Professional Documents
Culture Documents
By
A. K. Mishra
Chief Manager
Power Grid Corporation of India Limited
DEVELOPMENT OF NATIONAL GRID
PHASE - II
URI
WAGOORA
(By 2007)
DULHASTI
KISHENPUR RAVI
JULLANDHAR
HISSAR
MEERUT
BHUTAN
TALA RANGANADI
LUCKNOW TEESTA
BHIWADI KATHAL-
NR JAIPUR
M'BAD G'PUR
BONGAIGAON GURI
ALLAHABAD
/UNNAO MARIANI
PURNEA
SHIROHI MISA
MALANPUR VARANASI
SILIGURI/BIRPARA
SINGRAULI
500MW
B'SHARIF
ZERDA /BARH KAHALGAON
DEHGAM NAGDA BINA SATNA VINDHYA-
CHAL
N.K. KRISHNA
NER
NAGAR
LIMBDI GANDHAR/
AMRELI KAWAS
SEONI SIPAT
ROURKELA BANGLA
DESH
JETPUR CHEGAON
KORBA
VAPI BHANDARA RAIPUR HIRMA
PIPAVAV
BOISAR
PADGHE CHANDRAPUR TALCHER ER
DHABOL
WR
LONIKAND
1000MW JEYPORE
KOYNA
KARAD
RAMAGUNDAM
GAZUWAKA LEGEND
KOLHAPUR SR EXISTING/ X PLAN
IX PLAN
VIJAYAWADA
PONDA NARENDRA
765 KV LINES
COCHIN PUGALUR
Back
KARAIKUDI
KAYAMKULAM
KAYATHAR
TRIVANDRUM
NEED FOR UNIFIED LOAD DISPATCH &
COMMUNICATION (ULDC) SCHEME
-Unified approach in planning, design, procurement and
implementation.
- To realise real time monitoring and control of Power Grids and
minimize Grid disturbances.
SS
SS V F SS SS
DS P Q DS DS
SS
Q
O SS
RTUs
38 nos RLDC
OPERATIONS SCHEDULING
POWER SYSTEM ANALYSIS
DISPATCHER TRAINING
SIMULATOR
MAIN FEATURE IN LD &C SCHEME
CENTRALISED COMPUTER BASED CONTROL AND
COMMUNICATION SYSTEM
REAL TIME MONITORING & CONTROL OF POWER SYSTEM
OPERATION
REAL TIME ENERGY MANAGEMENT SYSTEM
DYNAMIC PLANNING FOR RELIABLE SYSTEM OPERATION
REAL TIME EVALUATION OF IMPACT OF POSSIBLE
CONTINGENCIES ON THE SYSTEM
QUICK RESTORATION OF GRID IN CASE OF DISTURBANCE
MAIN FEATURE IN LD &C SCHEME
COORDINATED CONTROL OF MVAR & LOAD FLOW TO
MAINTAIN OPTIMUM VOLTAGE & FREQUENCY PROFILES
OPERATION OF SYSTEM AT IT’S FULL CAPACITY THROUGH
CONTINUOUS CONTINGENCY ANALYSIS
EFFICIENT, RELIABLE & SECURE OPERATION OF GRID.
REAL TIME ENVIRONMENT FOR TRAINING DESPATCHERS
TO COPE WITH CONTINGENCIES
DEVEOPLMENT TOWARDS FORMATION OF NATIONAL LOAD
DESPATCH CENTRE
SCADA - SUPERVISORY CONTROL AND DATA ACQUISITION
S/S
DMS FUNCTION EMS FUNCTION AUTOMATION
FUNCTION
POWER SYSTEM ANALYSIS SEQUENCE
SCADA Telemetry
Network Topology
Available Control
List of Real time state
contingencies
Base case violations
OPF
Contingencies on current state of
Base case control
system
recommendations
Contingency Analysis
Available Control
Post-contingency
violations
OPF
Post-contingency
control
recommendations
HIERARICHAL SETUP OF INDIAN POWER SECTOR
NRLDC SRLDC
AREVA SYSTEM GE SYSTEM
ERLDC
AREVA SYSTEM NLDC
AWARD TO AREVA
NERLDC
WRLDC
AREVA SYSTEM
GE SYSTEM
Responsibilities of SLDCs and Sub-LDCs
SLDCs
Operation, monitoring and control of state owned power system.
