Professional Documents
Culture Documents
1
SYLLABUS
2
CAUSES OF DISPUTES
A combination of environmental and behavioral factors can lead
to construction disputes.
The five most common causes
1. Contract errors or omissions
The biggest reason for construction disputes is one that can be perhaps most easily
avoided. A thoroughly vetted contract that is fully agreed upon by all parties can save
a huge headache down the line
2. Differing site conditions
While a construction bid is based on the assumption that site conditions are reflected
within the initial package, this is often not the case. Subsurface condition differences
and other unexpected changes can be a large cause for constriction disagreements.
3. Noncompliance of contractual obligations
While a well-worded contract can be a difference maker, it’s sometimes not enough.
If a contractor, sub-contractor, employer or any other party fails to comply with their
obligations, the other parties involved will generally try to seek recourse.
3
4. Failing to correctly administer the contract
Again, a contract issue is at the heart of the disagreement, underscoring the
importance of drafting a strong, agreed upon and respected contract.
5. Claims errors
Whether a claim is poorly drafted or even unsubstantiated can make a big difference.
Attorneys often define claims in contracts for this very reason.
OTHER CAUSES ARE:
Quality and Workmanship, Site conditions etc.
4
TYPES OF DISPUTES
Claim: Demand for something considered one’s due
Claims of Contractor against Owner/Client
Claims of Owner/Client against Contractor
Sub-contractor’s claims
5
Claims of Contractor against Owner/Client
6
Claim Generating Circumstances
1. Delay in the supply of drawings and clarifications
2. Defects in the specifications furnished
3. Delay/manufacturing defects in materials/equipment supplied
by the owner
4. Changes in law, regulations or codes subsequent to the award of
the contract
5. Changed or differing site conditions
6. Delay due to other contractor’s work
7. Acceleration in work demanded by the owner
8. Defects in the contract agreement
9. Inordinate delay in the release of payments
10. Unjustified termination of the contractor by the owner
7
11. Substantial delay in handing over the site
12. Owner’s failure in his implied duties
13. Unreasonable rejection of acceptable work
14. Delay in clearances
15. Suspension of work by the owner for his own convenience
16. Rescheduling/prolonging work for financial and other reasons
17. Work arising during maintenance period, which is not covered by the
contractor’s obligations
18. Owner’s delay in decision over amendments/change orders
19. Quantity variations, for which provision is not made in the contract
8
20. Failure by sub-contractors nominated by the owner
9
Claims of Owner/Client against Contractor
10
Owner’s Claim Procedure
Engineer’s Comments
Consultant’s Comments
Claims Committee’s Recommendation
Top Management’s Approval
Claim Initiation by the Client/Owner
Excusable Delays
11
Modes of Settlement of Disputes
12
Direct Negotiations
13
Settlement Through Courts
Last resort
Attempted only if direct negotiation and arbitration fails
Time consuming, to the tune of several years
Expensive
14
Settlement Through Arbitration
Arbitration is the hearing and determination of a dispute
by an impartial referee selected by the parties concerned.
Arbitrator is a person chosen by the concerned parties to
pronounce judgment on the dispute.
Sole Arbitrator
Joint Arbitrators
15
Advantages of Arbitration over Litigation
1. Cost
2. Speed
3. Convenience
4. Technical knowledge
5. Informality
7. Finality of award
16
Disadvantages of Arbitration
Itis the parties’ responsibility to bear the costs of
both the arbitrator and the venue where the
arbitration is to take place.
There are limited powers of compulsion or sanction
available to the arbitrator if one party fails to
comply with the directions set by the arbitrator.
There are limited appeal rights available during
arbitration.
Costs can be similar to litigation at court.
17
Indian Arbitration Act 1940
Provides for arbitration in the following three cases:
18
The Act:
does not dictate the form of arbitration to be adopted
does not prescribe the procedure for arbitration
does not interfere with the award given by the arbitrator
does not require the arbitrator to state reasons in support of his
ruling
19
Arbitration Clause
20
4 The arbitration proceedings will be conducted by the
arbitrator(s) in accordance with laid down procedures, at
mutually convenient places and dates
21
Arbitration Award
Decision of Arbitral Tribunal is termed as Arbitral Award
An arbitration award (or arbitral award) is a determination on the merits
by an arbitration tribunal in an arbitration, and is analogous to a judgment
in a court of law.
