Professional Documents
Culture Documents
Section 75 of the
Contracts Act 1950
Introduction
Section 75 of the Contracts Act 1950
3) However, for cases where the court finds it difficult to assess damages for the
actual damages employable, and yet the evidence clearly shows some real loss
inherently which is not too remote, the words in question will apply. The court
ought to award substantial damages as opposed to nominal damages which
are reasonable and fair according to the court’s good sense and fair play. In
any event, the damages awarded must not exceed the sum so named in the
contractual provision.
The Selva Kumar ruling seriously undermined the importance and effectiveness of
LAD clauses and consequently its role in allowing parties to a contract to allocate
risks in their contractual obligations and to avoid expensive and lengthy litigation
in the event of breach.
Johor Coastal Development Sdn Bhd v Constrajaya Sdn Bhd
(“Johor Coastal”) [2009] 4 MLJ 445
The issues before the Federal Court:
(1) Whether that part of the decision in Selva Kumar which obliges a
party having the benefit of a liquidated damages clause to prove its
losses, notwithstanding the words in S.75 Contracts Act “whether or
not actual damage or loss is proved to have been caused thereby”, is
correct
(2) Whether or not parties entering into a contract are entitled to
contract out of the provisions of S.75 Contracts Act
The Federal Court by a 2:1 majority answered the first question in the
affirmative but did not address the second issue on the facts of the case.
A dissenting voice
Dissenting judgement of Hashim Yusof FCJ in Johor Coastal:
1. The monies was rightly forfeited by the appellant, being an amount that was
reasonable in view of the nature of the project and its abandonment by the
respondent three years after the agreement was signed. Although proof of
loss and damages could be given, it would be a very lengthy process that the
parties agreed on a stipulated sum in the event of breach. It could not be the
case that the innocent party would be the one to have to prove the loss.
2. The parties had expressly agreed and named the sums payable in case of
breach as reasonable compensation to the non-defaulting party. The party
further waived any objection thereafter that those sums would be otherwise
than fair or reasonable compensation. Such stipulation was not contrary to
S.75 Contracts Act.
To avoid the effect of Selva Kumar ruling – contracting out
of S.75 Contracts Acts
• e.g. of an LAD clause drafted in response to the Selva Kumar ruling:
Clause 22.2 of the PAM Contract 2018: “The Liquidated Damages
stated in the Appendix is a genuine pre-estimate of loss and/or
damage which the Employer will suffer in the event the Contractor is
in breach…The parties agree that by entering the Contract, the
Contractor shall pay to the Employer the said amount, if the same
becomes due without the need for the Employer to prove his loss
and/or damage…”
• Obiter by FC in Cubic decision – “parties not at liberty to contract out
of S.75”[para 54]
Recent COA decisions applying Selva Kumar ruling
• Malayan Cement Industries Sdn Bhd v Golden Island Shipping (L) Bhd [2018]
• 1 CLJ 228 - contract to purchase iron ores
• Saycon Construction Sdn Bhd v Rosado Tradeline Sdn Bhd [2018] 4 MLJ 652
- construction contract
• Tekun Nasional v Plentitude Drive (M) Sdn Bhd and 2 Other Appeals [2018] 8 CLJ 693
- big contract to develop the entire core system infrastructure of the defendant which
consisted of upgrading loan repayment facility by introducing the mobile gadget and
standing instruction system
• Mars Telecommunications Sdn Bhd v Cubics Electronics Sdn Bhd (In liquidation)
[2017] 6 MLJ 321
- sale and purchase of land
Cubic Electronics Sdn Bhd (In liquidation) v Mars
Telecommunications Sdn Bhd (“Cubic”) [2018] MLJU 1935
Facts:
The Plaintiff offered to purchase land with plant and machinery thereon from the
Defendant for RM90 million on the terms set out in the Info Memo. Pursuant thereto, the
Plaintiff paid an earnest deposit of RM1 million. Failure to execute the SPA within a month
from the date of the acceptance would result in the forfeiture of the earnest deposit as LAD
and not by way of penalty. Upon the signing of the SPA the Plaintiff would have to pay 10%
of the purchase price as deposit.
On numerous requests by the Plaintiff and upon the payment of further sums by the
Plaintiff toward the earnest deposit, the Defendant had on three occasions granted an
extension of time to the Plaintiff to execute the SPA. By the time the final request was
rejected by the Defendant, the Plaintiff had made a total payment of RM3 million plus the
non-refundable interest of RM40,000.
The Courts’ decisions
• The High Court had dismissed the Plaintiff’s claim for the refund of the
earnest deposits forfeited, and held that that the forfeiture of the
deposits does not contravene S.75 Contracts Act and that the deposits
paid amounting to RM3 million are true deposits whereby the
Defendant need not prove loss or damage.
• The Court of Appeal, delivering its judgement in July 2017, agreed with
the learned High Court Judge that deposits are, generally speaking,
liable to be forfeited without proof of damage but held that the
amount liable to be forfeited by the Defendant was only the RM1
million that was agreed as earnest deposit at the time of entering into
the agreement.
