Professional Documents
Culture Documents
18-2
Materials requirements planning (MRP) is a means for determining the number of parts, components, and materials needed to produce a product MRP provides time scheduling information specifying when each of the materials, parts, and components should be ordered or produced Dependent demand drives MRP MRP is a software system
18-3
Given the product structure tree for A and the lead time and demand information below, provide a materials requirements plan that defines the number of units of each component and when they will be needed
Product Structure Tree for Assembly A Lead Times A 1 day B 2 days C 1 day D 3 days E 4 days F 1 day Total Unit Demand Day 10 50 A Day 8 20 B (Spares) Day 6 15 D (Spares)
18-4
First, the number of units of A are scheduled backwards to allow for their lead time. So, in the materials requirement plan below, we have to place an order for 50 units of A on the 9th day to receive them on day 10.
Day: A Required Order Placement 1 2 3 4 5 6 7 8 9 50 10 50
LT = 1 day
18-5
Next, we need to start scheduling the components that make up A. In the case of component B we need 4 Bs for each A. Since we need 50 As, that means 200 Bs. And again, we back the schedule up for the necessary 2 days of lead time.
Day: A B R e q u ire d O rd e r P la c e m e n t R e q u ire d O rd e r P la c e m e n t 20 200 20 50 200 1 2 3 4 5 6 7 8 9 10 50
Spares
4x50=200
18-6
Finally, repeating the process for all components, we have the final materials requirements plan:
Day: A LT=1 B LT=2 C LT=1 D LT=3 E LT=4 F LT=1 Required Order Placement Required Order Placement Required Order Placement Required Order Placement Required Order Placement Required Order Placement 1 2 3 4 5 6 7 8 9 50 200 100 55 55 20 200 200 200 400 300 20 200 400 100 300 10 50
20 20 200
A
Part D: Day 6
C(2) F(2)
40 + 15 spares
18-7
Time-phased plan specifying how many and when the firm plans to build each end item
Aggregate Plan (Product Groups)
18-8
Frozen No schedule changes allowed within this window Moderately Firm Specific changes allowed within product groups as long as parts are available Flexible Significant variation allowed as long as overall capacity requirements remain at the same levels
18-9
Exhibit 15.5
Frozen Capacity
Moderately Firm
15 Weeks
26
18-10
Based on a master production schedule, a material requirements planning system: Creates schedules identifying the specific parts and materials required to produce end items
Determines exact unit numbers needed Determines the dates when orders for those materials should be released, based on lead times
18-11
Inventory transactions
Secondary reports
Primary reports Planned order schedule for inventory and production control Exception reports Planning reports Reports for performance control
18-12
Super BOM
18-13
Pegging
18-14
Planned orders to be released at a future time Order release notices to execute the planned orders Changes in due dates of open orders due to rescheduling Cancellations or suspensions of open orders due to cancellation or suspension of orders on the master production schedule Inventory status data
18-15
Planning reports, for example, forecasting inventory requirements over a period of time Performance reports used to determine agreement between actual and programmed usage and costs Exception reports used to point out serious discrepancies, such as late or overdue orders
18-16
Gross Requirements Scheduled receipts Projected available balance Net requirements Planned order receipt Planned order release
8-
MRP Example
It X
-H
Ti
(W
ks)
18-18
Da 1 2 3 4 5 6 7 8 9 10 5 50 45 45
X L 2
Onhand 50
A(2)
Gross requ remen s Schedu ed rece p s roj a a ba ance Ne requ remen s anned order rece p anner order re ease Gross requ remen s Schedu ed rece p s Proj avail. balance Ne requiremen s Planned order receip Planner order release Gross requiremen s Scheduled receip s Proj. avail. balance Ne requiremen s Planned order receip Planner order release Gross requiremen s Scheduled receip s Proj. avail. balance Ne requiremen s Planned order receip Planner order release Gross requiremen s Scheduled receip s Proj. avail. balance Ne requiremen s Planned order receip Planner order release
