DRIVEWAY REHABILITATION

AS OF FEBRUARY 28, 2022


SITE DEVELOPMENT KEYPLAN

RDU - CARPARK
ENTRANCE

UGF DRIVEWAY
MAIN DROP-OFF (FRONT OF BDO)

GOVERNMENT ROAD
STATUS
FEB. 28, 2022

SCHEDULE JANUARY FEBRUARY MARCH


REPORT OUTLINE ITEM/DESCRIPTIO N
START FINISH
DURATION
28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

CO N STRU CTIO N PHASE 28-Jan-22 15-Mar-22 46


Program of Works
A. RDU Entrance 28-Jan-22 18-Feb-22 21
1.0 Board-up W orks 28-Jan-22 28-Jan-22 1
Accomplishments 2.0 Demolition of Existing Road 29-Jan-22 31-Jan-22 3
3.0 Hauling of Debris 01-Feb-22 05-Feb-22 5
4.0 Compaction and Leveling of sub-grade material (Soil Preparation) 06-Feb-22 09-Feb-22 4
Progress Photos 5.0 Gravel Bedding and Steel Works for Sidewalk 09-Feb-22 10-Feb-22 2
6.0 Concreting of Sidewalk 11-Feb-22 11-Feb-22 1
7.0 Gravel Bedding and Steel Works for Roadway 12-Feb-22 15-Feb-22 4
8.0 Concreting of Roadway 16-Feb-22 16-Feb-22 1
9.0 Stone Riprap W orks 17-Feb-22 21-Feb-22 5
10.0 Clearing and Removal of Board-up 18-Feb-22 18-Feb-22 1
11.0 Concrete Curing 16-Feb-22 04-Mar-22 14

B. UGF Area (Infront of BDO ) 23-Feb-22 02-Mar-22 7


1.0 Board-up W orks 23-Feb-22 23-Feb-22 1
2.0 Demolition of Existing Road incl. Hauling of Debris 23-Feb-22 25-Feb-22 3
3.0 Compaction and Leveling of sub-grade material (Soil Preparation) 26-Feb-22 27-Feb-22 2
4.0 Gravel Bedding and Steel Works 27-Feb-22 28-Feb-22 2
5.0 Concreting and Finishing 01-Mar-22 01-Mar-22 1
6.0 Clearing and Removal of Board-up 02-Mar-22 02-Mar-22 1
7.0 Concrete Curing 01-Mar-22 14-Mar-22 14

C. Mall Drop-off 02-Mar-22 12-Mar-22 10


1.0 Board-up W orks (Area1) 02-Mar-22 02-Mar-22 1
2.0 Removal of Existing Stone Finish and O ld Asphalt incl. Hauling of Debris 03-Mar-22 05-Mar-22 3
3.0 Board-up W orks (Area2) 06-Mar-22 06-Mar-22 1
4.0 Removal of Existing Stone Finish and O ld Asphalt incl. Hauling of Debris 06-Mar-22 08-Mar-22 3
5.0 Surface Preparation 09-Mar-22 09-Mar-22 1
6.0 Asphalt Laying W orks 10-Mar-22 11-Mar-22 2
7.0 Painting Works 12-Mar-22 12-Mar-22 1
8.0 Clearing and Removal of Board-up 12-Mar-22 12-Mar-22 1

D. Carpark Entrance 07-Mar-22 15-Mar-22 8


1.0 Board-up W orks 07-Mar-22 07-Mar-22 1
2.0 Demolition of Existing Road incl. Hauling of Debris 08-Mar-22 11-Mar-22 4
3.0 Compaction and Leveling of sub-grade material (Soil Preparation) 12-Mar-22 13-Mar-22 2
4.0 Gravel Bedding and Steel Works 13-Mar-22 13-Mar-22 1
5.0 Concreting and Finishing 14-Mar-22 14-Mar-22 1
6.0 Clearing and Removal of Board-up 15-Mar-22 15-Mar-22 1
7.0 Concrete Curing 14-Mar-22 27-Mar-22 14

