Professional Documents
Culture Documents
Specification Issues
1
2
Power Transformer Technical Specification
During 2006 and 2007 to date, an unusually high number of requests have arrived for
Technical Specification reviews, both in New Zealand and Australia.
More than six power transformer Technical Specifications for machines over 200MVA in
New Zealand alone.
The challenges of a significantly loaded electrical network reliant on service aged
equipment: refurbish and/or replace.
The challenges of increasing load and “new” generation types e.g. wind turbines.
The commodity price issues (copper, electrical steel, structural steel and oil).
The changes from well established European factories to new South East Asian
manufacturing sites.
The need for form relationships with new people (new manufacturer personnel, new
employers/clients).
It may be that power transformer Technical Specifications has become cumbersome,
out of focus and needs a
“spring clean”.
The peer review process: are our ideas good ones?
3
Why Have a Technical Specification?
4
2. The Single-Point Earthing of Power
Transformer Cores, Frames and Tanks
The insulation is failing.
Dissolved Gas Analysis tests are being over-run withalarming gas signatures. repair bill
is significant.
What is the Industry going to do about it?
Why are expected Partial Discharge pass levels being set at 50% of the value specified
in the IEC International Standard for new transformers?
5
4. On-Load Tap-Changers on Generator
Step-Up Transformers
More and more tapping ranges. Lower and lower tap sizes.
Why – the generator has an Automatic Voltage
Regulator?
5. Transformer Cooling
ONAN/ONAF/ODAF versus ODW versus ONAN? When should we buy straight ONAN
machines?
Reliable, not dependent on l.v. systems, and simple.
ONAN/ODAF may be significantly more cost effective above 65MVA?
6
PART 1. FIRE & EXPLOSION
PROTECTION
What is considered an acceptable level of fire and explosion protection that
should be specified for power transformers in thefollowing scenarios?
8
steam and gas plant than hydro. All money and susceptible to damage.
Nitrogen.
Enclosure.
Fire Wall.
Blast walls in all critical areas.
Design of location.
Fast acting protection
c) A generator step-up transformer connected to a
hydro-turbine unit
Environmental risks - oil contamination of lakes / rivers, etc. Containment of full volume of
oil.
Buchholz relay.Pressure relief.Vented cable box.Generator circuit breaker.
Bushing monitoring. Conservator tank isolation.
Choice of oil.Temperature indicators.Fire protection (foam).GSU transformer - generator
CB – required.
Water sprinklers and oil interceptor.
Hydro in environment sensitive areas, must
consider heat and oil.
Environmental issues are important, especially oil
containment.Deluge.
9
Condition Based Management
Define asset condition (Health Index)
Link condition to performance & probability of failure
(PoF)
Calibrate Health Index/PoF against historic fault
rates
Estimate future condition and performance
Evaluate effect of investment programmes on future
condition and performance
Provides an ENGINEERING basis to evaluate risk
and determine investment requirements
10
d) Any power transformer greater than 100MVA
Physical separation (firewalls if duplicate units). Possible use of
‘Sergi’ protection, etc.
Positioning transformers away from station. However, look at the
economics.
Environmental risks - oil contamination of lakes / rivers, etc.
Containment of full volume of oil.
Buchholz relay. Pressure relief.Vented cable box.Generator circuit
breaker.
Bushing plus monitoring. Conservator tank isolation.Choice of
oil.Temperature indicators.Fire protection (foam). Blast walls and
sprinklers on wall.
Conservator shut off valves. Options: foam, water curtain, CO2,
FR3™.
Sergi system economical for larger units.
11
High velocity water spray system. C02 for sealed enclosures.Fast acting digital
protection.Sergi transformer protection or gas insulated transformer.
High velocity water spray system.C02 for sealed enclosures.Fast acting digital
protection. Sergi transformer protection or gas insulated transformer.
General Notes:
All scenarios require risk assessment. Consider use of polymer bushing i.e.
GSA, etc.
All scenarios depend on transformer size and blast wall requirements.
Oil containment bunding with fire-traps/ drainage.
Situational considerations – not one answer for all remote transformers or all
hydro, etc. All situations consider:
NFPA850 Guidelines – but these are only guidelines, but you must go
through and specify.
Blast walls for specified separation.
Bunding w/ drainage to suffocate fire.
Shutter valves on conservators.
Differential Protection.
12
PART 2.THE DETAILED DESIGN
REVIEW
When the Detailed Design Review process is specified: a) Employers
(Clients), what Detailed Design
Review (DDR) outputs do you require and why?
Using knowledge of supplier to tailor client requirements.
Adding value to project.
