Nation Hydrogen Mission
Nation Hydrogen Mission
Hydrogen
Mission
1.Inter-state transmission charges shall be waiver for 25 years from the project commissioned before 30 th June 2025
2.Banking of electricity shall be permitted for period 30 days for renewable energy
3.Green hydrogen /green ammonia plant will be granted open access for sourcing renewable energy within 15 days
4.Land in renewable energy park can be allocated to manufacturer of green hydrogen/green ammonia .
5.Green hydrogen /green ammonia plant can be setup in any manufacturing zones.
6.Can be setup bunkers nearby ports for exporting /use ammonia by shipping.
7.MNRE will establish a single portal for permission , generation , transportation and distribution of green hydrogen /green ammonia .