Professional Documents
Culture Documents
Project A Project B
0 -700 0 -700
1 100 1 400
2 200 2 300
3 300 3 200
4 400 4 100
5 500 5 0
Cont..
Uniform cash flows:
Where the annual cash flows are uniform
Original Investment
PB =
Annual cash flows
•Average investment =
Cont.
CFt
n
NPV = t
Co
(1 K )
where; NPV = Net present value
CFt = Cash inflows at different periods
Co = Cash outflow in the beginning
K = Cost of capital
CONT..
•In order to use this method properly, the following procedures are
followed.
1) Find the present values of each cash flow, including both inflows
& out flows using the cost of capital of the project for discounting.
2) Sum the discounted cash outflows & the discounted cash inflows
separately.
• Obtain the difference between the sum of the cash inflows & the
sum of cash out flows
Cont..
• PI > 1 Accept
• PI = 1 indifference
• PI < 1 reject
•Higher the profitability index more is the project preferred.
Internal Rate of Return (IRR)
• The IRR is the discount rate at which the NPV for
a project equals zero.
•This rate means that the present value of the cash
inflows for the project would equal the present value
of its outflows.
•The IRR is defined as the discount rate that equates
the present value of a project’s expected cash
inflows to the present value of the project’s costs:
Cont..
•Based on the IRR rule, an investment is acceptable if the IRR
exceeds the required return. It should be rejected otherwise.