Professional Documents
Culture Documents
Structural frames
Steel.
Concrete.
Timber.
Concrete
States of concrete
Concrete hydration
Concrete solidifies and hardens after mixing
with water and placement due to chemical
process known as hydration.
15 1:3:6 1 3 6
20 1:2:4 1 2 4
25 1:1½:3 1 1½ 3
40 1:1:2 1 1 2
Accelerators
Retarders.
Mixing of concrete
The mixing operation consists of rotation and
stirring, the ingredients of the concrete to uniform
mass.
This uniformity must not be disturbed by the
process of discharging from the mixer.
There are several types of concrete mixers are
used to mix concrete.
Some of them are batch mixers, tilting drum
mixers, pan type mixers & continuous mixers.
Batch mixer
Tilting drum mixer
Pan type mixer
Continuous mixer
Concrete mixers
The efficiency of the concrete mixer can be
measure by the viability variability of the samples
from the mix.
27
BS 5975 (BS code of practice for False
work) defines falsework as: Any temporary
structure used to support a permanent
structure while it is not self-supporting.
28
Formwork
29
It must be designed,
– To allow the concrete to form into the required shape
and dimensions
– To support the concrete, the people working on the
structure, plant required for placing concrete and
weather loadings until the concrete cures sufficiently
to become self-supporting.
30
31
Formwork system is the key factor
determining the success of a construction
project in terms of,
– Speed
– Quality
– Cost
– Safety of works
32
Considerations in using formwork
Design related considerations
Shape of the building.
Architectural features on building exterior.
Internal layout.
Structural form.
Building dimensions.
Span.
Finishing standard.
33
Considerations in using formwork
Construction related considerations
35
Able to struck without damage to the concrete or to
itself.
36
Joints between members must be tight enough to
prevent grout leakage.
37
Types of formwork
Foundation formwork
Column formwork
Beam formwork
Slab formwork
38
Beam formwork
The removal time for the formwork will vary with air
temperature, humidity and consequent curing rate
40
Beam formwork
41
Beam formwork
42
Formwork for beams
43
Column formwork
Consists of a vertical mould of the required shape and
size which has to retain the wet concrete and resist the
initial pressure caused by the wet concrete.
44
Alternatively the column can be cast to the underside of
the beams.
45
Column formwork
46
Foundation formwork
If the formwork is firm & hard, it may be possible to
excavate the trench for the foundations to the size & depth
required & cast the concrete against excavated faces.
47
Foundation formwork
48
Slab formwork
Floor or roof slab formwork consists of panels
of size that can be easily handled. The panels
can be framed or joisted & supported by the
beam forms with any intermediate propping
which is required .
49
Site work in relation to formwork
51
The formwork should be cleaned immediately
after striking & should be stacked for reuse.
54
Materials for formwork
Timber
Plywood
Steel
Plastic and rubber
In some situations concrete, if the formwork is
permanent.
55
Timber forms
Timber used for formwork must satisfy the
following requirements:
– It should be durable and treatable.
– It should have sufficient strength characteristics.
– It should be light weight and well seasoned
without deforming.
– It should hold nails well.
56
Advantages of using timber forms
Economical for small construction jobs.
Design is flexible and easy to erect.
Has good thermal insulation which makes it
useful to be used in colder regions.
Can easily be made into any shape or size.
57
Steel formwork
Mostly used in large construction projects or in
situations where large number of re-uses of the same
shuttering is possible.
58
Advantages of steel formwork over timber forms
59
Aluminium forms
– Aluminum forms are in many respects similar to
those made of steel.
– Due to their lower density, aluminium forms are
lighter than steel forms,& this is their primary
advantage when compared to steel.
60
Aluminium forms
– As the strength of aluminum in handling, tension and
compression is less than the strength of steel, it is
necessary to use large sections.
– The formwork turns out to be economical if large
numbers of reuses are made in construction.
– Major disadvantage of aluminum forms is that no
changes can be made once the formwork is fabricated.
61
Aluminium formwork system for residential housing block
62
Plastic formwork
Used for casting unique shapes and patterns &
a good finish can be obtained requiring
minimum or no surface treatment and repairs.
64
Plastic formwork…..
65
Checks before concreting
Are bolts and wedges secure against loosening due to
vibration?
Has the right number of ties used and are they in the
right position?
Are all ties properly tightened?
Have the stop-ends being properly secured?
Have all the joints been sealed to stop grout loss?
Is the formwork correctly aligned and leveled?
Are all the props plumb? And at the right spacings?
Are all the props and struts properly tightened up and
locked? 66
Checks before concreting
Can the formwork be struck without damaging the concrete?
Has the release agent being applied? Is it the right one?
Is the reinforcement correct?
Has the reinforcement the right cover? Are there enough
spacers?
Are the forms clean and free from rubbish?