104 LINKS
MODEM MODEM
WORKSTATION
JUKE BASED DEVELOPMENT
BOX ICCP
SCADA /EMS ISR OPERATOR
COMMUNICATION
SERVER SERVER CONSOLE CONSOLE SERVER
WITH TWO CRT
LAN 1
SPLITTER 1
TO OTHER CONTROL CENTERS
MODEM
VIDEO PROJECTION SYSTEM CHENNEL
/
MIMIC CONTROL BOARD TO RTUs 2X64KBPS
SCADA FUNCTIONS
DATA ACQUISITION
SUPERVISORY CONTROL
DATA EXCHANGE
DATA PROCESSING
oAlarms
oSequence of Event (SOE) recording
oGeneralised Calculations
DISTURBANCE DATA COLLECTION
HISTORICAL INFORMATION STORAGE & RETRIEVAL
EMS FUNCTIONS
OPERATION LOAD GENERATION POWER SYSTEM
SCHEDULING BALANCE ANALYSIS
SUBSTATION RTU
IEC 60870-5 /DNP
IEDs AT BAY LEVEL
CPU
CPU
IEC61850
PSTN
REDUNDANT
DISTRIBUTION
BUS
S/S
SCADA SYSTEM FOR REMOTE OPERATION
Pampore
Udhampur
Kishenpur
Jammu POWERGRID BROADBAND NETWORK
Pathankote Hamirpur
Jallandhar
Amritsar
Moga Shimla
Ludhiana Chandigarh
Hisar
Ambala
Bawana
Panipat
Link to Bhutan
NEW DELHI
Gurgaon
Mandola
Itanagar
Balipara
B’garh
Alwar Dadri Moradabad
Siliguri Bongaiga Tezpur
Agra Lucknow on
Guwah Misa
Kohima
Patna
Jaipur ati
Ko Varanasi Malda
Kanpur
ta Sasaram Shillon
Bhopal
Allahabad Farakk
g Imphal
Gandhinagar Ujjai B’Sharif
a
K’Ghat
n Durgapur
Vindhyachal Agartala Aizwal
Ahmedabad Itarsi Jabalpur Ranchi JamshedpurJeerat
Vadodra Indore Korba
Raipur Rourkela KOLKATA
Nagpur Talch
Surat Dhule BhilaiRengali
Cuttack
er
Nasik Chandrapur Indravati Bhubaneswar
T
SCADA NT SE
V ALARMS`
S
AGC ED PF CALC.
OPF
GENERATION
AND
IF HS ITE INTRCHANGE
SCHEDULES
HTC
LF UC IS
CS PLANT
LF
AVAILAB
REGIONAL
GENERATION
AND UC/HS
INTRCHANGE
SCHEDULES
RLDC
THANK YOU
Design of FO communication links
Selection of transmission lines / routes
Interconnection plans
Selection of suitable overhead FO cable(s)
technology
Selection of cables and associated hardware
fittings & attachments
Selection of communication transmission
technology (PDH / SDH / DWDM)
Finalisation of repeater locations for long links
Plan & Design of Equipment, power supply, air-
conditioning etc
Type of FO cables being used
Overhead FO cable : Installed on the transmission
line towers
Approach cable : To connect overhead FO cable
at the gantry tower with the transmission
equipment in the communication room inside the
sub-station area
Underground FO cables : Installed inside the
ducts below ground through open cut trenching
or through trenchless digging
Types of Overhead Fibre Optic Cables
OPGW
WRAP AROUND
ADSS
STATUS OF ULDC SCHEMES
REGION STATUS
North- 66 1 7 0 8 964 12
Eastern
3 WRLDC MUMBAI
4 SRLDC BANGALORE
5 ERLDC KOLKATA
6 NERLDC SHILLONG