Professional Documents
Culture Documents
and Evaluation of
Project
1
Copyright 2018 John Wiley & Sons, Inc.
Terms
10-2
The Planning–Monitoring–
Controlling Cycle
• We mainly want to monitor:
• Time (schedule)
• Cost (budget)
• Scope (project performance)
• Becoming more important as projects are increasingly complex
• Closed-loop system
• Revised plans and schedules following corrective actions
10-3
Designing the Monitoring System (Slide 1 of
2)
10-4
Designing the Monitoring System (Slide 1 of
2)
10-5
Creating a project monitoring
information system
• Creating a project monitoring system involves
determining:
• what data to collect
• how, when and who will collect the data
• how to analyse the data
• how to report current progress to management
Data collection
10-9
Report Types
10-10
Meetings
10-11
Meeting Rules
10-12
Common Reporting Problems
10-13
“To complete” and “At Completion”
10-14
Milestone Reporting
10-15
The project control process
• Control
• The process of comparing actual performance against plan to
identify deviations, evaluate courses of action and take
appropriate corrective action
• Project control steps
1. Setting a baseline plan
2. Measuring progress and performance
3. Comparing plan against actual
4. Taking action
• Tools
• Tracking and baseline Gantt charts
• Control charts
The Project Control Cycle
Figure 13.3 Project S-Curves
19
10 20 Duration
30 (in40
days) 50 60 70 80
Activities 4 8 12 20 10 8 6
2
S-curve
20
S-Curve Showing Negative Variance
Baseline and tracking Gantt charts
Earned Value Management
10-26
Cost Variance (CV)
• CV = EV – AC
10-27
Schedule Variance (SV)
• SV = EV – PV
10-28
Steps in Earned Value Management
10-30
Using the data in the table below, complete the table by calculating the cumulative
planned and cumulative actual monthly budgets through the end of June. Complete the
earned value column on the right. Assume the project is planned for a 12-month
duration and a $250,000 budget.
10-31
10-32
• Schedule Variances
Planned Value (PV) 98
Earned Value (EV) 54
Schedule Performance Index (SPI) EV/PV = 54/98 = .55
Estimated Time to Completion (1/.55) × 12 mos. = 21.75 mos.
• Cost Variances
Actual Cost of Work Performed (AC) 94
Earned Value (EV) 54
Cost Performance Index (CPI) EV/AC = 54/94 = .58
Estimated Cost to Completion (1/.58) × $250,000 = $434,622
10-33
Project Baseline, Using Earned Value
Assume you have collected the following data for your project. Its
budget is $75,000 and it is expected to last four months. After two
months, you have calculated the following information about the
project:
PV = $45,000
EV = $38,500
AC = $37,000
Calculate the SPI and CPI. Based on these values, estimate the time
and budget necessary to complete the project. How would you
evaluate these findings? Are they good news or bad news?
35
SPI = EV/PV = $38,500/45,000 = .86
CPI = EV/AC = $38,500/37,000 = 1.04
Estimated Time to Completion = (1/.86) × 4 months = 4.68 months
Estimated Cost to Completion = (1/1.04) × $75,000 = $72,078
The findings are a bit of good news and a bit of bad. The good
news is that your estimated cost to completion is lower than the
original budget; however, the bad news is that the project is behind
schedule and is likely to take 4.65 months to complete, rather than
the originally planned 4 months.
36
Earned Value Example
Schedule Variances
Planned Value (PV) = 103
Earned Value (EV) = 44
44 EV
Schedule Performance Index 43
103 PV
1
Estimated Time to Completion 7 163 months
.43
Cost Variances
Cumulative Actual Cost of Work Performed (AC) = 78
44 EV
Cost Performance Index 56
78 AC
1
Estimated Cost to Completion $210,714 $118,000
.56
Additional earned value rules
• Rules applied to short-duration activities and/or small-cost activities
• 0/100 per cent rule
• Assumes 100 per cent of budget credit is earned at once and
only when the work is completed
• 50/50 rule
• Allows for 50 per cent of the value of the work package
budget to be earned when it is started and 50 per cent to be
earned when the package is completed
• Per cent complete with weighted monitoring gates
• Uses subjective estimated per cent complete in combination
with hard, tangible monitoring points
Human Factors in Project Evaluation
and Control
• Project coordination and relations among stakeholders
• Adequacy of project structure and control
• Project uniqueness, importance, and public exposure
• Success criteria salience and consensus
• Lack of budgetary pressure
• Avoidance of initial overoptimism and conceptual
difficulties
Critical Success Factors in the Project
Implementation Profile
1. Project mission
2. Top management support
3. Project plans and schedules
4. Client consultation
5. Personnel
6. Technical tasks
7. Client acceptance
8. Monitoring and feedback
9. Communication channels
10. Troubleshooting
“Dear Mr. President—Please Cancel our Project!”: The
Honolulu Elevated Rail Project
This case is a great current example of a very expensive project that was kicked off because of an
assumed need—to relieve congestion in downtown Honolulu through an elevated urban rail
system. Critics argue that in addition to having a ballooning cost, the actual planning was poorly
conceived, leaving Honolulu with an intrusive and ugly rail system through the downtown area,
ruining panoramic views, and impeding traffic. Additionally, advocates underestimated the
power needs for the rail system, requiring the transport authority to renegotiate electricity fees for
the system. Finally, the original costs that were assumed for the project were calculated during an
economic downturn and with the economy booming again, the costs of the project have gone up
dramatically. All of these elements points to a state Governor who is anxious to be rid of the
project and hoping that President Trump will deny additional federal funding, in which case the
project will likely be cancelled.
Questions
1.Why are public works projects like the Honolulu Rail project nearly impossible to stop once
they have been approved, even if later cost estimates skyrocket?
2.Project Management researchers have charged that many large infrastructure projects, like this
one, suffer from “delusion” and “deception” on the parts of their advocates. Explain how
“delusion” might be a cause of ballooning budgets in this project. How does “deception” affect
the final project budget overruns?
41