Professional Documents
Culture Documents
FOR AREAS OF
RESPONSIBILITY
IN THIS CHAPTER, WE WILL LEARNS
Mission
Goals
objectives
Strategy
Tactics
Operational
Plan
1.3.The business plan
What to to in future?
How to do it?
When to do it?
Who should do it?
1.3.The business plan
level Activity
Smart principle
f i c
e ci
Sp b le
u r a
e as
M
ab l e
c h iev
A
R ele v a n t
Realistic /
SMART
Timetable
Coordination
Cascading of
organizational goals and objectives
Specific objectives for each member
Participative decision making
Explicit time period
Performance evaluation and feedback
MBO Strategy : Three Basic Parts
Disadvantages
The development of objectives can be time consuming,
leaving both managers and employees less time in which to
do their actual work.
Systems An agree- upon plan or process for carrying out an activity: ex:
accounting system, MIS
Policy General statement that provide guideline for management
decision – making
Procedure Are chronological sequences of actions required to perform a
task. They have 3 main advantages: efficiency; routine,
standardization
Rules Prescribes a specific, definite action that must be taken in a given
situation
Programs Are coordinated group or series of plans, which together achieve
a particular objective
Budgets
3.2. Office procedures and systems
3.2. Office procedures and systems
Effective system and procedures should ensure that:
Relationship with customer are effectively managed
Relationship with suppliers are effeftively managed
Office functions interrelate properly and are not duplicated
Example:
Cheques over a certain amount to need two
signatories
Effective credit control procedures
Computer security procedures and access levels
3.3. Financial control procedures
Marketing
Marketingstrategy
strategy
Meet
Meetcustomer
customerexpectation
expectation Create
Createcustomer
customerpreferences
preferences
better
betterthan
thanthe
thecompetition
competition for
forproducts
productsand
andservices
services
Competitive
Competitiveadvantage
advantage Competitive
Competitiveadvantage
advantage
5. Product policy.
5.1. Product development
Product means everything that is used by a firm to provide consumer
satisfaction.
Learned
6 Project management
6.1. What is a project?
6.2. Planning and resourcing technique
6.3. Projecting network
6.4. More projecting planning tool
1. What is a project?
Sequencing the work down, so that resources can be allocated in the most convenient way
• Example:
Testing
Costs
- Direct
- Overhead
Considerations
- Total materials
- Lead times
- Contingencies
- Additional work escalation
Estimating job time
Duration
Earliest start
Latest start
Gantt chart
6.3. Projects as networks
1. Network analysis
2. The critical path, event times, floats
3. Crashing activity
4. Uncertain activity durations
5. Criticisms of critical path analysis
1. Network analysis
allocate resources
Event Event
Activity Activity
A B
1 2 3
1. Network analysis
• Neither activity D nor E can start until C is completed, but D and E could be done at
the same time if required.
D 3
1 2
C
E 4
• H can’t start until F and G are both complete
1 F
H
3 4
2 G
Example: Draw network for project building a factory
3
1 2 4 5
2 C 3 D
dummy
A 5
1 4
B E
The critical path, event times and floats
• The critical path is the path through the network with the greatest total duration
• A network can have more than one critical path, if several paths tie for the greatest
duration
• Activities on the critical path must be started and completed on time, otherwise
the total project tie will be extended
Example:
Latest event time is the latest time by which all preceding activities must be
completed if the project as a whole is to be completed in the minimum time
Event
number
Latest event time
The critical path, event times and floats
• The float for any activity is the amount time by which its
duration could be extended up to the point where it would
become critical
• It is a bar chart showing the number and mix of staff over the duration of the project
• It is used to plan and control the human resource requirement of the project
Resource histograms