Professional Documents
Culture Documents
8 FINANCIAL ANALYSIS
FINANCIAL ESTIMATES & PROJECTIONS (only
as a basis for additional readings )
• To judge a project from the financial angle, we
need information about the following
– Cost of project
– Means of financing
– Estimates of sales & production
– Cost of production
– Working capital requirement & its financing
– Estimates of working results profitability projections
– Break even point
– Projects cash flow statements
– Projected balance sheets
2.8 FINANCIAL FEASIBILITY
• From the point of view of:-
The direct project beneficiaries
Project as a whole
Any financial intermediary
The government
• Values directly quantifiable Project inputs at market
prices
• Government policy measure effects can either be
cost or benefits
• Debt services are costs; &
• Presents an entity's point of view
PURPOSE OF FINANCIAL ANALYSIS
P= F
(1+r)n The discount factor
11
TIME VALUE OF MONEY
• Uncertainty:
– Birr 100 now is more than Birr 100 at a future date
– This ‘bird-in-the-hand’ principle affects many aspects of financial management
– That is why individuals prefer current consumption to future consumption
• Inflation:
– Under inflationary conditions, the value of money, expressed in terms of its
purchasing power over goods & services, declines.
– Nominal or market interest rate = real interest or return + risk premiums +
expected rate of inflation.
• There are two methods of estimating time value of money:
• these are
– compounding &
– discounting.
12
THE NATURE OF PROJECT SELECTION MODELS
• There are two types of project selection models.
Non-numeric and models do not use numbers as inputs
Numeric But numeric models do
1 2 Total
A 20,000 20,000 - 20,000
B 20,000 20,000 2,000 22,000
C 20,000 14,625 9,825 24,450
D 20,000 16,325 8,125 24,000
Then, which one is more desirable-taking into account the net proceeds?
Net Cash Flow of 4 Hypothetical Projects with Identical Initial Investment Outlays & Life Periods
Although the total net proceeds of C & D are identical, D earns more income earlier than C.
Thus D is more desirable than C
Project B is more desirable than A
Why????
RLDS 605
B) RETURN ON INVESTMENT (ROI)
• the initial fixed investment in the project divided by the estimated annual cash
inflows from the project.
• The ratio of these quantities is the number of years required for the project to
repay its initial fixed investment.
– For example, assume a project costs $100,000 to implement & has annual net cash inflows of
$25,000. Then Payback period = $100,000/$25,000= 4 years.
• This method ignores any cash inflows beyond the payback period
• The payback period is the length of time from the beginning of the project until
the sum of net incremental benefits of the project equal to total capital
investment.
• It is the amount of time it takes to recover the original/investment cost.
• The method is very simple.
• Moreover, it is a good measure when the project has problem of liquidity.
• The pay-back period is also a common, rough means of choosing among projects in
business enterprise, especially when the choice entails high degree of risk.
• Payback rule: If the calculated payback period is less than or equal to some pre-specified payback period,
then accept the project. Otherwise reject it.
TYPES OF PROJECT SELECTION MODELS
This method has two important weaknesses:
fails to consider the time & amount of net benefits after the payback period.
does not adequately take into account the time value of money even in the
payable periods.
Payback Period
Peak
cumulative
Payback period cash flow
+ve
Total
profit
Birr
Time
h
as
- ve
fc
w o
flo te
Ra
I 0 20000 -
1 2000 31000
2 8000
3 12000
4 9000
II 0 20000 -
1 2000 34000
2 12000
3 8000
4 12000
III 0 20000 -
1 1000 37000
2 5000
3 6000
4 8000
5 10000
6 5000
7 2000
EXERCISE 3
• Calculate the payback period for this project given the net cash
flows indicated in the table below
• Show the cash flow graphically
Time 0 1 2 3 4 5
(yrs)
Revenue 100 100 200 200 200
Costs (300) 20 20 20 20 20
Net Cash -300 80 80 180 180 180
flows
ANSWER TO EXERCISE 4
Time (yrs) 0 1 2 3 4 5
Costs (300) 20 20 20 20 20
n
Ct
NPV A0 t
i 1 (1 r )
Where,
Ct = the net cash flow in period t
32
THE NET PRESENT VALUE
• Simplest measure
• Measures aggregate surplus generated by the
project
• PV of Benefit – PV of Costs
Decision criteria
NPV > 0 Accept
NPV < 0 Reject
NPV = 0 Marginal case
NPV
Suppose that the project has the following data
• Initial Investment (I) = 300,000 Birr
• Annual costs of operation = 20,000 Birr
• Expected annual revenue =
100,000 Birr/year in the first 2 years &
34
Gross cash flows
Time 0 1 2 3 4 5
(yrs)
Revenue 100 100 200 200 200
Costs (300) 20 20 20 20 20
Net cash -300 80 80 180 180 180
flows
DF= 10%
35
Discounted cash flows for interest 10%
Year 0 1 2 3 4 5
Cash flows -300 80 80 180 180 180
NPV = 208.7
DPBP= 3.2 years
36
Find the NPV of an environmental project from the following
table & suggest whether the project should be accepted
1 200,000 50,000
2 200,000 50,000
3 300,000 100,000
4 300,000 100,000
5 350,000 100,000
Initial Investment: Birr 1,000,000
Discount Rate: 10%
37
Exercise
• Assume that the initial investment of a project is Birr
450,000. In the first & second years, the net benefits are
50,000 & 75,000 respectively. In the third, fourth & fifth
years, the net benefits stand at 100,000; 125,000 &
150,000. respectively. The discount rate is 10%.
