Professional Documents
Culture Documents
© Siemens AG 2015
page 2/54 PRM Unrestricted EM TS PO
V 17
© Siemens AG 2015
page 3/54 PRM Unrestricted EM TS PO
V 17
Consultant NA
PM Ritesh Kr Sharma
CPM Vibha Chhabra
Duration 16 months
© Siemens AG 2015
page 4/54 PRM Unrestricted EM TS PO
V 17
SAFETY HUT
© Siemens AG 2015
page 5/54 PRM Unrestricted EM TS PO
V 17
© Siemens AG 2015
page 6/54 PRM Unrestricted EM TS PO
V 17
© Siemens AG 2015
page 7/54 PRM Unrestricted EM TS PO
V 17
11kV SIDE
BRICK WORK ABOVE 1ST LVL SLAB IN PROGRESS
ERECTION & TESTING COMPLETED FOR 11 kV HV TESTING FOR 66 kV GIS COMPLETED ON 12 04 17
SWITCHGEAR
© Siemens AG 2015
page 8/54 PRM Unrestricted EM TS PO
V 17
GIS SIDE
BEAM AT+5.65m
66 kV INDOOR & OUTDOOR GIS IN
HT CABLE PROGRESS
TERMINATION IN
SIDE
GIS SIDE
COLUMNPROGRESS
ABOVE CORBEL BEAM IN PROGRESS
STAGING FOR GIS PORTION SLAB CASTING COMPLETED TILL 5.65M LVL
© Siemens AG 2015
page 9/54 PRM Unrestricted EM TS PO
V 17
GIS SIDE
66 kV GIS ROOM – EOT CRANE
BEAM AT+5.65m IN PROGRESS
© Siemens AG 2015
Page 10/54 PRM Unrestricted EM TS PO
V 17
GIS SIDE
GIS SIDE BEAM AT+5.65m IN PROGRESS
COLUMN ABOVE CORBEL BEAM IN
ETC FOR ACDB COMPLETED BATTERY CHARGER CUM DCDB
PROGRESS
RELAY & RTU TESTING IN PROGRESS
© Siemens AG 2015
page 11/54 PRM Unrestricted EM TS PO
V 17
GIS SIDE
GIS CUM
GIS CUM CONTROL
CONTROL ROOM BEAM
ROOM BUILDING AT+5.65m
BUILDING GRIT
FRONT VIEW
WASH IN PROGRESS
COMPLETED
GIS SIDE
COLUMNCORBEL
ABOVE CORBEL
BEAM INBEAM
PROGRESS
IN PROGRESS
© Siemens AG 2015
page 12/54 PRM Unrestricted EM TS PO
V 17
© Siemens AG 2015
Page 13/54 PRM Unrestricted EM TS PO
V 17
© Siemens AG 2015
page 14/54 PRM Unrestricted EM TS PO
V 17
© Siemens AG 2015
page 15/54 PRM Unrestricted EM TS PO
V 17
© Siemens AG 2015
page 16/54 PRM Unrestricted EM TS PO
V 17
© Siemens AG 2015
page 17/54 PRM Unrestricted EM TS PO
V 17
Financi
al
Date of Issue Due
Item Observations Action Items Impact Responsible Status Remarks
Review Type Date
(INR
Million)
© Siemens AG 2015
page 18/54 PRM Unrestricted EM TS PO
V 17
PMTC+ V2.26 *w /o Commitment Currency Exchange Rate 71.000 Currency INR © Siemens
Report from AG 2015
2017-05-15 12:45:15
Revenue 211' 160 211' 160 211' 160 0 211' 160 161' 616 211' 160 211' 160 211' 160 211' 160 211' 160 211' 160
expected 211' 160 211' 160 211' 160 211' 160 211' 160 211' 160
Cost of sales 185' 602 185' 602 185' 602 + 1' 561 187' 163 143' 236 185' 612 187' 162 187' 162 187' 162 187' 162 187' 162
expected 186' 006 187' 162 187' 162 187' 162 187' 162 187' 162
Gross margin 25' 558 25' 558 25' 558 - 1' 561 23' 997 18' 380 25' 548 23' 998 23' 998 23' 998 23' 998 23' 998 23' 998 ' 000