An arbitration award is the award granted by the arbitrator in their decision.
This award can be money one party has to pay to the other party. It can also
be a non-financial award, such as stopping a certain business practice or
adding an employment incentive.
The award should be dated and place when it is made should be mentioned.
Copy of award should be given to each party.
22
Construction Cost??
Expense incurred by a contractor for labor,
material, equipment, financing, services,
utilities, etc., plus overheads and contractor's
profit. Costs such as that of land, architectural
design, consultant and engineer's fee are not
construction costs.
23
Types of Construction Cost
Before moving into the main classification of project costs, some of the
specific costs encountered in construction projects are explained below.
25
Indirect Costs of Construction Project
26
The indirect cost can be classified as:
Project overhead costs can either be fixed or time-related costs. Different costs
coming under overhead costs are the costs of stores, safety facilities, workshops,
offices, staffs and parking facilities. All those plants that are required to support
the working crews will come under this cost.
27
2.General Overhead Costs
The general overhead costs cannot be directly charged for a specific
project. These form the costs that are used to support the overall
activities of the company. The general overhead costs will include
the cost of the design engineers, expenses of head-office, cost of
directors and managers, schedulers etc.
28
Based on a future plan of actions Prepared in advance
Based on objectives to be attained Expressed in monetary and/or
physical units
Prepared for the implementation of policy formulated by the
management
29
A project budget reflects the financial plan of operations ,divided
into responsibility centers, while scientific goal clearly outlined
along with the costs expected to be incurred.
Purpose is to assign financial targets and resources to each
responsibility centers.
In a construction Projects the client and contractor is having
separate budgets.
The client construction budget is a capital budget,which is
enmarked by the clients for a project. It includes the expenditure on
preliminaries, procurement of land, consultants fee, contractors
payment and the cost of working capital.
A contractor budget is earned value income and resources
expenditure oriented budget.It include quantity statement of income
and expenditure and forecast of financial statement of project
balance sheet,cash flow ,profit and loss and performance measuring
base time. 30
31
32
Types of budget
33
Earned value budget
The earned value means “what we get for what we spent”
The earned value or sales value of the work in progress yields revenue.
This revenue nourishes the growth of the project..
It is the earned value forecast that forms the base for the quantification of
the entire production budget.
Therefore it is important that all those engaged in project management
should take an active role in the formulation of the earned value budget..
First step is preparing monthly physical targets to be achieved. These
targets are achieved from the project schedule of work.
This is computed by assigning standard earned value for each package and
then aggregating these month wise to derive the work done earned value.
34
Project operating expense budget
Determined by summing up the standard costs of corresponding
work packages constituting the tasks.
It details the resources and costs planned for achieving phased
objectives.
It can also be termed as expenditure budget.
Project expenditure can be classified as production related expenses
and administration related expenses.
Production related expenses: includes budgets for each of the
production responsibility centres and the services responsibility
centres who support the production.
Administration expenditure budget: consists of general
administration budget, technical management budget and temporary
work and common facilities budget
35
Indirect Expense Budget
It includes Cost inflation, Escalation and Contingencies.
Inflation results in an increase in the price of goods and services, and thus
gradually decrease the purchase power of money.
Escalation in a project work can be taken as the difference between the
original and the latest estimate of the final cost of the project.
The inflationary trend can be reviewed at the time of the review of the
budget and the cash flows forecast can be modified by taking the prevailing
trend of prices.
36
Project Master Budget
37
38
Importance of Project Budget
Provide an organized procedure for planning
Outlines the financial plan of the project.
Depicts the management vision for the future.
Without budget there can be no budgetary controls
Supply information on the basis of which
corrective action may be taken
39
Project Budget preparation Guidelines
1.The budget should be prepared after the project plan is
crystallized.
2.The budget should be prepared by a team not by an individual.
3.The budget should be prepared, proceeding systematically using
scientific techniques as applied in a given situation .
4.The budget should be prepared in the format used for making a
corporate budget.
5.The budget should be prepared as a comprehensive total
document.
The budget should be prepared keeping in mind that it has to be
used for budgetary control.
40
41