SM CITY BAGUIO – DRIVEWAY REHABILITATION


REPORT OUTLINE
DRIVEWAY REHABILITATION COMPLETION DATE OF TURN-OVER DATE
Program of Works (After Curing)
REMARKS
PHASE DATE

Accomplishments

Progress Photos 1. RDU Entrance Feb. 18, 2022 Mar. 4, 2022 Completed

2. Road infront of BDO Mar. 3, 2022 Mar. 14, 2022 On-going

3. Mall Drop-off (Asphalt) Mar. 11, 2022 Mar. 12, 2022

4. Carpark Entrance Mar. 14, 2022 Mar. 28, 2022

SM CITY BAGUIO – DRIVEWAY REHABILITATION


REPORT OUTLINE

Program of Works

Accomplishments

Progress Photos

SM CITY BAGUIO – DRIVEWAY REHABILITATION


REPORT OUTLINE
ROAD REHAB COMPLETION PREVIOUS WEEK THIS WEEK VARIANCE
Program of Works (Accumulative %) (Accumulative %)
REMARKS
infront of BDO DATE (%)

Accomplishments
1. Board-up Works Feb. 23, 2022 0.00% 100% 100% Completed
Progress Photos

2. Demolition of Existing Road Feb. 24, 2022 0.00% 100% 100% Completed

3. Hauling of Debris Feb. 25, 2022 0.00% 100% 100% Completed

4. Compaction and Leveling Feb. 27, 2022 0.00% 100% 100% Completed

5. Gravel Bedding and Dowels Mar. 1, 2022 0.00% 90% 90%

6. Concreting Mar. 2, 2022 0.00% 0.00% 0.00%

7. Site Clearing and Board


Mar. 3, 2022 0.00% 0.00% 0.00%
down

8. Concrete Curing Mar. 14, 2022 0.00% 0.00% 0.00%

TOTAL 0.00% 61.25% 61.25%

SM CITY BAGUIO – DRIVEWAY REHABILITATION


REPORT OUTLINE ROAD BOARD-UP
Program of Works AS OF FEBRUARY 28, 2022
Accomplishments
LEGEND:
Progress Photos Previous: Area = 0.0 sqm
This Week: Area = 132.0 sqm
Balance: Area = 0.0 sqm

02/23/2022 02/23/2022

Target Actual Completion Remarks


Over-all Accomplishment this 100% 100% Feb. 23 Completed
week :
SM CITY BAGUIO – DRIVEWAY REHABILITATION
REPORT OUTLINE BREAKING OF EXISTING ROAD AND PULL-OUT OF DEBRIS
Program of Works AS OF FEBRUARY 28, 2022
Accomplishments
LEGEND:
Progress Photos Previous: Area = 0.0 sqm
This Week: Area = 67.50 sqm
Balance: Area = 0.0 sqm

02/24/2022 02/23/2022

Target Actual Completion Remarks


Over-all Accomplishment this 100% 100% Feb. 24 Completed
week :
SM CITY BAGUIO – DRIVEWAY REHABILITATION
REPORT OUTLINE GRAVEL BEDDING AND DOWEL WORKS
Program of Works AS OF FEBRUARY 28, 2022
Accomplishments
LEGEND:
Progress Photos Previous: Area = 0.0 cum
This Week: Area = 19.8 cum
Balance: Area = 2.2 cum

02/28/2022 02/28/2022

Target Actual Completion Remarks


Over-all Accomplishment this 90% 90% Mar. 1 On-going
week :
SM CITY BAGUIO – DRIVEWAY REHABILITATION
REPORT OUTLINE PROGRESS PHOTOS
Program of Works AS OF FEBRUARY 28, 2022
Accomplishments

