● Lumpy Demand
● Lead Time
● Time Phasing
PLANT PARAMETERS
● Execute tcode “OMI8” in command field from SAP easy
access screen.
● Step 2 : – On change view plant parameters for material
requirement planning screen, click on new entries button to
maintain plant parameters for MRP.
MRP TYPE
● ND – No Planning.
● PD – MRP.
● R1 – Time-phased planning.
● VB – Manual reorder point planning.
● VM – Automatic reorder point planning.
● VV – Forecast-based planning.
MRP GROUP
● Access the activity choosing one of the following navigation
options:
IMG Menu: Production -> Materials Requirements Planning
-> MRP Groups -> Carry Out Overall Maintenance of MRP
Groups (Transaction Code: OPPRC)
● On the MRP Group screen enter the Plant field and choose
Overview.
● On the Change View “MRP Control Parameters – Material
Level”: Overview screen choose New entries.
● On the New Entries: Details of Added Entries screen, make
the required entries.
MRP CONTROLLERS
● To create the MRP Controller there is no t-code.
● IMG.
● Production.
● MRP.
● Master Data.
● Define MRP Controller.
CREATION OF MATERIAL IN MRP VIEWS
● Go to the transaction code MM01.
● Enter the new material to be created, its industry sector and
material type.
● Then click on “Select Views” to select the views of the
material master that will be created.
● The views selected for our material master creation are
Basic data1 and MRP 1-4.
● Then press Enter.
GENERATING PLANNED ORDERS / REQUISITIONS
● Automatic planning
● Assembly To Order
● Purchase requisition with delivery scheduling