You are on page 1of 4

Sveučilište u Zagrebu

Fakultet prometnih znanosti

RAILWAY TRAFFIC TECHNOLOGY I

METHODES OF TRAIN ASSEMBLY


doc. dr. sc. Marjana Petrović
Task 1
• It is neccesary to assembly collecting train that
will operate on line that have 9 railway
stations in which train leaves or picks up
wagones. On a track there is sequence of 25
wagons where name of railway station is
represented by number of that station (from 1
to 9). In order to assembly train you should
use Futtner methode.

www.fpz.unizg.hr
Task 2
• On the track there is sequence of 38 wagons
that you should use to assembly train using
Futtner methode. Names of railway station are
replaced with the number of the station.

www.fpz.unizg.hr