Professional Documents
Culture Documents
1 3
4
Activity on Arrow
2 4 5
1 6
3
Lag Time
For example,
if there must be a two-day delay between the finish of one task
and the start of another, you can establish a finish-to-start
dependency and specify two days of lag time for the successor
task.
Chapter 6-18
A node has duration
Node represents an activity
Activity has duration
All activities except the first and the last activity
must have:
At least one activity entering them
code
Program
install
test
Data
Take on
Fragment of precedence network
Rules for formulating activity on node Network Model
Chapter 6-21
6.16 Activity-On-Arrow Networks
Fragment of A CPM Network - Events
Chapter 6-23
Rules for formulating activity on node Network Model
Chapter 6-24
6.8 Formulating A Network Model
Resolving The Dangle
The figure implies that the project is complete once the
software has been installed and the user manual written
We should redraw the network with a final completion activity
Activity B Activity D
Activity C
Burst Activities
Activity B
Activity A Activity C
Activity D
Forward Pass
Forward Pass—Earliest Times
Earliest dates on which activity may be started or
completed, assuming that we know the actual start
date
How soon can the activity start? (early start—ES)
start 28 H 30 Finish
24 F 28
Analysis Present
4 2
11 G 20
Design
9
Here development analysis and design wont be linked with start instead
other activities would be linked other than start
FORWARD PASS
Activity Duration predecessor
A 5
B 7 A
C 4 A
D 10 B
E 3 C
F 5 C
G 6 D,E
H 4 G,F
Backward Pass
Backward Pass—Latest Times
Latest date at which the project may be
started and finished without delaying the
end date of the project
How late can the activity start? (late start—LS)
How late can the activity finish? (late finish—
LF)
Late Finish (LF) = LS + Dur
Backward Pass
There are three steps for applying the
backward pass:
Subtract activity times along each path through the network
(LF – Dur = LS).
Carry back the LS time to the activity nodes immediately
preceding the successor node. That LS becomes the LF of
the next node, unless the preceding node is a burst point.
In the case of a burst point, the smallest succeeding LS
becomes the LF for that node (because the latest the
predecessor can finish is when any one of the successor
activities should start)
Backward pass example
Backward pass
10 17
0 2
6.12 Identifying The Critical Path
The Critical Path [2/3]
E
B Dev. Present.
Design 6
5
A
Contract
5 F H
D
Survey Analysis Present
13 4 2
C
Market ID G
6 Demog.
9
Path One: A-B-E-H = 18 weeks
Path Two: A-B-D-F-H = 29 weeks
Path Three: A-C-D-F-H = 30 weeks
Path Four: A-C-G-H = 22 weeks