Specifically reviewing: component mounting,
footprints, weights, shape, oil volumes etc.
Reconfirmation of 'no surprises' / confirmation that supplier has the ability to
deliver.
Compatibility with existing spares / stock, intercompatibility with existing
network.
Key scope requirements.
Fit for purpose.
Delivery.
Inspection process.
Transport / shipping to site.
Site constraints.
Performance criteria. 13
Cooling plus interlock systems.
Material listing.
Acceptance tests.
Type tests / compliance.
Special tests.
Material quality.
Review of mechanical design.
Review of loss calculations.
Scope of DDR and timing of review at supplier.
Compare DDR outputs to specification clauses.
Special transformers need proper DDR.
Report on basis of IEC and CIGRE DDR guide documents.
Result is confidence in the transformer design.
14
Provide alternatives.
Assurance that the design will work and meet specifications.
Provides assurance that the employer is getting what we want.
Facilitates forum for improvements in design that may impact on
overall cost and performance.
Gain understanding of the design so we can gain understanding of
test results.
Find any steps in design/manufacture that you want to witness to
help with maintenance
15
b) Contractors (suppliers), what are the key matters that will
influence the power transformer detailed design that you
need the Employer (Client) to clarify?
Ensuring spec following best practice.
Possible provision of future on-line monitoring equipment.
What is important to client i.e. on time, cost, etc?
Confirmation of spec / deviations.
QA (Quality Assurance) requirements.
Drawing, documentation, manuals, maintenance procedures.
Required specs.
Seismic requirements.
Weight - gross, transport.
Dimensions - centre of gravity.
Terminations.
16
Specification does not cover all details. Need DDR these details,
Allows agreement on these details.
No DDR for standard transformers only one off/New Designs.
Also discussed customer acceptance Clarification of:
Out of date standards included in spec.
Standard Designs i.e. 6MVA spec but a 7.5MVA standard –
cheaper, faster, and easier.
Component specification – e.g. bushings, colour, tap changer
type – This may effect delivery and cost.
Transport issues.
Paint colour.
Factors relating to delivery and cost.
Component specification – e.g. bushings, colour, tap changer
type – This may effect delivery and cost.
Transport issues.
Paint colour.
Factors relating to delivery and cost.
17
Need to know in spec if employer wants In general, this is a
very important process that is important for both parties. It aids
clarification andunderstanding of how to proceed with
designb(contractor) and provides a certain level of
optimisation for the employer (client) i.e. relationship influence on
design e.g. stress levels or specific short circuit.
Need employer to have expertise or a contractor to be brought
in.
General Notes:
Should a detailed spec be required? How about the customer
saying we need a transformer to fill this space, these are the
connections, go to it. However, still a lot of things need to be
known. Different tolerances are not always required, overbuilding,
etc. It’s about relationship/confidence in supplier. QA systems,
review, etc. should be done before specifications i.e. due
diligence.
Standardisation of one set of designs does not always work, as
component costs may change meaning the set design is no longer 18
PART 3. TECHNICAL
SPECIFICATION EXPERIENCES
a) From an Employer (Client) and / or Contractor
(Supplier) perspective, what information must be
given in a 2007 Technical Specification?
Refer to standard lists. MVA, voltage, impulse, tap changer,
connection, vector group, and seismic. Intended application.
Rating, MVA, kV. Vector group. Cooling, type of oil.
Impedance. Tap-changer, plus minus percentage.
Load profile.
Regulation.
Standards (manufacturers).
List of accessories.
Type of bushing.
Short circuit withstand capability.
19
Seismic.
System earthing.
BIL (Basic Insulation Level).
Loss evaluation formula.
Guaranteed losses.
Corrosion protection.
Tank strength.
Noise level.
Phase clearance, spacing.
Creepage distances.
Surge arrestors.
Cable box, open bushings.
CT (Current Transformer) requirements,
protection.
Remote tap changing.
Station voltage
20
Refer to AS60076.1 appendix A as a minimum requirement.
Site requirements – Footprint, Transport etc.,
MVA, Voltage, Losses, Vector group. Bushing types, taps,
terminations, SCADA interfaces, protection devices, auxiliaries,
voltage, and cooling and seismic requirements.
Finishing – Painting, galvanising, wielded or bolted.
Documentation for transfer and timetable.
As built, maintenance manuals, specs, wiring specs and code.
Standards AS/NZ and IEC.
Relevant standards.
General characteristics / performance criteria
Auxiliary components / systems.
Arrangement of transformer; dimensions; bushing/terminal
layouts; site requirements;
system requirements.
