Basements are constructed below ground level for additional space or buoyancy. There are four main methods of constructing basements - open cut, cut and cover, top down, and composite. Factors like site constraints, soil conditions, and construction speed determine the suitable method. Common retaining walls for deep basements include soldier pile walls, sheet pile walls, diaphragm walls, and contiguous bored pile walls. Dewatering and installing basement walls and floors are also important steps of basement construction.
Basements are constructed below ground level for additional space or buoyancy. There are four main methods of constructing basements - open cut, cut and cover, top down, and composite. Factors like site constraints, soil conditions, and construction speed determine the suitable method. Common retaining walls for deep basements include soldier pile walls, sheet pile walls, diaphragm walls, and contiguous bored pile walls. Dewatering and installing basement walls and floors are also important steps of basement construction.
Basements are constructed below ground level for additional space or buoyancy. There are four main methods of constructing basements - open cut, cut and cover, top down, and composite. Factors like site constraints, soil conditions, and construction speed determine the suitable method. Common retaining walls for deep basements include soldier pile walls, sheet pile walls, diaphragm walls, and contiguous bored pile walls. Dewatering and installing basement walls and floors are also important steps of basement construction.
level”. Basement are common in tall building as carparks, storage of services and underground shopping centres. The term “basement” has been regarded as synonymous to the term “deep pit”, which applies to excavation over 4.5m deep. The main purpose of constructing basement are:- 1. To provide additional space 2. As a form of buoyancy raft There are essentially four general methods of constructing a basement:- 1. Open cut method 2. Cut and cover method 3. Top down method 4. Composite method Open cut technique is the simplest method of providing an excavation to the required depth. The sides of the excavations are sloped in some cases with possible slope protection to ensure the stability of the solid mass. Upon excavating to the required level, the basement is then constructed from bottom upwards, in the conventional way. After the completion of the basement, the remaining excavation areas i.e. between the basement and the side slopes are subsequently backfilled. The cut and cover technique is used when the site is tight, e.g. located within a heavily built- up urban area, where ground movement to the adjacent surrounding must be kept to a minimum. Soil retaining structures are firstly erected to prevent the surrounding earth from sliding out whereas stuttering and bracing are also provided according to design so that excavation works can be proceed safely and at reasonable pace until reaching the deepest basement level. The basement is then constructed in the conventional way, bottom upwards in sequence with removal of the temporary struts. The top down technique is an extension of the cut and cover technique. In order to optimise the cut and cover technique, permanent basement structural walls (i.e. Diaphragm walling, contiguous bored pile wall) are employed to support the excavation face with the basement floor slabs acting as struts for external walls. The slabs depend on the prefounded columns as supports for the vertical loads on the floor. These columns are known as ‘profounded’ because they are constructed prior to bulk excavation. In this technique, the basement floor slabs are cast before excavation to the next level and construction proceeds from the top downwards for the basement structure The unique characteristic of the prefounded column is that it can be installed either for temporary use (for construction of basement only) or it can be designed as part of the permanent load carrying member for the completed structures. As obvious advantage of this form of construction is that the superstructure can proceed upwards from ground level simultaneously with the excavation downwards. The overall development may be completed months earlier than the conventional bottom-up approach in view of this overlapping of substructure and superstructure construction time schedule. Composite technique is a mixture of top down and bottom-up construction techniques. The main objective of this technique is to optimise the top down technique by solving the problem of excavation in limited headroom condition. As in top down technique, perimeter structural walls are installed to support the excavation face. Pre-founded columns are then installed. The perimeter portion of the storey 1 slab is cast off the ground, using the pre-founded columns to support the floor slab. Excavation to the middle portion proceeds to basement 1 formation level, where the slab is also cast off the ground. After completing the basement 1 slab, the middle portion of storey 1 slab is then constructed in a bottom-up upwards scheme. Since this form of construction utilises both bottom-up and top down technique The superstructure can then proceed upwards while simultaneously, the substructure proceeds downwards. Access openings are provided in the floor slabs for the removal of excavated material in the lower basements. The obvious merit of this technique is that excavation is facilitated with no headroom limitation except for the portion underneath the cast slab. This scheme will obviously speed the construction process considerably. 1. Site constrain which includes accessibility to the site and the proximity of existing building. 2. The soil condition, whether is consists of sand, clay, or silt. This is especially vital for the open cut technique. 3. The space for soil slopes within the perimeter of the site. 4. Speed of construction. 5. Whether the depth of basement is deep enough to justify the use of the technique that would have economies of scale. 6. Whether the site area is extensive enough for operations associated with the technique. 7. The cost of construction in terms of economy. 1. Retaining wall 2. Excavation 3. Dewatering 4. Basement wall 5. Basement floor 6. Waterproofing Some of the retaining wall which are commonly used in Malaysia for deep basement construction are as follows:- 1. Soldier pile walls 2. Steel sheet pile walls 3. Diaphragm walls 4. Contiguous bored pile walls (CBP) 5. Secant pile walls Consist of a vertical wide flange steel members with horizontal timber lagging. Often used as temporary retaining structures for construction and excavation. ELEVATION: Soldier Pile
PLAN: Soldier Pile
