INRM (ABF)

Team- Churchu
Engagement with Panchayat and
Community
 Capacity building of PRI on their role and
responsibilities in Strengthening panchayat
and executive committee.
 Orientation and capacity building of PRI on

INRM, MGNREGS processes and different


circulars.
 Village level meeting/Rally in all panchayats.
 Training and Regular meeting with SHG, VO

on MGNREGA and INRM.


Best Practices
 Strengthening Gram Sabha-MGNREGA Act provisions, Process, INRM
planning.
 Beneficiaries Group meeting.
 Scanning the gaps and grooming of laborer and SHG mates.
 Video dissemination on INRM in local language.
 Capacity and knowledge building of beneficiaries for asset utilization.
 Try to assure that GRS can present the MGNREGA work in front of PRI
members.
 Assure the relation with SHGs mates, SHGs, PRI members and Block
functionaries.
 Work demand generation.
 Application from SHGs to sanction INRM schemes and women friendly
schemes.
 Exposure to different location where INRM planning and Mango
Plantation activity has taken place.
Progress (FY 2019-20 and 2020-21)
S no. Activity Plan Achievement Amount
Mobilized
1 No. of villages where
INRM Based Planning is
done & Executed
2 No. of Water Harvesting 24 4553060
Structures(Tanks/Pond/
Dobha)
3 On- Farm Field Bunding, 99 3291424
TCB in Acre.
4 Didi badi Yojna 51 973800
5 Mango Plantation 84 30663115
Total 258 39481399
Challenges
 Timely payment to NREGA labours
 Some time does not support from block
administration for sanctioning of land
treatment schemes.
 Less engagement of GRS.
 Due to COVID-19 less participation of
villagers and PRI members in Planning
process.
Thank you