[cont’d]
vii. The initial onus lies on the party seeking to enforce a damages clause
under section 75 of the Act to adduce evidence that firstly, there was
a breach of contract and that secondly, the contract contains a clause
specifying a sum to be paid upon breach. Once these two elements
have been established, the innocent party is entitled to receive a sum
not exceeding the amount stipulated in the contract irrespective of
whether actual damage or loss is proven subject always to the
defaulting party proving the unreasonableness of the damages clause
including the sum stated therein, if any.
viii. If there is a dispute as to what constitutes reasonable compensation,
the burden of proof falls on the defaulting party to show that the
damages clause including the sum stated therein is unreasonable.
The law relating to deposits
The learned CJ referred to the decision in Cavendish v Square Holdings BV v Talal El
Maksessi [2015] UKSC 67 where the UK Supreme Court had made the observation that:
(i) both the law on penalties and the law against forfeiture may be applied to the same
clause (on forfeiture of deposit) albeit the relationship between the two is “not entirely
easy” and
(ii) the previously ambiguous position purporting to support the mutually exclusive approach
may be best rationalised by applying the reformulated law on penalties, that is, looking at
legitimate interest and proportionality rather than the law of relief against forfeiture.
In agreement with the UK developments, the learned CJ held that a deposit is subject to S.75
Contracts Act – departing from previous ruling in Linggi Plantations Ltd v Jagatheesan [1972]
1 MLJ 89 (PC)
Cavendish Square Holdings BV v Talal El Maksessi
(“Cavendish”)
• Facts: By an agreement, Mr Makdessi agreed to sell to Cavendish a controlling stake
in the holding company of the largest advertising and marketing communications
group in the Middle East. The contract provided that if he was in breach of certain
restrictive covenants against competing activities, Mr Makdessi would not be
entitled to receive the final two instalments of the price paid by Cavendish (clause
5.1) and could be required to sell his remaining shares to Cavendish, at a price
excluding the value of the goodwill of the business (clause 5.6). Mr Makdessi
subsequently breached these covenants. He argued that clauses 5.1 and 5.6 were
unenforceable penalty clauses. The Court of Appeal, overturning the High Court’s
decision, held that the clauses were unenforceable penalties under the penalty rule
as traditionally understood.
• Held: that neither clause 5.1 nor clause 5.6 are unenforceable penalty clauses, and
accordingly allowed the appeal
The Legal Principles
• The penalty rule, being of long standing, should not be abolished but
neither should it be extended [36-40].
• The fundamental principle is that the penalty rule regulates only the
contractual remedy for the breach of primary contractual
obligations, and not the fairness of those primary obligations
themselves. The relevant contractual remedy typically stipulates
payment of money, but it equally applies to obligations to transfer
assets or clause where one party forfeits a deposit following its own
breach of contract [13-18].
[cont’d]
• Facts: ParkingEye Ltd agreed with owners of the Riverside Retail Park to
manage the car park at the site. ParkingEye displayed numerous notices
throughout the car park, saying that a failure to comply with a two hour time
limit would “result in a Parking Charge of 85 pound sterling”. On April 15
2013, Mr Beavis parked in the car park, but overstayed the two hour limit by
almost an hour. ParkingEye demanded payment of 85 pounds sterling. Mr
Beavis argued that the Parking Charge was unenforceable at common law as
a penalty, and/or that it was unfair and unenforceable by virtue of the Unfair
Terms in Consumer Contracts Regulations 1999. The Court of Appeal upheld
the first instance decision rejecting those arguments.
• Held: that the charge does not contravene the penalty rule, or the UTCCR
1999 (dismissed the appeal by a majority of six to one)
Application of new penalty test to
ParkingEye v Beavis
• Mr Beavis has a contractual licence to park in the car on the terms of
the notice posed at the entrance, including the two hour limit. The
charge was for contravening the terms of the contractual licence. This
is a common scheme, subject to indirect regulation by statute and the
British Parking Association’s Code of Practice. The charge had two
main objects: (i) the management of the efficient use of parking space
in the interest of the retail outlets and their users by deterring long-
stay or commuter traffic, and (ii) the generation of income to run the
scheme [94-98].
[cont’d]
• Unlike in Cavendish, the penalty rule was engaged. However, the charge
is not a penalty. Both ParkingEye and the landowners had a legitimate
interest in charging overstaying motorists, which extended beyond the
recovery of any loss. The interest of the landowners was the provision
and efficient management of customer parking for the retail outlets. The
interest of ParkingEye was in income from the charge, which met the
running costs of a legitimate scheme plus a profit margin [99]. Further
the charge was neither extravagant or unconscionable, having regard to
practice around the UK, and taking into account the use of this particular
car park and the clear wording of the notices [100-101].
• note: not relevant to discuss the UTCCR 1999
Applying the new penalty test to Cubic
Prepared by SM Choong/UMLaw/210519