in % of revenue 12.1% 12.1% 12.1% - 0.7% 11.4% 11.4% 12.1% 11.4% 11.4% 11.4% 11.4% 11.4% 11.4%
2 5 1 5 4 .4 5 5 5 2 3 9 9 7 .7 9 5 5 2 3 9 9 7 .7 9 5 5 2 3 9 9 7 .7 9 5 5 2 3 9 9 7 .7 9 5 5
Functional costs 6' 335 6' 335 6' 335 0 6' 335 4' 848 6' 335 6' 335 6' 335 6' 335 6' 335 6' 335 6' 335
in % of revenue 3.0% 3.0% 3.0% 0% 3.0% 3.0% 3.0% 3.0% 3.0% 3.0% 3.0% 3.0% 3.0% 0.0%
Profit 19' 224 19' 224 19' 224 - 1' 561 17' 663 13' 532 19' 214 17' 663 17' 663 17' 663 17' 663 17' 663 17' 663
in % of revenue 9.1% 9.1% 9.1% - 0.7% 8.4% 8.4% 9.1% 8.4% 8.4% 8.4% 8.4% 8.4% 8.4%
Costs of capital ' 000 ' 000 ' 000 ' 000 ' 000 ' 000 ' 000 ' 000
Risks (CCN+Clo s eOutCCN) -' 010 -' 010 -' 010 -' 010 -' 010 -' 010 -' 010
NCC (CC N+C lo s eOutCCN) ' 000 ' 000 ' 000 ' 000 ' 000 ' 000 ' 000
Improvement (CCN+Clo s eOutCCN) ' 000 ' 000 ' 000 ' 000 ' 000 ' 000 ' 000
Change orders Revenue (CCN+Clo seOutCCN) ' 000 ' 000 ' 000 ' 000 ' 000 ' 000 ' 000 ' 000
Claim Out (CCN+Clo s eOutCCN) ' 000 ' 000 ' 000 ' 000 ' 000 ' 000 ' 000
Risks -1' 840 -1' 840 -1' 840 -1' 840 -1' 840 -1' 840
Opportunities ' 000 ' 000 ' 000 ' 000 ' 000 ' 000
Claims incoming ' 000 ' 000 ' 000 ' 000 ' 000 ' 000
Claims outgoing ' 000 ' 000 ' 000 ' 000 ' 000 ' 000
© Siemens AG 2015
page 20/54 PRM Unrestricted EM TS PO
V 17
LoA As Sold PM80 OEC* Change EAC* Actual* Obligo* Expected POC Work
Cost of sales by category
2016-03-16 OEC to EAC 17-04 17-04 17-04 17-05 17-04 Progress
PM, Engineering 25' 669 25' 669 25' 669 + 1' 551 27' 220 17' 801 1' 244 27' 220 65.4% 65.4%
Products - EM TS TI ' 000 ' 000 ' 000 0 ' 000 ' 000 ' 000 ' 000 0.0%
Products - EM TR ' 000 ' 000 ' 000 0 ' 000 ' 000 ' 000 ' 000 0.0%
Products - EM HP 62' 845 62' 845 62' 845 0 62' 845 62' 845 ' 000 62' 845 100.0% 100.0%
Other Equipment 38' 578 38' 578 38' 578 0 38' 578 32' 805 ' 792 38' 578 85.0% 85.0%
Transportation 3' 089 3' 089 3' 089 0 3' 089 1' 152 1' 141 3' 089 37.3% 37.3%
Installation 10' 537 10' 537 10' 537 0 10' 537 5' 693 2' 776 10' 537 54.0% 54.0%
Civil Works 41' 000 41' 000 41' 000 0 41' 000 22' 683 11' 695 41' 000 55.3% 55.3%
Platform ' 000 ' 000 ' 000 0 ' 000 ' 000 ' 000 ' 000 0.0%
Surcharges and Inclusions 2' 053 2' 053 2' 053 0 2' 053 ' 258 ' 000 2' 053 12.6%
Risk (incl. LD) ' 890 ' 890 ' 890 + ' 011 ' 901 ' 000 ' 000 ' 900 0.0%
Warranty ' 940 ' 940 ' 940 0 ' 940 ' 000 ' 000 ' 940 0.0%
Total 185' 602 185' 602 185' 602 + 1' 561 187' 163 143' 236 17' 649 187' 162 76.5% 76.5%
Cost to aggregated projects ' 000 ' 000 ' 000 0 ' 000 ' 000 ' 000 ' 000 #DIV/0!
