made to control the situation until shut-down is
allowed to proceed
(Rev.0 – 19.04.2015)
Alarms
• Assist the operator to identify abnormal, hazardous and
unsafe plant and process conditions.
• Operators must be able to identify, understand and respond
to alarms appropriately.
• Consider:
‒ Do they require an operator response?
‒ How are they presented to the operator?
PP/HSE/NEB255/005/NEBOSH
(Rev.0 – 19.04.2015)
The FARSI Model for Defining Performance
Standards
• Functionality
• Availability
• Reliability
• Survivability
• Interdependence
PP/HSE/NEB255/005/NEBOSH
(Rev.0 – 19.04.2015)
Uses of Steam within the Processing
Industries
As a source of heating (direct or indirect) for spaces and processes:
PP/HSE/NEB255/005/NEBOSH
(Rev.0 – 19.04.2015)
Water Hazards
• Cooling towers – Legionella and water-fog:
‒ Legionella bacteria exists in water.
‒ Grows between 20°C and 55°C (37°C is ideal).
‒ Feeds on nutrients in water.
‒ Risk of disease if water droplets
containing viable bacteria are inhaled.
‒ Cooling towers - hot water/high air flow
generates aerosols (‘water-fog’).
PP/HSE/NEB255/005/NEBOSH
(Rev.0 – 19.04.2015)
Exothermic and Endothermic Reactions
PP/HSE/NEB255/005/NEBOSH
(Rev.0 – 19.04.2015)
Thermal Runaway Reaction - Causes
• Incorrect vessel charging:
‒ Incorrect reactants.
‒ Incorrect volumes of reactants.
‒ Wrong specification of raw materials (impurities).
• Incorrect use of catalysts.
• Poor/failed temperature control.
• Poor/failed mixing.
• Loss of power (which affects critical controls).
• Maintenance failures.
PP/HSE/NEB255/005/NEBOSH
(Rev.0 – 19.04.2015) (Continued)
Thermal Runaway Reaction - Causes
• Instrumentation failures.
• Variations in operation:
‒ result of the failure to apply MOC procedures; or
‒ a basic lack of understanding of the reaction chemistry.
• Design failure resulting in insufficient controls, e.g. heat cooling.
• Insufficient operator training or familiarisation.
• Inadvertent addition of compressed air, nitrogen, steam, etc.
(increases pressure).
• Exposure of the vessel to fire.
PP/HSE/NEB255/005/NEBOSH
(Rev.0 – 19.04.2015)
Thermal Runaway Reaction -
Consequences
• Venting or dumping of product and materials.
PP/HSE/NEB255/005/NEBOSH
(Rev.0 – 19.04.2015)
Thermal Runaway Reaction
PP/HSE/NEB255/005/NEBOSH
(Rev.0 – 19.04.2015)
Failure Modes for Tank Shells and Associated Pipe
Work
PP/HSE/NEB255/005/NEBOSH
(Rev.0 – 19.04.2015)
Failure Modes for Tank Shells and Associated Pipe
Work
Creep failure
PP/HSE/NEB255/005/NEBOSH
(Rev.0 – 19.04.2015)
Failure Modes for Tank Shells and Associated Pipe
Work
Stress:
Stress (loading on a material)
causes strain (deformation of
material).
PP/HSE/NEB255/005/NEBOSH
(Rev.0 – 19.04.2015)
Failure Modes for Tank Shells and Associated Pipe
Work
Thermal shock:
• Rapid and extreme temperature changes.
PP/HSE/NEB255/005/NEBOSH
(Rev.0 – 19.04.2015)
Filling of Tanks
Overfilling:
• Continuous monitoring to prevent overfilling.
• Volume of vessel and content should be known before filling.
Alarms:
• Two alarm trip systems:
‒ High level alarm (LAH) - normal operational level exceeded. Not a
reference point for filling operation.
‒ High high level alarm (LAHH) - maximum design capacity of the tank.
• If LAHH is exceeded the tank will overpressurise and overflow.
