JOB SEQUENCING WITH

DEADLINES
Prepared by

Mrs.P.Anusha M.Sc(IT).,M.Phil.,D.P.T.T.,(Ph.D).,
Assistant professor,
Department of Information Technology,
Bon secours college for women,
Thanjavur.
Job Sequencing with Deadlines
• In job sequencing problem ,the objective is to
find a sequence of jobs which is completed
with their deadlines and give maximum profit.
• In this problem we have n jobs
j1,j2……….jn.
Each job has an associated with deadline
d1,d2…….dn.
And profit
p1,p2….pn.
Job Sequencing with Deadlines
 Profit will be only earned or awarded if the job is
completed on or before the deadline.

 we assume that each job has takes unit of time to


complete.

 The objective is to earn max profit, when only one


job can be scheduled or processed at any given
time.
Job Sequencing with Deadlines
Consider the following 5 jobs and associated
deadline, profit:

INDEX 1 2 3 4 5

JOB j1 j2 j3 j4 j5

DEADLINE 2 1 3 2 1

PROFIT 60 100 20 40 20
Job Sequencing with Deadlines
Sort the jobs according to their profit in
descending order:
INDEX 1 2 3 4 5

JOB j2 j1 j4 j3 j5

DEADLINE 1 2 2 3 1

PROFIT 100 60 40 20 20
Job Sequencing with Deadlines
Jobs j3 and j5 are having profit 20. so we placed j3 as
first as it come before j5.

FIND THE MAX DEADLINE VALUE:


Looking at the jobs, we can say the max deadline
value is 3.
Dmax=3;
So we will have 3 slots to keep track of free the time
slot
Job Sequencing with Deadlines
Set the timeslot to empty
TIME SLOT 1 2 3
STATUS empty empty empty

Total number of jobs=5;


So
n=5;
And
Dmax=3
 We look at job j2, it has a deadline one. This means we have
to complete job j2 in timeslot1. if we want to earn the
profit.

 We look at job j1, it has a deadline two. This means we have


to complete job j1 before timeslot 2 in order to earn profit.

 We look at job j3, it has a deadline three. This means we


have to complete job j3 before timeslot 3 in order to earn
profit.
OBJECTIVE:

• To select jobs that will give us higher profit


i=1;
K=min(dmax,deadline(x)),
Or k=min(3,deadline(1)),
Or k=min(3,1),
Or k=1;
Is k>=1;
1>=1 yes
Check time slot(k)==empty;
Timeslot(1)==empty? Yes,
Fill the timeslot1 with j2.
i=2;
K=min(dmax,deadline(x)),
Or k=min(3,deadline(2)),
Or k=min(3,2),
Or k=2;
i>k>=1
2>=1
Yes
Check time slot(k)==empty;
Timeslot(2)==empty? Yes,
Fill the timeslot2 with j1.
i=3;
K=min(dmax,deadline(x)),
Or k=min(3,deadline(2)),
Or k=min(3,2),
Or k=2;
i>k>=1
2>=1
Yes
Check time slot(k)==empty;
Timeslot(2)==empty?
No
Reduce K by 1
So
i=3
K=1
1>k>=1
1>=1 yes
Check time slot(k)==empty;
Timeslot(1)==empty?
No
Reduce K by 1
So
i=3
K=0
1>k>=1
0>k=1; No
So we will move to next job
i=4;
K=min(dmax,deadline(x)),
Or k=min(3,deadline(3)),
Or k=min(3,3),
Or k=3;
i>k>=1
3>=1
Yes
Check time slot(k)==empty;
Timeslot(3)==empty? Yes
Fill the time slot 3 with j3. now time slot has filled with jobs
so we have to stop here.

Required job sequence:


J2 → j1 → j3.
Then
Maximum profit:
100+60+20=180.
Thank you