n/a ' 000 ' 000 ' 000 0 ' 000 ' 000 ' 057 ' 000 0.0%
Imminent Losses ' 000 ' 000 ' 000 0 ' 000 ' 000 ' 000 ' 000 0.0%
fx effects ' 000 ' 000 ' 000 0 ' 000 ' 000 ' 000 ' 000 0.0%
not PoC ' 000 ' 000 ' 000 0 ' 000 ' 000 ' 000 ' 000 0.0%
© Siemens AG 2015
page 21/54 PRM Unrestricted EM TS PO
V 17
Green Green Lowlights Since the customer is doing GIS project for the 1st time, they are not very technically sound. Our engineering
team is extending all technical supports to customer for Engineering approvals.
© Siemens AG 2015
page 22/54 PRM Unrestricted EM TS PO
V 17
Yellow Yellow Lowlights Customer is not good in making payments to contractors as per customer past record. We have taken a very
aggressive approach for our payments as per T&C of PO.
© Siemens AG 2015
page 23/54 PRM Unrestricted EM TS PO
V 17
Green Green Lowlights Customer has expressed their concern of commissioning the substation by 30th April 17. We are working our
level best to meet customer satisfaction
© Siemens AG 2015
page 24/54 PRM Unrestricted EM TS PO
V 17
6446
F323- GIS
AF79 BRPL-
- 66/11
2FC7 kV
- Substat
EEC3 ion at
- 62OP Mithap EM EM
D6B2 - ur (IN) TS TS
131B 9094 322 62OP- SA Regi 565 2,97 2,97 2,9 12.1
3E04 2 143 90942 C 200 M IN India on IN 5 4 360 12.10% 4 74 360 0% 0.50% 0 370 50 150 150 0 20 370
© Siemens AG 2015
page 25/54 PRM Unrestricted EM TS PO
V 17
© Siemens AG 2015
page 26/54 PRM Unrestricted EM TS PO
V 17
LOA PAC
29/04/16
31/08/17
Contractual
© Siemens AG 2015
page 27/54 PRM Unrestricted EM TS PO
V 17
© Siemens AG 2015
page 28/54 PRM Unrestricted EM TS PO
V 17
© Siemens AG 2015
page 29/54 PRM Unrestricted EM TS PO
V 17
EXPEDITING SCHEDULE
CONTRACTUAL SCHEDULE
© Siemens AG 2015
page 30/54 PRM Unrestricted EM TS PO
V 17
© Siemens AG 2015
Page 31/54 PRM Unrestricted EM TS PO
V 17
© Siemens AG 2015
page 32/54 PRM Unrestricted EM TS PO
V 17
© Siemens AG 2015
page 33/54 PRM Unrestricted EM TS PO
V 17
© Siemens AG 2015
page 34/54 PRM Unrestricted EM TS PO
V 17
© Siemens AG 2015
page 35/54 PRM Unrestricted EM TS PO
V 17
© Siemens AG 2015
page 36/54 PRM Unrestricted EM TS PO
V 17
© Siemens AG 2015
page 37/54 PRM Unrestricted EM TS PO
V 17
© Siemens AG 2015
page 38/54 PRM Unrestricted EM TS PO
V 17
Subtotal TOP5 4'077 45.14% 1'840 '000 4'077 45.14% 1'840 '000 -1'840
Subtotal REST '000 '000 '000 '000 '000 '000 '000
Total identified 4'077 45.14% 1'840 '000 4'077 45.14% 1'840 '000 -1'840
Therein with:
General risk contingency 3'137 28.70% '900 '000 3'137 28.70% '900 '000 -'900
RC for default and delay '000 '000 '000 '000 '000 '000 '000
