Professional Documents
Culture Documents
Earned Value System PDF 4
Earned Value System PDF 4
Budget Management
Budget Development
• Good scheduling skills and abilities
• Understanding of the project scope
• Well developed WBS and project
schedule
57
Budget Management
57
Budget Management
57
Budget Management
57
Budget Management
58
Budget Management
Cost Budgeting
• The planning process that involves
summarizing, or aggregating, the
estimated costs for individual
activities to establish a total cost
baseline for the project.
58
Budget Management
Cost Baseline
• Time based budget that is used as a
basis for measuring, monitoring, and
controlling the overall cost
performance of the project.
• Also represents “Planned Value”
58
Budget Management
Cost Baseline
Cumulative Costs
Time
58
Budget Management
Cost Control
• The process of influencing factors
that create variances, and controlling
changes to the project budget.
58
Budget Management
59
Earned Value Management
60
Earned Value Management
60
Earned Value Management
60
Earned Value Management Example
60
Earned Value Management
60
Earned Value Management
60
Earned Value Management
60
Earned Value Management
Schedule Performance
Index (SPI)
SPI = EV / PV
•Good News: If SPI value is >1 or =1, the project
schedule trend is currently ahead or on planned
schedule
•Bad News: If SPI value <1, the project schedule
trend is currently behind schedule
61
Earned Value Management
61
Earned Value Management
Estimate at Completion
(EAC)
#1
Actual costs to date plus a new estimate for all
remaining work (original plan no longer valid)
EAC = AC + ETC
(ETC Estimate to Complete)
61
Earned Value Management
Estimate at Completion
(EAC)
#2
Actual costs to date plus remaining budget
(current variances are viewed as atypical of future
variances)
EAC = AC + BAC - EV
61
Earned Value Management
Estimate at Completion
(EAC)
#3 & #4
Actual costs to date plus remaining budget
modified by a performance factor (CPI) (current
variances are viewed as typical of future
variances).
62
EAC = BAC / CPI
Earned Value Management Example
62
Earned Value Scenario
63
Earned Value Scenario
64
Earned Value Scenario
65
Earned Value Scenario
Method #2:
EAC = AC + BAC – EV
= $48,000 + $100,000 - $42,000
= $106,000
(Change Management for $6,000 funds
request)
67
Earned Value Scenario
Estimate to Complete (ETC):
Method #3
EAC = AC + [(BAC – EV) / CPI]
= $48,000 + [($100,000 - $42,000) / 0.875]
= $48,000 + $66,285
= $114,285
(Change Management for $14,285 funds
request)
Method #4
EAC = BAC / CPI
= $100,000 / 0.875
= $114,285
(Change Management for $14,285 funds
67 request)
Earned Value Scenario
68
Budget Management
Module 6 Exercise
• Work as a team to perform EVM on
assigned project on page 69.
• Prepare a report similar to the
module scenario reporting project
progress.
• Brief class on methods of recovery, if
69
needed, for project.
Budget Management
$50K
$40K
$30K
$20K
$10K
1w 2w 3w 4w 5w 6w 7w 8w 9w 10w
Budget Management
$50K
$40K
$30K
$20K
$10K
1w 2w 3w 4w 5w 6w 7w 8w 9w 10w
$60K
$50K
$40K
Cost
$30K
Variance
$20K
Schedule
Variance
$10K
1w 2w 3w 4w 5w 6w 7w 8w 9w 10w