Progress Photos

SM CITY BAGUIO – DRIVEWAY REHABILITATION


REPORT OUTLINE

Program of Works ITEM START FINISH REMARKS

Accomplishments

Progress Photos 1. Concreting of Phase 2 March 2, 2022 March 2, 2022

Look Ahead Schedule


2. Board Down of Phase 2 March 3, 2022 March 3, 2022

3. Concrete Curing of Phase 2 March 3, 2022 March 17, 2022

4. Board up of Phase 3 March 4, 2022 March 4, 2022

SM CITY BAGUIO – DRIVEWAY REHABILITATION


3RD FLOOR TOILET
AS OF FEBRUARY 22, 2022
PROJECT : SM CITY BAGUIO EXPANSION
SUBJECT : WORK BREAKDOWN SCHEDULE FOR 3RD FLOOR TOILET

DAYS TO SCHEDULE Feb-22 Mar-22


ITEM/DESCRIPTION
COMPLETE START FINISH 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
I. 3RD FLOOR TOILET
1 Transfer of Play Equipments of Quantum
2 Board-up Works on Quantum Tenant 1 11-Feb-21 11-Feb-21
3 Demolition Works on existing area
a. Demolition of Dry Wall 4 12-Feb-21 15-Feb-21
b. Demolition of Ceiling and Utilities 7 15-Feb-21 21-Feb-21
c. Demolition of Tiles and Topping 10 14-Feb-21 23-Feb-21
4 CHB Wall Partition 18 15-Feb-21 04-Mar-21
5 Waterproofing Works 7 24-Feb-21 02-Mar-21
6 Plumbing Layout and Works 10 03-Mar-21 12-Mar-21
7 Mechanical / Ducting Works 10 05-Mar-21 14-Mar-21
8 Fire Protection Works 7 06-Mar-21 12-Mar-21
9 Electrical Works 12 03-Mar-21 14-Mar-21
10 Installation of Wooden Doors (Slop Sink & PWD) 3 05-Mar-21 07-Mar-21
11 Installation of Roll-up Doors (Male and Female Toilet) 4 03-Mar-21 06-Mar-21
12 Ceiling and Painting Works 10 15-Mar-21 24-Mar-21
13 Installation of Lighting Fixtures 2 20-Mar-21 21-Mar-21
14 Wall Tiling Works 7 25-Mar-21 31-Mar-21
15 Installation of Plumbing Fixtures 3 27-Mar-21 29-Mar-21
16 Installation of Glass Mirrors 2 30-Mar-21 31-Mar-21
17 Floor Tiling Works 7 01-Apr-21 07-Apr-21
18 Granite Countertop 3 05-Apr-21 07-Apr-21
19 Toilet Partition 2 08-Apr-21 09-Apr-21
20 PWD Grab Rail 2 08-Apr-21 09-Apr-21
21 Toilet Signages & Graphics 2 08-Apr-21 09-Apr-21
Total Days (Critical Path) 64

STATUS
FEB. 22, 2022

SM CITY BAGUIO – 3RD FLOOR TOILET


3RD FLOOR TOILET
REPORT OUTLINE 3RD FLOOR TOILET – DISMANTLING OF TILES AND DRY WALL
Program of Works AS OF FEBRUARY 11, 2022
Accomplishments

LEGEND:
This Week: Area = 238.52 sqm
Balance: Area = 397.52 sqm

Target Actual Completion Remarks


SM CITY BAGUIO – 3RD FLOOR TOILET Over-all Accomplishment this 65% 65% March 4 On-going
week :
REPORT OUTLINE

Program of Works ITEM START FINISH REMARKS

Accomplishments

Progress Photos 1. Waterproofing Works March 7, 2022 March 14, 2022

Look Ahead Schedule


2. MEFPS March 3, 2022 March 18,2022

SM CITY BAGUIO – DRIVEWAY REHABILITATION


END OF REPORT
THANK YOU!

(SM CITY BAGUIO)