Professional Documents
Culture Documents
Rajesh Sharma
SAP Certified Consultant
ERP Sourcing & Procurement6.0,
SAP S/4 HANA Sourcing & Procurement,
SAP EWM 9.5 , SAP Activate 05
SAP ERP 6.0
Material
Requirement
Planning
✓ Basics of Material Requirement Planning
✓ MRP Profile
✓ Safety Stock
✓ Scheduling
✓ MRP Run
✓ Execution of MRP
MRP areas are optional. All Material Requirements planning can plan without referring MRP Areas.
1. Plant MRP areas (obligatory) that are automatically created by activating planning with MRP
areas. Their number match with number of plant, if MRP area is defined the MRP area covers
entire plant,
2. Storage location MRP areas that are defined by the storage location assigned to them.
3. Subcontractors MRP areas that provide requirements planning of the materials provided for
a subcontractor and are defined by the assignment of this subcontractors.
There are many settings need to made separately for each plant or for each MRP area. The actual
Planning procedure is exactly the same.
If the MRP type is to ND, then it is means no. Planning run is carried out for those materials.
Then their is no MRP procedure required.
MRP uses warehouse stocks, schedule receipts and requirements would be from sales order,
dependent requirements, order reservations, BOM explosions etc. CBP calculates requirements
When the stocks level goes below the permitted reorder point. The requirements would be
Triggered by the past historical data of consumption and forecasts data.
Above mentioned MRP type are available in standard SAP, customize MRP types could be
Configured based on business requirements. It could be configured with the help of copy option
From the existing MRP types, and changing the required fields to suit the business requirements
SAP CBP could be used for planning B and C materials. As this procedure could triggers
Requirements with less efforts and setup. It could be used for planning operation supplies also.
MRP could be use for A materials. As the stock level of A materials is very important and
Required to determine crucial decisions on materials, MRP would be used for planning of A
Materials. MRP calculates materials requirements based on the requirements triggered by the
Warehouse stock, schedule receipts and issues.
As opposed to MRP, consumption based planning
procedures are based on previous material
consumption. External requirements such as sales
Orders, planned independent requirements , and
reservations, are generally not relevant to planning.
MRP controllers with information about current issue
at same time. Is sales orders dependent manual
reservations, display in the current stock/requirements
list. The planning procedures in consumption-based
planning are easy to use methods of requirements
planning. That assist in achieving the goals with little
effort. The use of these MRP procedures is prefer in
areas without in-house production or in manufacturing
plant for plan B and C materials and operating supplies.
The following are planned directly as requirements in
MRP sales orders, planned independent requirements,
reservations. MRP is useful for planning finished goods,
and import assembly groups and components
(A materials)
In reorder point planning, checks are run to determine the planned available stocks (total from
plant stock and fixed receipts) fall short of reorder point determined for material in material
master record. If it fall down from reorder point the procurement must be triggered. The
reorder point should cover the expected average material requirement during replenishment.
Reorder Point are of two types
- Reorder point manually
-MRP controller determine Reorder point automatically where the system calculate the
reorder point using the forecast.
It uses historical values in the material forecast to estimate future requirements. These
requirements are future requirements are immediately available in planning. The system
executes the forecast calculation at regular intervals.
Time phase planning also uses historical values in material forecast to estimate the future
requirements. In this procedure the planning is only executed according to predefined
intervals. It can shifted to delivery time if a vendor always deliver a material on a particular
week day.
MRP Type are defined in customizing
for material management under
Consumption-based planning➔
Master Data➔ Check MRP types. The
MRP types is a key which use to
determine the procedure use for
Planning a material, and to determine
The MRP parameters that must be or
Can be entered during maintenance
of the Material Master Record.
For requirement planning different The MRP indicator for forecast determines whether the
MRP type parameters are relevant. Forecast values in the net requirements calculation are
MRP controller whether it is MRP or To be consider, if so whether as total requirements or as
Consumption based planning. Planned requirements. You can specify whether reorder
Forecast indicator can be use to Point and safety stock are to be automatically calculated.
determine the forecast results, are
To be used in planning. The
Consumption indicator for forecast
determine which historical values
used in planning.
The following Master data is required to
carry out MRP process:
MRP Data in the material master record can be sub divided into the following categories.
• General data that you must/can always define for a planning material
• Data dependent on MRP procedure
• Data required for scheduling
• Data required for lot-sizing calculation
This date specifies the order start date for planned orders and the release date for purchase
requisitions (Release in this context means the release of the purchase requisition for conversion
into a purchase order as a result of Purchasing).
The purchasing department processing time is calculated in workdays, and the planned delivery
time in calendar days.
The delivery date therefore stands firm (for planned orders, this means the order
finish date).
The purchasing department processing time is the time available for the buyer
to convert a purchase requisition into a purchase order. You determine this in
Customizing for Materials Management under Consumption-Based Planning →
Plant Parameters → Carry Out Overall Maintenance of Plant Parameters.
The planned delivery time is the number of days required to procure the material
from external procurement.
The goods receipt processing time is the timeframe between receiving the
material and the receipt in the warehouse. It is required for unpacking, checking,
storing material and so on.
The planned delivery time and the goods receipt processing time are determined
for each material. (You can also determine the planned delivery time in the outline
agreement or purchasing info record according to vendor).
T-code: SPRO→ Logistics General→ Materials Management→ Consumption based planning→
Master Data→ Check MRP type
Material Master Record for T-M525A-01 T-Code- MM02
SAP Easy Access→ SAP Menu→ Logistics→ Materials Management→ Material→ Display→ Display
Current
MRP 2 View GR Processing Time-1 day, Planned delivery time 02 day safety stock 10
T-Code : SPRO→ Material Management→ Consumption based planning→ Plant parameters→
Carry out over all maintenance of plant parameters Enter plant number
Planned Order :
. Describe the functions of a MRP profile and create own MRP profiles
. Explain how materials planned with reorder point planning are scheduled.
Thank You…………………..