50 50
50
50
50
50
50
50
50
45 90 75 75 75 75 75 75 75 75 15 15 45 25 25 25 25 25 25 25 25 20 20
15
45 10 10 10 10 10 35 35 40
20 40
40 40 100
35
20 20
20
20
20
20
20 80 80
80
18-19
Day: 1 2 3 4 5 6 7 8 9 10 5 50 45 45
X L 2
Onhand 50
A(2)
B(1)
Gross requiremen s Scheduled receip s Proj. avail. balance Ne requiremen s Planned order receip Planner order release Gross requiremen s Scheduled receip s Proj. avail. balance Ne requiremen s Planned order receip Planner order release Gross requiremen s Scheduled receip s Proj. avail. balance Ne requiremen s Planned order receip Planner order release Gross requiremen s Scheduled receip s Proj. avail. balance Ne requiremen s Planned order receip Planner order release Gross requiremen s Scheduled receip s Proj. avail. balance Ne requiremen s Planned order receip Planner order release
50 50
50
50
50
50
50
50
50
45 90 75 75 75 75 75 75 75 75 15 15 45 25 25 25 25 25 25 25 25 20 20
15
45 10 10 10 10 10 35 35 40
20 40
40 40 100
35
20 20
20
20
20
20
20 80 80
80
18-20
Day: 1 2 3 4 5 6 7 8 9 10 5 50 45 45
X L 2
Onhand 50
A(2)
B(1)
C(3)
Gross requiremen s Scheduled receip s Proj. avail. balance Ne requiremen s Planned order receip Planner order release Gross requiremen s Scheduled receip s Proj. avail. balance Ne requiremen s Planned order receip Planner order release Gross requiremen s Scheduled receip s Proj. avail. balance Ne requiremen s Planned order receip Planner order release Gross requiremen s Scheduled receip s Proj. avail. balance Ne requiremen s Planned order receip Planner order release Gross requiremen s Scheduled receip s Proj. avail. balance Ne requiremen s Planned order receip Planner order release
50 50
50
50
50
50
50
50
50
45 90 75 75 75 75 75 75 75 75 15 15 45 25 25 25 25 25 25 25 25 20 20
15
45 10 10 10 10 10 35 35 40
20 40
40 40 100
35
20 20
20
20
20
20
20 80 80
80
18-21
Day: 1 2 3 4 5 6 7 8 9 10 5 50 45 45
X L 2
Onhand 50
A(2)
B(1)
C(3)
C(2)
Gross requiremen s Scheduled receip s Proj. avail. balance Ne requiremen s Planned order receip Planner order release Gross requiremen s Scheduled receip s Proj. avail. balance Ne requiremen s Planned order receip Planner order release Gross requiremen s Scheduled receip s Proj. avail. balance Ne requiremen s Planned order receip Planner order release Gross requiremen s Scheduled receip s Proj. avail. balance Ne requiremen s Planned order receip Planner order release Gross requiremen s Scheduled receip s Proj. avail. balance Ne requiremen s Planned order receip Planner order release
50 50
50
50
50
50
50
50
50
45 90 75 75 75 75 75 75 75 75 15 15 45 25 25 25 25 25 25 25 25 20 20
15
45 10 10 10 10 10 35 35 40
20 40
40 40 100
35
20 20
20
20
20
20
20 80 80
80
18-22
Day: 1 2 3 4 5 6 7 8 9 10 5 50 45 45
X L 2
Onhand 50
A(2)
B(1)
C(3)
C(2)
D(5)
Gross requiremen s Scheduled receip s Proj. avail. balance Ne requiremen s Planned order receip Planner order release Gross requiremen s Scheduled receip s Proj. avail. balance Ne requiremen s Planned order receip Planner order release Gross requiremen s Scheduled receip s Proj. avail. balance Ne requiremen s Planned order receip Planner order release Gross requiremen s Scheduled receip s Proj. avail. balance Ne requiremen s Planned order receip Planner order release Gross requiremen s Scheduled receip s Proj. avail. balance Ne requiremen s Planned order receip Planner order release
50 50
50
50
50
50
50
50
50
45 90 75 75 75 75 75 75 75 75 15 15 45 25 25 25 25 25 25 25 25 20 20
15
45 10 10 10 10 10 35 35 40
20 40
40 40 100
35
20 20
20
20
20
20
20 80 80
80
18-23
Yes
Execute: Capacity Plans Material Plans
18-24
Lot-for-lot (L4L) Economic order quantity (EOQ) Least total cost (LTC) Least unit cost (LUC) Which one to use?
The one that is least costly!