This is suitable method for site where the space around the excavation is insufficient for sloping back the sides. It’s usually necessary to provide lateral support at 1 or more levels above the ground that can be done using 2 ways that is internal braces or tieback anchor Tieback Anchors are tension members drilled into the ground behind the wall The most common type is a grouted anchor with a steel tendon The technique of building slurry walls involves the casting of concrete walls, from 450 mm to 1.5 m in thickness and up to 122 m in depth below grade around one or more sides of an excavation. Guide walls are normally constructed to improve trench stability and to serve as guides for excavation. The cast-in-place, reinforced concrete wall is placed in sections or panels, usually not exceeding 7 m in length and the full depth required. The completed wall may serve a dual purpose by acting as a retaining wall during the excavating phase and while the interior foundations are being built and later being used as the permanent exterior foundation walls for the building. The wall may be built in consecutive or alter nating panels, and the procedure will vary, depending on which system is used. Under the consecutive method after the first panel is complete, others are constructed next to it, on either side, and, except for the first one, all the panels will be the same, with regard to reinforcing and end forming. Diaphragm wall excavation
Basement top-down construction using diaphragm walls
Diaphragm wall reinforcement & concreting
Contiguous bored pile wall is a line of bored piles installed close together or touching. Smaller diameter micro piles may be installed in between each adjacent pile to close the gaps between the main piles. Grouting may be pumped in through performed pipes inserted into holes drilled between the piles. The typical sequence of construction is such that the next pile is to be constructed more that 3 m away from the previous one. Contiguous piling may be covered with mesh reinforcement or fabric faced with rendering or sprayed concrete/shotcreting/guniting. Contiguous Bored pile wall construction Secant piles are similar to contiguous bored piles except that they are constructed with two adjacent piles. Primary (soft) and secondary (hard) piles are interlocked into each other. The primary are not reinforced while the secondary pile are. The primary piles are first constructed in an alternate manner to leave a clear space for the construction of secondary piles later, the space being a little under the diameter of the secondary piles to ensure the interlocking. The primary piles are cast with the specified strength of mass concrete (usually lower strength concrete) without reinforcement. Before the concrete of the primary piles are fully set, the soil between two adjacent primary piles is drilled and/or cut along a parallel but slightly offset line, such that the holes cut into the sides of the two adjacent primary piles, using appropriate coring tools. Reinforcement cage is then lowered into the bored holes and concreted (usually with higher strength concrete) to form the secondary piles. In this manner, each secondary piles is positioned in between, and ‘secant’ with, two adjacent primary piles to form an interlocking joint. Excavation of soil for large basement may involve the support of the ground around it. Even if the soil appears to be self-supporting, precautions against collapse should be taken. The simplest solution is to cut back the slides of the excavation to the angle of repose of the soil, thus avoiding the need for temporary support. This requires access to a much larger area than the basement itself, and the removal and replacement of a large volume of soil. After the lowering of the water table, some form of retaining wall must be erected around the basement perimeter before the soil is excavated. Dewatering systems are divided into two, which are:- i. Sump pumping ii. Well point system A sump is constructed to collect the ground water, providing a suitable depth for pump to work in. The depth of the sump may exceed 7.5m. The water pumped out must be directed away from site. A more effective method of ensuring that water is removed from area of an excavation during the period of the work is de-watering by the well point system. This system requires a small device called a well- point to be forced into the ground using water jet. This is called jetting. The well-points are jetted into the ground around the proposed excavation down to a depth of five to six meters, which is the maximum for single well point system. The well-points are placed about every 1.5m and are link together by a ring main connected to a pump. As the well-point is jetted in, lengths of pipe are attached to it until the required depth is reached. When the suction pump is started, water is drawn through the well-point, which also screens out fine material. The pump must kept running continuously to keep water out of the excavation throughout the work. To increase the depth of the de-watering, a two stage installation can be employed. Basement structures can be waterproofed by one of three basics methods: i. Membrane system ii. Integral system iii.Cavity/ drainage system It provides a physical barrier forming a tanking system using either sheet membranes or liquid membranes or both. Sheet membranes are preformed, factory-made in rolls, which are bonded or cast against the substrate to form a continuous membrane by lapping. The common lapping for side laps are 100mm and end laps are 150mm. Lapping may be achieved by torching/faming, use of bonding compound or self-adhesive membranes. Liquid membranes come in either one or two- component in liquid or gel form. They are applied either by brush, rollers or spray. Liquid membranes give the flexibility for works on uneven surface and complicated details. It provides protection against water penetration based on the use of admixtures with waterproofing properties in the concrete mix to form concrete with surfaces that are repellent to water, and/or to fill the capillary pores hence reduces the permeability of the concrete. There are two main types of integral waterproofing systems:- 1. The hydrophilic - typically uses a crystallization technology that replaces the water in the concrete with insoluble crystals. 2. Hydrophobic system - uses reactive hydrophobic pre-blocking ingredients, fatty acids, silica fume etc to block pores within the concrete, preventing water passage. This method provides an excellent barrier to moisture penetration by allowing moisture that has passed through the structural wall to drain down within a cavity formed between the inner face of the structural wall and an inner non-load bearing wall. This inner wall is built of a floor covering of special triangular precast concrete tiles, which allows the moisture from the cavity to flow away under the tiles to a sump, where it is discharged into a drainage system either by gravity or by pumping.