Based on this information, find the NPV & show whether
the project should be accepted or rejected.
• Will your decision change if the discount factor is
increased to 15%?
38
NPV
To include the impact of inflation where we have is the predicted
rate of inflation p during period t
t
n
Ct
NPV A0 t
i 1 (1 r pt )
39
NPV (exercise)
Early in the life of a project, net cash flow is likely to be negative
The major outflow at this stage is the initial investment in the
project
The project is acceptable if the sum of the NPVs of all estimated
cash flows over the life of the project is positive.
Example, the investment is 100,000 with a net cash inflow of
25,000 per year for a period of eight years. The discount rate is
15%, an inflation rate is 3% per year. Calculate NPV.
Use the above formula.
The answer is = 1939.
The NPV of the inflows is greater than the NPV of the outflow-
i.e., the NPV is positive-the project is deemed acceptable.
40
NPV
Calculation & Answer:
NPVA = -5,000 + 500 + 1,000 + 1,000 + 1,500 + 2,500 + 1,000 = $469
(1.084)1 (1.084)2 (1.084)3 (1.084)4 (1.084)5 (1.084)6
NPVB = -2,000 + 500 + 1,500 + 1,500 + 1,500 + 1,500 + 1,500 = $3,929
(1.084)1 (1.084)2 (1.084)3 (1.084)4 (1.084)5 (1.084)6
Given that both machines have NPV > 0, both projects are acceptable. However, for
mutually exclusive projects, the decision rule is to choose the project with the
greatest NPV. Since the NPVB > NPVA, the company should choose the project for
Machine B.
41
2. IRR
• Internal rate of return (IRR)
• The internal rate of return is defined as the rate of discount, which brings
about equality between the present value of future net benefits & initial
investment. It is the value of r in the following equation.
n
Ct
I 1 r
t 1
t
• I – investment cost
• Ct – Net benefit for year t
• r - IRR
• n - Life of the project
• Illustration: For project A in the above table can be formulated as follows:
42
IRR
Internal Rate of Return (IRR);- emerges from the cost-benefit data of the
project
It is the discount rate that reduces the NPV of a project to zero
NPV
NPV
IRR
Discount Rate
43
IRR
• Calculation of IRR
• Year Cash flow
• 0 -100000
• 1 30000
• 2 30000
• 3 40000
• 4 45000
• The IRR is the value of r which satisfies the following equation:
44
IRR
Year 0 1 2 3 4
Cash flow (100,000) 30,000 30,000 40,000 45,000
Since the value is slightly higher than our target value, which is 100,000, we
increase the value to 16%.
45
IRR
• Since this value is now less than 100,000, we conclude that the value of r
lies between 15 & 16%. For most of the purposes, this indication suffices.
• If a more refined estimate of r is needed, we use the following procedure:
1. Determine the NPV of the two closest rates of return
(NPV/15%) = 802
(NPV/16%) = 1,359
2. Find the sum of the absolute values of the NPVs obtained in Step 1
802+1,359 = 2,161
3. Calculate the ratio of the NPV of the smaller discount rate, identified in
Step 1, to the sum obtained in Step 2
802/2,161 = 0.37
4. Add the number obtained in Step 3 to the smallest discount rate
15+0.37 = 15.37
46
INTERNAL RATE OF RETURN
Decision criteria
NPV
IRR Project-A
IRR Project-B
Discount rate
48
IRR
Interpolation
NPV
49
Self-check Exercise
Table 1. Cash flow for project A & B
Initial investment is Birr 20,000 each.
Discount factor: 10%
Project A Project B
50
Exercise
Find the NPV & IRR of an environmental project from the following table
1 200,000 50,000
2 200,000 50,000
3 300,000 100,000
4 300,000 100,000
5 350,000 100,000
Initial Investment: Birr 700,000
52
BENEFIT- COST (B/C) RATIO
• BCR =
Or
54
BCR
t T
Benefit t
t 1 1 r t
BCR t T
Cost t
t 1 1 r
t
55
Find the BCR & decide whether to accept the project
1 100 100
2 100 50
DF: 10%
56
Find the BCR
1 100 100 0
2 100 50 50
57
BCR
58
Exercise
• The details of a project which costs Birr. 25,000 as initial investment
are given below:
• Year Cash flow
• 0 (25,000)
• 1 5,000
• 2 7,000
• 3 13,000
• 4 16,000
• Calculate:
• a)Net present Value(NPV) at 20%:
• b) Internal Rate of Return(IRR):
• c) Payback Period:
• Use graphs to display your answers
59
DF 10% 15% 17%
Payback Period(PBP) PBP < target period PBP > target period
Accounting Rate
of Return(ARR) ARR > target rate ARR < target rate
Internal Rate of
Return(IRR) IRR > cost of capital IRR < cost of capital
61
COMPARISON OF DISCOUNTED MEASURES OF PROJECT
WORTH
RLDS 605
Financial checklist