PP/HSE/NEB255/005/NEBOSH
(Rev.0 – 19.04.2015)
Element 4: Fire and Explosion Protection
PP/HSE/NEB255/005/NEBOSH
(Rev.0 – 19.04.2015)
Filling of Tanks
Overfilling:
• Continuous monitoring to prevent overfilling.
• Volume of vessel and content should be known before filling.
Alarms:
• Two alarm trip systems:
‒ High level alarm (LAH) - normal operational level exceeded. Not a
reference point for filling operation.
‒ High high level alarm (LAHH) - maximum design capacity of the tank.
• If LAHH is exceeded the tank will overpressurise and overflow.
PP/HSE/NEB255/005/NEBOSH
(Rev.0 – 19.04.2015)
Jet Fires
Mechanism:
• Continuous, directed, spray of
fuel ignited immediately.
• Gas, liquid or vapour.
Consequences:
• ‘Blowtorch’ jet of flame.
• Radiated heat.
• Can explode.
PP/HSE/NEB255/005/NEBOSH
(Rev.0 – 19.04.2015)
Pool Fires
Mechanism:
• Spillage of liquid fuel.
• Can be on water.
• Vapour ignites above pool.
Consequences:
• May flow if not contained.
• Unburnt fuel may form a vapour cloud which can explode.
PP/HSE/NEB255/005/NEBOSH
(Rev.0 – 19.04.2015)
Boiling Liquid Expanding Vapour Cloud Explosion
(BLEVE)
Typical mechanism:
• External jet fire attack - tank walls heat up.
• Liquid boils - PRV operates.
• Vessel weakens - crack develops.
• Catastrophic vessel rupture.
• Rapid depressurisation of superheated contents - cloud of fine
droplets formed.
Consequences:
• Missiles, fireball, secondary explosion.
PP/HSE/NEB255/005/NEBOSH
(Rev.0 – 19.04.2015)
Confined Vapour Cloud Explosion (CVCE)
Mechanism:
• Flammable vapour builds up within building, vessel, etc.
• Ignition occurs.
Consequences:
• Shockwave.
• Overpressure.
• Heat.
• Missiles.
PP/HSE/NEB255/005/NEBOSH
(Rev.0 – 19.04.2015)
Unconfined Vapour Cloud Explosion (UVCE)
Mechanism:
• Flammable vapour.
• Ignited before it disperses.
Consequences:
• Shock waves.
• Overpressure.
• Heat.
PP/HSE/NEB255/005/NEBOSH
(Rev.0 – 19.04.2015)
Active and Passive Systems
Active fire protection:
“Equipment, systems and methods, which, following initiation, may be
used to control, mitigate and extinguish fires.”
Passive fire protection:
“coating or cladding arrangement..., which, in the event of fire, will
provide thermal protection to restrict the rate at which heat is
transmitted to the object or area being protected”.
BS EN ISO 13702:1999
PP/HSE/NEB255/005/NEBOSH
(Rev.0 – 19.04.2015)
Passive Fire Protection
Preformed boards, cladding, wall linings, etc.
• Fire resistant materials bound into cement, etc.
Prefabricated walls, partitions, fire doors:
• Structures made in a factory to be assembled on site.
Spray coatings:
• Intumescent coatings sprayed onto structural steelwork, etc.
Seals and sealants:
• Intumescent seals prevent the spread of smoke and fire.
PP/HSE/NEB255/005/NEBOSH
(Rev.0 – 19.04.2015)
Hazardous Area Classification
and Zoning
Flammable Vapours
• Zone 0 – present continuously.
• Zone 1 – present occasionally in normal operations.
• Zone 2 – present for short durations and not in normal operations.
Flammable Dusts
• Zone 20 – present continuously.
• Zone 21 – present occasionally in normal operations.
• Zone 22 – present for short durations and not in normal operations.
PP/HSE/NEB255/005/NEBOSH
(Rev.0 – 19.04.2015)
Primary and Secondary Explosions
Primary Explosion
• Initial explosion within the process.
• May disturb lying dust in the room.
Secondary Explosion
• Often much larger.
• Involves dust stirred up by primary explosion.
PP/HSE/NEB255/005/NEBOSH
(Rev.0 – 19.04.2015)