Professional Documents
Culture Documents
Project Time Management
Project Time Management
Winter 2018
Define activities
Sequence activities
Develop Schedule
Control Schedule
Exercises
Introduction
Project Time Management
The key benefit of this process is that it provides guidance and direction on how the project
schedule will be managed throughout the project.
Define Activities
Define Activities is the process of identifying and documenting the specific actions to be
performed to produce the project deliverables.
The key benefit of this process is to break down work packages into activities that provide
a basis for estimating, scheduling, executing, monitoring, and controlling the project work.
Define Activities
Define Activities
Sequence Activities is the process of identifying and documenting relationships among the
project activities.
The key benefit of this process is that it defines the logical sequence of work to obtain the
greatest efficiency given all project constraints.
Sequence Activities
17
Sequence Activities
Task Dependency Types
Sequence Activities
Task Dependency Types
19
Sequence Activities
Leads and Lags
A lead is the amount of time whereby a successor activity can be advanced
with respect to a predecessor
activity. For example, on a project to construct a
new office building, the landscaping could be scheduled to start two weeks
prior to the scheduled punch list completion.
Estimate Activity Resource
Estimate Activity Resources is the process of estimating the type and quantities of
material, human resources, equipment, or supplies required to perform each
activity.
The key benefit of this process is that it identifies the type, quantity, and
characteristics of resources required to complete the activity which allows more
accurate cost and duration estimates.
Estimate Activity Duration
The key benefit of this process is that it provides the amount of time each activity will take
to complete, which is a major input into the Develop Schedule process.
Estimate Activity Duration
Develop Schedule
The key benefit of this process is that by entering schedule activities, durations,
resources, resource availabilities, and logical relationships into the scheduling tool,
it generates a schedule model with planned dates for completing project activities.
Develop Schedule
Develop Schedule
Develop Schedule
Gantt Charts
• Gantt charts provide a standard format for
displaying project schedule information by
listing project activities and their corresponding
start and finish dates in a calendar format
• Symbols include:
– A black diamond: milestones or significant events
on a project with zero duration
– Thick black bars: summary tasks
– Lighter horizontal bars: tasks
– Arrows: dependencies between tasks
Develop Schedule
Milestones
• Milestones are significant events on a project
that normally have zero duration
• You can follow the SMART criteria in
developing milestones that are:
– Specific
– Measurable
– Assignable
– Realistic
– Time-framed
Develop Schedule
Sample Tracking Gantt Chart
34
Develop Schedule
D=7 5 F=2
a. How many paths are on this network diagram?
b. How long is each path?
c. Which is the critical path?
d. What is the shortest amount of time needed to complete this project?
Develop Schedule
Shortened
duration thru
crashing
Overlapped
Tasks or fast
tracking
Develop Schedule
Multitasking Example
52
Buffers and Critical Chain
A buffer is additional time to complete a task
Murphy’s Law states that if something can go wrong, it
will, and Parkinson’s Law states that work expands to
fill the time allowed. In traditional estimates, people
often add a buffer and use it if it’s needed or not
Critical chain schedule removes buffers from individual
tasks and instead creates
– A project buffer, which is additional time added before the
project’s due date
– Feeding buffers, which are addition time added before tasks
on the critical path
Develop Schedule
https://www.youtube.com/watch?v=MA3wTTf76Pc
Exercises
The amount of time that a schedule activity can be delayed without delaying the
early start date of any immediate successor activity within the network path is
called:
A. Total Float
B. Free Float
C. Zero Float
D. Project Float
Exercises
All of the following involve schedule compression techniques EXCEPT:
A. 6
B. 14
C. 0
D. 8
Exercises
Exercises
A. 18
B. 17
C. 9
D. 36