Is there proper access for concreting and compaction?
Is all ancillary equipment available, such as vibrators,
lighting, skips and hand tools?
Is the curing equipment and covers ready?
Have all the necessary guard rails and toe boards are been
provided?
67
Defects on finished concrete surfaces
Two defects which can occur on the surface of finished
concrete are,
• Blow holes – small holes less than 15 mm in diameter
caused by air being trapped between the concrete and the
formwork
• Uneven colour - caused by the water in the concrete being
absorbed irregularly into the formwork. A mixture of old &
new materials increase this defect.
68
Mould oils & emulsions
Mould oil can be applied to the inside surface of
the formwork to prevent uneven colouring
problems. Mould oil which incorporates an
emulsifying agent will discourage blow holes
and reduce uneven colouring.
69
Scaffolding
Temporary working platforms erected
around the perimeter of a building or a
structure to provide a safe working
place at a convenient height.
Usually required when the working
height is 1.5m or above the ground
level.
Includes any working platforms,
ladders and guard rails. Basically there
are two main types of scaffolding.
Putlog scaffolds.
Independent scaffolds.
70
Putlog scaffolds
Consists of a single row of uprights or standards set
away from the wall at a distance that will
accommodate the required width of the working
platform.
Standards are joined together with horizontal
members called ledges and are tied to the building
with cross members called putlogs.
Putlogs are built into the bed joints or perpend as
work proceeds.
Only suitable for new work in bricks or blocks.
71
72
Independent scaffolds
73
74
Working platforms
These are close boarded or plated level surfaces at a
height at which work is being carried out and they
must provide a safe working place of sufficient
strength to support the imposed loads of operatives and
materials. All working platforms above the ground
level must be fitted with a toe board and a guard rail.
75
Mobile scaffolds
These are also called
mobile tower scaffolds.
They can be assembled
from pre-formed framing
components or from
standard scaffold tubes
and fittings. These are
used mainly for property
maintenance and must not
be moved while occupied
by persons or equipment.
76
77
Scaffold materials
Tubular steel
Tubular aluminium alloy
Timber
78
Concrete placing
The operation of placing ensures the requirement of
strength, impermeability and durability of harden
concrete in the actual structure.
As far as placing is concerned, the main objective is to
deposit the concrete as close as possible to its final
position so that segregation is avoided and the concrete
is fully compacted.
The aim of the good concrete placing can be stated as,
is to get the concrete into position at a speed and in a
condition, that allow it to be compacted properly.
By manually
By manually
By using concrete chutes
By using concrete chutes
By use cranes and buckets
By use cranes and buckets
By using concrete pumps
By using concrete pumps
Compaction
Once the concrete has been placed , it is ready to be
compacted.
The purpose of compaction is to get rid of the air voids
that trapped in loose concrete.
It is important to compact the concrete fully because air
voids reduce the strength of the concrete.
Air voids increase concrete’s permeability. That in
turns reduces its durability.
If the concrete is not dense and impermeable, it will not
be watertight.
Compaction
Moisture and air are more likely to penetrate to
the reinforcement causing it to rust.
“Honey combs” may occur due to the air voids.
To compact concrete you apply energy to it so
that mix becomes more fluid. Air trapped in it
can then rise to the top and escape.
As a result, the concrete become consolidated
and left with a good dense material.
Methods of compaction
Rodding: rodding is a manual technique and are
only suitable for work of foundations and
columns.
Vibration: is the quickest and best method to
compact concreter.
Porker vibrators are used for this purpose. Porkers
with diameter ranging 25 and 75 mm are readily
available and these are suitable for most
reinforced concrete work.
Internal & external vibration
External Vibration
Use of porker vibrators
Use of porker vibrators
Use of porker vibrators
The length of time it takes for a porker
vibrator to compact concrete fully depends on:
– The workability of the concrete: the less workable
the mix, the longer it must be vibrated.
– Bigger vibrators do faster job in compaction.
– The depth of the concrete: thick sections of the
concrete take longer for compaction.
Proper placement and compaction of
concrete
To achieve proper placing and compaction following rules
should be kept in mind.
– The concrete should placed in uniform layers not in large heaps
or slopping layers.
– The rate of placing and of compaction should be equal.
– On no account should water ever be added to concrete in setting.
– Each layer should be fully compacted before placing the next
one, and each subsequent layer should be placed whilst the under
lying layer is still plastic so that monolithic construction is
achieved.
– Collision between concrete and formwork or reinforcement
should be avoided.
Curing
Care needs to be taken to properly Cure concrete
and to achieve best strength and hardness.
This happens after concrete has been placed.
Cement requires a moist, controlled environment
to gain strength and harden fully.
Cement paste hardened over a time and in around
3 weeks , over 90% of the final strength is
typically reached , though it may continue to
strengthen for decades.
Curing
Curing