Professional Documents
Culture Documents
Risk Definitions
and General
Categories
Definition of Risk
2
Traditional Definition of Risk
5
Risk Metalanguage Statement: Example 1
“As a result of more than expected test failures, more
design/build/test cycles may occur, which will lead to
schedule delays and added project costs.”
6
A complementary metalanguage for describing a risk in the
project's risk register is:
<RISK> due to <CAUSE >
7
The Potential Impact of Risks on Major Project Objectives
Project risks are associated with activities that could impact one or
more of the major project objectives—schedule, budget, scope, and
technical/quality. Project teams typically prioritize these objectives
in their own way, usually in accordance with key stakeholder
expectations.
Typically, the larger, more strategic, and complex the project is, the
more risks need to be addressed. In some circumstances, the team
does not have all the information and/or resources readily available
to address all risks at one time. Trade-off decisions that factor into
project priorities and relative risk-severity ratings are typically
required. it is important to understand the major project objectives
(and their priorities), and how to objectively evaluate and compare
project risks to facilitate sound project trade-off decisions.
8
Risks to Major Project Objectives:
10
Deciding on a response to an encountered issue (e.g., a
technical/quality requirements change) can be extremely
difficult at times. Do you accept the resulting risks to one or
more of the project objectives (e.g., try to absorb the change, but
recognize the potential for overrunning the project budget and
pushing out the project delivery schedule)? Do you adjust one
or more of the objectives (e.g., either make a counteracting
additional requirements change or appropriately adjust the
budget for the additional scope and make a commensurate
adjustment to the schedule)? Or do you decide on a combination
of both (e.g., adjust the budget to accommodate the added
scope, and add risk by trying to absorb the potential schedule
impact) based in part on the project priorities? Whatever
decision is made, it can benefit from sound risk management
practices. Objective evaluation of relative risk severities can
help.
11
Sometimes the likelihood of these encountered issues can
be foreseen (maybe due to past experiences) and identified
a priori as potential issues (risks) to project success while
planning the project. To facilitate decision making
regarding how to respond, it is helpful to have some
processes and guidelines (also referred to as “organizational
process assets”) to objectively and consistently assess risk
severity within the performing organization.
12
Discussion
13
Risk-Severity Definition
14
Risk Probability and Impact Scales
15
16
Risk Categories and Groupings
18
19
The Work Breakdown Structure (WBS)
20
21
Some large project development plans are split into phases,
where each phase is essentially organized as its own project,
which is dependent on the results of the preceding phase. The
project consists of several phases, including project planning,
design feasibility, design development, design verification,
low-rate production, and high-rate production. This type of
project lends itself nicely to the WBS risk categorization
process. For example, risk can be independently assessed for
each phase preceding high-rate production to determine
overall project risk in terms of meeting the major project
objectives up to that project milestone.