DC Lights
For SHS and BCS, DC lights are necessary
– Available power is very limited
– Electricity is very precious
– High efficiency lights are necessary
Type of DC Lights
– DC Fluorescent Lamp
Compact Fluorescent Lamp (CFL)
– Halogen Lamp
– LED Lamp (Preferred Lamp for HEP Project because of its
high efficiency)
3W&1W LED
1W LED
7 W LED
Load 3/19
DC Lights
Halogen lamp is easily available at automobile parts shop
– Easily available but power consumption is higher than CFL.
LED lamp is now popular as lightings for both off-grid and on-grid areas
– Cost of LED is becoming cheaper than CFL light.
– LED light is now one of the component recommended for SHS
Illuminance at each
Lights Current (A) distance from light (Lux)
1m 2m
CFL 9W 0.58 83.0 20.0
Halogen 10W 0.80 50.0 8.0
LED 2.5W 0.23 120.0 35.0
Candle N/A 1.2 0.5
Load Management for SHS30
3.0W LED Lamp
1.0 W LED 5.0W CP 5.0 W Built-in Total
Option
Sala Kitchen Room Overnight Charger Radio/MP3 consumption
at 61%-80%
State of 6 hrs 2 hrs 2 hrs 11 hrs 1 hrs 2 hrs 56 Wh
Charge
at 41%-60%
State of 4 hrs 2 hrs 2 hrs 11 hrs 0 hrs 1 hrs 40 Wh
Charge
At 21%-40%
State of 4 hrs 2 hrs 0 hrs 2 hrs 0 hrs 1 hrs 25 Wh
Charge
At 0%-20%
State of 2.5 hrs 0 hrs 0 hrs 0 hrs 0 hrs 0 hrs 8 Wh
Charge
Load Management for SHS75
7.0W Linear LED 3.0W LED Lamp
5.0W 5.0 W Built- Total
Option Backdoo CP in consumptio
Office 1 Office 2 Room Frontdoor Charger Radio/MP3 n
r
at 61%-80%
State of 8 hrs 3 hrs 3 hrs 0 hrs 8 hrs 2 hrs 4 hrs 140 Wh
Charge
at 41%-60%
State of 6 hrs 0 hrs 3 hrs 0 hrs 8 hrs 2 hrs 3 hrs 100 Wh
Charge
At 21%-40%
State of 4 hrs 0 hrs 3 hrs 0 hrs 8 hrs 0 hrs 0 hrs 61 Wh
Charge
At 0%-20%
State of 1 hrs 0 hrs 0 hrs 0 hrs 4 hrs 0 hrs 0 hrs 19 Wh
Charge
21%-40% 41%-60% 61%-80%
SOC SOC SOC
0%-20% 81%-100%
SOC SOC
COMPUTATION of AVAILABLE
ENERGY
Irradiation Data (NASA)
Bislig Butuan CDO/ Cot. Davao Dipolog GenSan Glan Kor. Monkayo Pagadia Surigao Tandag
Lumbia City / Mati n City City
Jan 3.83 4.09 4.67 4.6 4.43 4.77 4.55 5.11 5.13 4.78 4.84 4.43 4.15
Feb 4.3 4.59 5.22 4.94 4.75 5.32 4.88 5.48 5.44 5.22 5.23 5.07 4.83
Mar 4.95 5.24 5.99 5.46 5.32 5.99 5.35 6.03 5.95 5.82 5.64 6 5.51
Apr 5.59 5.83 6.39 5.7 5.71 6.16 5.63 6.23 5.88 6.18 5.82 6.7 6.2
May 5.52 5.59 5.91 5.26 5.37 5.61 5.19 5.62 5.35 5.73 5.21 6.53 5.95
Jun 5.01 4.93 5.33 4.89 4.92 4.97 4.89 5.05 5.02 5.24 4.73 5.69 5.23
Jul 5.13 4.89 5.27 4.86 4.9 4.95 4.96 5.04 5.06 5.25 4.64 5.53 5.24
Aug 5.34 4.9 5.36 4.9 4.99 5.09 5.08 5.27 5.22 5.58 4.74 5.63 5.36
Sep 5.4 4.99 5.51 4.96 5.09 5.14 5.2 5.62 5.35 5.85 4.83 5.8 5.55
Oct 4.91 4.76 5.18 4.79 4.98 4.87 5.06 5.59 5.29 5.7 4.65 5.28 5.07
Nov 4.27 4.41 4.94 4.74 4.75 4.79 4.89 5.34 5.22 5.34 4.72 4.73 4.42
Dec 3.84 4.11 4.63 4.63 4.43 4.66 4.62 5.08 5.17 4.84 4.73 4.39 4.12
Ave 4.84 4.86 5.37 4.98 4.97 5.19 5.03 5.46 5.34 5.46 4.98 5.48 5.14
Model Data (Bislig)
Irradiation Data (kW/m2/day) Available Energy (Wh)
Tilt 0 Tilt 10 Tilt 15 SHS30 SHS75
5
Irradiation Data
3
Tilt 0
2 Tilt 10
Tilt 15
1
0
n b r r y n l g p t v c
Ja Fe Ma Ap Ma Ju Ju Au Se Oc No De
Month
10
Model Data (Bislig)
6
4
Irradiation Data
Ave
2 Min
Max
1
0
Tilt 0 Tilt 10 Tilt 15
Tilt Angle
Model Data (Bislig)
Irradiation Data (kW/m2/day) Available Energy (Wh)
Tilt 0 Tilt 10 Tilt 15 SHS30 SHS75
Ep = PVcap x IRR x PR
E – Available Energy
Pvcap – Capacity of PV Module
IRR- Irradiation Data
PR – Performance Ratio
13
Formula
For SHS-30:
E = 30 x 4.14 x 0.64
= 79.49 Wh
approx- 80Wh
14
Formula
For SHS-75:
E = 75 x 4.14 x 0.64
= 198.72 Wh
approx - 200Wh
15
COMPUTATION of ENERGY
CONSUMPTION
16
Formula
Econ = Lp x T
LED Charger/Radio/MP3
Energy Consumed
12 12 9 12 15 20 80
(Wh)
END OF MODULE 8:
Load