Professional Documents
Culture Documents
Lecture 4 Project
Lecture 4 Project
Cost management is the process of planning and controlling the costs associated
planning cost management, creating good estimates, and using earned value
Notice two crucial phrases in this definition: “a project” and “approved budget.”
1 03/11/2022
Cont…
There are four processes for project cost management:
1.Planning cost management:
The first step in project cost management is planning how the costs will be
managed throughout the life of the project.
It involves determining the policies, procedures, and documentation that
will be used for planning, executing, and controlling project cost.
The project manager and other stakeholders use expert judgment, analytical
techniques, and meetings to produce the cost management plan.
The main output of this process is a cost management plan.
2 03/11/2022
Cont…
In general, a cost management plan includes the following
information:
1. Level of accuracy:
2. Units of measure
3. Organizational procedures links
4. Control thresholds
5. Rules of performance measurement
6. Reporting formats
7. Process descriptions:
3 03/11/2022
Cont…
2. Estimating costs.
Involves developing an approximation or estimate of the costs of the resources
4 03/11/2022
Cont…
It's the sum of the cost estimates for all the tasks on your project schedule.
The main outputs of the cost budgeting process are a cost baseline, project
funding requirements, and project documents update. project documents
updates, such as items being added, removed, or modified in the scope
statement or project schedule.
A cost baseline is the budget that has been approved for the project, broken
down into a list of salaries, materials, equipment and more.
cost baseline for measuring project performance and to determine project
funding requirements.
The cost management plan, scope baseline, activity cost estimates, basis of
estimates, project schedule, resource calendars, risk register, agreements,
and organizational process assets are all inputs for determining the budget.
5 03/11/2022
Cont…
4. Controlling costs
Controlling project costs includes monitoring cost performance,
7 03/11/2022
Basic Principles Of Cost Management
Many IT projects are never initiated because IT professionals do not
8 03/11/2022
Cont…
profits are revenues minus expenditures. To increase
10 03/11/2022
Cont…
Indirect costs are not directly related to the products or
services of the project, but are indirectly related to
performing the project.
For example, indirect costs would include the cost of
electricity, paper towels, and other necessities in a large
building that houses 1,000 employees who work on many
projects.
Sunk cost is money that has been spent in the past.
Consider it gone, like a sunken ship that can never be
raised.
When deciding what projects to invest in or continue, you
should not include sunk costs.
11 03/11/2022
Cont…
Learning curve theory states that when many items are produced repetitively,
the unit cost of those items decreases in a regular pattern as more units are
produced.
The basic concept of unit theory is that as the quantity of units produced
1,000 handheld devices that could run the new software and access
information via satellite.
The cost of the first handheld unit would be much higher than the cost of the
thousandth unit.
12 03/11/2022
Cont…
Reserves are dollar amounts included in a cost
13 03/11/2022
Earned Value Management(EVM).
Earned value (EV) is a way to measure and monitor the level of work completed on a project
Simply put, it's a quick way to tell if you're behind schedule or over budget on your project. You
can calculate the EV of a project by multiplying the percentage complete by the total project
budget.
EVM is a project management methodology that integrates schedule, costs, and scope to measure
Given a cost performance baseline, project managers and their teams can determine how well the
project is meeting scope, time, and cost goals by entering actual information and then comparing
it to the baseline.
A baseline: in project management is a clearly defined starting point for your project plan which
14 03/11/2022
Cont…
EVM is considered by Insight to be one of the “critical few” best practice
areas for monitoring project performance from both a cost and schedule
perspective.
which means ,it is common to think about projects with binary thinking:
1. Ahead of schedule vs behind schedule
2. Over budget vs under budget
Under budget (=using less money than planned) If you come in under budget,
everyone will be very to create a favorable.
Over budget (=using more money than planned) Feature movies always run
over budget.
Ahead of schedule (=doing or finishing something earlier than planned
Behind schedule (=later than planned or expected.
15 03/11/2022
CONT…
Both project performance factors have a direct impact on
the total project cost.
What will be the total cost of my project if I'm ahead of
schedule but my costs are higher than expected? If I'm
behind schedule but my costs are lower?
EVM provides great information to help with these
questions.
Calculating earned value
Software packages such as Microsoft Project can perform
earned value calculations automatically, and they’re
simple calculations that can quickly be performed
manually as needed.
16 03/11/2022
Cont…
Earned
value management involves calculating three
project’s WBS.
17 03/11/2022
1. The planned value(pv)
(PV) also known as Budgeted Cost of Work Scheduled (BCWS).
It is the portion of the approved total cost estimate planned to be spent on an
of money that has been spent for the work completed by a specific date.
18 03/11/2022
3. The earned value (EV)
EV is based on the original planned costs for the project or
19 03/11/2022
EV
This calculation will allow you to objectively and quantitatively
20 03/11/2022
example
Let’s take a look at an example. Assume we’re halfway
$100,000.
$55,000.
21 03/11/2022
Therefore, in summary:
Planned Value (PV) = $55,000
(Budget at Completion).
22 03/11/2022
CONT…
With these available numbers, we're ready to do some
calculations.
1. Schedule Performance Index (SPI)
SPI measures progress achieved against progress planned.
(SPI) calculation: SPI = EV/PV
An SPI value <1.0 indicates less work was completed than was
planned.
SPI >1.0 indicates more work was completed than was planned.
So ,Schedule Performance Index (SPI) = EV/PV =
$50,000/$55,000 = 0.91 (bad because <1)
23 03/11/2022
Cont…
2. Cost Performance Index (CPI):
CPI measures the value of work completed against the actual
cost.
(CPI) calculation: CPI = EV/AC
24 03/11/2022
Cont…
analysis.
The Earned Value (EV) minus the Planned Value (PV)... It is the
25 03/11/2022
Cont…
4. Cost Variance (CV) :
Cost variance (CV), also known as budget variance.
>0)
26 03/11/2022
Cont…
5. Estimated at Completion (EAC) :
Estimate at Completion (EAC) is the current expectation of total
cost.
The EAC represents the final project cost given the costs
27 03/11/2022
The end
Question?
28 03/11/2022