You are on page 1of 44

Project Management

Gannt Chart/CPM/PERT

Prof. ajayakumar vt
9447832662
What is a project
Characteristics of Projects
•Unique task- not repetitive/do correctly every
time
•Temporary task-
•Group task- knowledge, skill, techniques

2
What is Management
• To manage is to forecast plan, to organise, to
command, to co-ordinate and control.

Planning scheduling and controlling of


complex and interrelated job activities.

3
Project Management
• It’s a temporary group activity designed to
produce a unique product, service or result.
(pmi)
• PM is discipline of planning ,organizing,
securing and managing resources to bring
about successful completion.(wiki)

4
PM
• Pm is application of knowledge, skills, and
techniques to execute project effectively
and efficiently.(pmi)

5
Process and Project Management
• Process- Repetitive

• Projects-Unique

6
Project Examples
– Constructing houses, factories, shopping malls,
athletic stadiums etc.
– Developing military weapons systems, aircrafts,
new ships
– Launching satellite systems
– Constructing oil pipelines
– Developing and implementing new computer
systems
– Planning concert, football games, or basketball
tournaments
– Introducing new products into market

7
Project Planning
• Resource Availability and/or Limits
– Due date, late penalties, early completion
incentives
– Budget
• Activity Information
– Identify all required activities
– Estimate the resources required (time) to complete
each activity
– Immediate predecessor(s) to each activity needed
to create interrelationships
8
Project Scheduling
• Setting of sequence of Activities in a time
scale, ie setting of resources in a time scale
to perform jobs

9
Project Controlling
• Control on resources and time
• Updating of progress of activities.

10
Unique features of Construction
Projects
• One time Activity- to be perform correctly every time.
• Complexity-a set of interrelated task to be done by
specialists.
• High cost and Time
• High risk features
• Difficulty in defining quality standards
• Feedback Mechanism

11
Unique features of Construction
Projects
• Lack of experience of client or owner
• Untrained workers.

12
Project Scheduling and Control Techniques
Gantt Chart
Critical Path Method (CPM)
Program Evaluation and Review Technique (PERT)

13
Phases of Construction Project

14
Try it out?
• Digging foundation-20 weeks
• Erecting of shutters-12 weeks
• Pouring of concrete- 16 weeks

Total period required to complete the work?


Try it out to demonstrate the above jobs as a
graph or a picture?
15
Total period is 48 weeks.
Try it out to complete the work within 36 weeks
16
Define GANTT CHART
A
B

C
D
E
activity

time

17
Gantt Chart
• Developed by Henrry Gantt in 1900
• Pictorial representation of complex project
activities.
• Consist to two axis
• X- axis for Time Y-axis for Activities
• Bars represent activities and its length for
time/duration of activity
18
• Various jobs with estimated time and
money can be marked on time scale
• some bars run parallel-concurrently
• Some bars run serially- sequential order
• Some bars overlaps each other- take
different time span for ctivity.

19
20
21
22
23
24
BAR CHART WEAKNESS
Interdependency:
•Serious deficiency bar/gantt chart is cant
show interdependencies among the activities.
• Digging of fdn- 20 weeks
Erecting the side shutter- 12 weeks
Pouring of concrete- 16 weeks
Can you complete the work within 36 weeks?
25
Bar chart weakness

26
• Some activities not allowed to overlap by
time
• Some activities can proceed simultaneously
• But conditions and relationships between
the activities cant be explained and
demonstrated.

27
Weakness of bar chart
Progress of project:
Normally does not show the progress of work
project.

28
Weakness of bar chart
Uncertainties
Tolerance in duration times estimated for
various activities not reflect in bar chart.
Because of the technological progress, the
traditional knowledge or practices play a very
insignificant role. In such situation jobs cant
be forecast with exactness.

29
Mile stone chart
1 2 3

4 5 6

7 8

30
MILESTONE CHART

31
MILESTONE CHART
• Modifying the bar chart by adding new
elements is called mile stone chart or system.
• Mile stones are key events or points in time
which can be identified as the project progress.
• A long term job is broken down to several
pieces, each of which stand for an identifiable
majaor events.

32
Mile stone chart

33
Mile stone chart
• Each event is numbered. This work
breakdown increases the awareness of the
interdependencies between task.

• This is the basic concept of CPM and PERT


net work structures.

34
35
36
Work breakdown structure
• A mile stone structure demonstrate the
work breakdown structure.
• it bring into picture the functional elements
of a programme and their interrelationships.
• This is achieved through what is known as
the work breakdown structure.
• It establish hierarchical order in a system.

37
Work breakdown structure
• A method of breaking down a project into individual
elements ( components, subcomponents, activities and
tasks) in a hierarchical structure which can be scheduled
and cost
• It defines tasks that can be completed independently of
other tasks, facilitating resource allocation, assignment
of responsibilities and measurement and control of the
project
• It is foundation of project planning
• It is developed before identification of dependencies and
estimation of activity durations
• It can be used to identity the tasks in the CPM and PERT

38
39
• The breakdown is continued until the
assembly is reduced to elements or
components representing manageable units
for planning and control.

40
• The breakdown could be either end item
oriented or product oriented.
• End item Oriented units:-which form a
necessary part of the final item.( a control
unit in the final deliverable system)
• Product oriented unit- organisational or
service units which are also essential for the
completion of project.
41
You are a Project
Engineer/Manager!
Can you asses the following
•Earliest start time?
•Earliest fish time?
•Latest start time?
•Latest finish time ?
•Do you have any free time b/n activites?
•Which activities controls the project duration?
42
• How you can allocate resources to each and
every activity.
• What you do if there is limits on resources
• You want to reduce the project time. What
do to crash the time?
• How the crashing relating to cost of
projects?
43
44

You might also like