by
N.R.Kale
AXEN/1
IRICEN/Pune
RB letter No 98/CE-II/PRA/32
dated 23.05.01
Safe working of contractors:
The contractor shall not start any work without the
presence of railway supervisor at site
Barricading shall be provided wherever justified and
feasible as per site condition
The supervisor/workmen should be counseled about
safety measures.
A competency certificate to the contractor’s
supervisor shall be issued by an officer, which will
be valid only for the work for which it has been
issued.
Contd. …
Officer in-charge
Measures to be ensured prior to start of
the work
Engineer in charge must have –
1. Name & address of contractor assigned to
execute the work
2. Registration number of individual
vehicle/machine (s) proposed to be used.
3. Names and license particulars of the drivers
to be deployed on contractor’s
vehicle/machinery
Measures to be ensured prior to start of
the work
Ensure-
1. Survey of site by supervisor of contractor &
Railway’s supervisor to assess the
precautions to be taken at site.
2. The land strip adjacent to running track
where road vehicle/ machinery is to ply for
work shall be demarcated by line in
advance at the appropriate distance.
Measures to be ensured prior to start of
the work
3. Barricading as per design shall be provided
in full length of work area.
4. The work site shall be suitably demarcated to
keep public and passenger way from work
area.
5. Signage boards such as ‘Work in progress’
etc to be provided at appropriate locations to
warn public/passengers.
B) Provision of Barricading
3500 mm
Barricading
3500 mm
Elevation of Barricading
Contd. …
6000 mm
150 mm wide line with lime
3500 mm
6000 mm
Contd. …
1200 M