21
Voltage, vector group, frequency, noise requirements (sound
pressure, sound power,
distance), loss’s, rating, list of standards that it must comply to,
Overload rating, ambient temperature, earthing, fault level,
environment, seismic requirement, altitude, typical rang of
impedance, tap rang, type of entry.
22
Too prescriptive specs i.e. 'old school'
Too many standards.
Insistence on copper winding.
Totally useless offload sufficient.
Specification of duplicate/overlapping test
requirements ( contributes to additional cost/time) e.g.
stating two test methods to gain same result,
such as megger vs. sweep frequency tests.
Irrelevant/out of date standards.
PD (Partial Discharge) test requirements NZ/AUS
very low – almost impractical.
Radiator specified to be both galvanized and
painted.
Colour of bushing in cable box.
Items that are contradictory. 23
Items that are out of date.
c) Why are on-load tap changers being fitted to generator
step-up transformers and what are the implications of
increasing tapping ranges and decreasing step sizes?
Insurance policy.
Guarantees and flexibility?
Transformer design.
Old school, conservative.
Asset owner compliance.
More voltage regulation required.
Near load centres.
Increase tap range: extreme ends of tap settings are not used.
Totally useless offload sufficient.
More leads and more introduced points of potential failure.
24
EGR (Electricity Governance Rules) requirements impact on generators
ability to
support/import reactive power is severe.
Tap changers are not needed on generator transformers with an AVR
(Automatic Voltage Regulator).
d) Is single-point earthing of core, frames, and tanks
a good approach? What happens when the single
point earthing fails?
Good idea! Cost trade-off on insulation may be agreed acceptance testing
completed.
In service for specified period and handed over.
On site install / commissioning completed and documentation complete.
Fence sitting: cost of coping with circulating current vs. single point.
Want device that is reliable regardless of design
Choice of single point earthing or not is a trade
off between equipment costs and losses. The “best” will vary with
circumstances.
25
Residual Life Estimates-NZ network transformers
27
What could be done during refurbishment
29
Testing of
transformers
30
Testing of Transformers
Post refurbishment, testing is done only at low voltage
Emphasis on Insulation resistance test post refurbishment
Minimum acceptable value is specified based on TMI-US guidelines
IR & PI values are often not achievable due to the transformer capacitance
IEC standards do not specify a minimum value
Minimum value for Insulation Resistance should be specified independent of
kVA Rating
We recommend
50Hz separate source voltage test at 75% rated value for refurbished
transformers
No-load excitation at 100% voltage for 30 minutes for refurbished transformers
31
Partial Discharge test
Post repair, a partial discharge test is specified
IEC 60076 recommends PD test for transformers with
Um>300kV
Some clients insist on this test for lower voltages
Values specified are 50% of IEC recommended values
The transformer is manufactured 25-30 years ago
Only part of the winding is replaced
The transformer was originally not subjected to a PD test
Is it practical to achieve such low levels?
The PD test is conducted in an unshielded environment
32
Repair of transformers
33
34
Repair of Transformers
While formulating repair specifications, we recommend
Testing of the replacement winding for turns ratio, resistance and inter-strand
tests
prior to shipping the windings to New Zealand
This will involve the windings be put on a transformer core
But it is recommended
We have had failures of replacement windings having
Centre entry and two halves in parallel
Unequal turns between parallel halves
Recommend the involvement of replacement contractor in inspecting the
winding prior to shipping
to avoid surprises / delays upon arrival in New Zealand
Specify PD levels to which transformer will be tested to the replacement
winding manufacturer
35
Transformer life time
The Transformer life expectation is measured by
the Rate of Degradation of the Insulation
normally this Insulation is cellulose paper.
The expectation of transformer end life can be
indicated by the degree polymerization of paper
approximate 200 (and other indications).
37
Cellulose Conductor Insulation Ageing
38
TRANSFORMER LIFE TIME – CELLULOSE DESIGN
40
TRANSFORMER LIFE TIME – CELLULOSE
DESIGN
41
Temperature Rise and Driven Factors
Temperature Rise for Class A (IEC 60076-2/ ANSI C57);
Top oil rise ; = 60K / 55 K or 65 K.
Average oil rise ; = 65 K / 55 K or 65 K (By resistance method)
Hot spot rise ; = 78 K / 65K or 80K.
Site elevation height;
The standard elevation height is 1000 m above sea level.
Climatic temperature behaviors;
Yearly average ambient temperature (IEC std = 20oC) transformer life time.
Hot monthly average ambient temperature (IEC std = 30oC)
Maximum ambient temperature (IEC std = 40oC) transformer loading capability
42
43
44
45
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78