RC for warranty '940 100.00% '940 '000 '940 100.00% '940 '000 -'940
RC Total 4'077 45.14% 1'840 '000 4'077 45.14% 1'840 '000 -1'840
No risk contingency '000 '000 '000 '000 '000 '000 '000
© Siemens AG 2015
page 39/54 PRM Unrestricted EM TS PO
V 17
No Opportunities as on date
© Siemens AG 2015
page 40/54 PRM Unrestricted EM TS PO
V 17
No Claims as on date
© Siemens AG 2015
page 41/54 PRM Unrestricted EM TS PO
V 17
No NCR as on date
© Siemens AG 2015
page 42/54 PRM Unrestricted EM TS PO
V 17
in INR
OEC NCC CI Claims Change Order Risks Change 6 Change 7 Change 8 Change 9 Others MIKA
Productive - Statutory risk
Hours + Freight risk
© Siemens AG 2015
page 43/54 PRM Unrestricted EM TS PO
V 17
Receivable Summary
Billing and Collection Plan
Less: Collections during the month Apr'17 3'0 17-Aug 0'0 12'4 21'1
© Siemens AG 2015
Page44/54 PRM Unrestricted EM TS PO
V 17
200,000 100,000
Cash In cum
80,000
150,000
60,000
100,000
40,000
50,000 20,000
0 0
16-Q3 16-Q4 17-Q1 17-Q2 17-Q3 17-Q4 18-Q1 18-Q2 18-Q3 18-Q4 19-Q1 19-Q2 19-Q3 19-Q4 20-Q1 20-Q2 20-Q3 20-Q4 21-Q1
© Siemens AG 2015
page 45/54 PRM Unrestricted EM TS PO
V 17
© Siemens AG 2015
page 46/54 PRM Unrestricted EM TS PO
V 17
© Siemens AG 2015
page 48/54 PRM Unrestricted EM TS PO
V 17
© Siemens AG 2015
page 49/54 PRM Unrestricted EM TS PO
V 17
Miscellaneous
Detail of Septic Tank & Soak Pit Approved 02.12.2016 Completed, 13.02. 2017
Design of Supporting Structure for LA & BPI Approved 06.10.2016 Completed, 11.01. 2017
General Details of Supporting Structure for LA & BPI Approved 13.10.2016 Completed, 11.01. 2017
Fabrication Details of Supporting Structure for LA & BPI Approved Completed, 11.01. 2017
Design of Foundation for 66 kV Equipment Structure Approved 22.10.2016 Completed, 11.01. 2017
G.A. & RCC Details of Lighting Mast Foundation Approved 18.10.2016 Completed, 25.10. 2016
Design of 20/25 MVA 66/11 kV Power X-mer foundation Approved 04.10.2016 Completed, 09.12. 2016
© Siemens AG 2015
page 50/54 PRM Unrestricted EM TS PO
V 17
© Siemens AG 2015
page 51/54 PRM Unrestricted EM TS PO
V 17
1st lvl roof bean & slab 140 Sqmt Completed 28.11.2016
Column upto Corbel level GIS Hall and Corbel Beam 8 nos Completed 11.12.2016
Clean room condition of GIS Hall & 11kV Switchgear 1 Lot Completed 15.03.2017
© Siemens AG 2015
page 52/54 PRM Unrestricted EM TS PO
V 17
Equipment (LA, BPI, station transformer, cap. bank) foundation 14 Nos. Completed 05.04.2017
© Siemens AG 2015
page 53/54 PRM Unrestricted EM TS PO
V 17
© Siemens AG 2015
page 54/54 PRM Unrestricted EM TS PO