Professional Documents
Culture Documents
Theterm claim applies to the differences that are developed during the life of the contract under protests and
potential claims, and that are not yet resolved at the time the contractor returns the proposed final estimate of the
amount of additional money or time asked for.
Disagreements between the contractor and the owner, and sometimes including the architect/engineer, regarding
the following issues are increasing on construction projects
Interpretation of the plans and specifications
What should be considered as extra work to the contract
Payment for contract work and change orders
Extensions of time
Damages for delay caused by either the owner or the contractor
Changed or unforeseen conditions
Performance of subcontractors
Compliance with contractual requirements
Partial acceptance of a project by the owner
POTENTIAL CLAIMS ACCORDING TO FIDIC
POTENTIAL CLAIMS ACCORDING TO FIDIC
POTENTIAL CLAIMS ACCORDING TO FIDIC
POTENTIAL CLAIMS ACCORDING TO FIDIC
CHANGE ORDERS AND CLAIMS
Ingeneral, most claims issues will fall into approximately 10 classifications, with numerous variations
possible within each category.
Constructive changes
loss of productivity
Termination
Miscellaneous problems
CHANGE ORDERS AND CLAIMS
Differences Between the Parties
In order to establish that a loss has occurred, the court system requires proof for any of
the following:
The costs associated with the work of the contractor
The cost for the owner or the contractor to complete the work
If the owner delayed the contractor, the additional costs incurred by the contractor
The amount of profit associated with the work performed and for the work not performed yet and
any other consequential damages
The profit lost by the owner if the project is delayed or the contractor provides defective work
In addition to filing a claim for damages, an owner or a contractor could file a claim for
consequential damages. These are damages that are beyond direct losses
Owners might claim diminished or lost profits because of delays
Contractors could claim they lost the opportunity for additional business or their
bonding capacity was diminished or canceled by the surety
CHANGE ORDERS AND CLAIMS
Construction Delay Claims
In order to make sure that the projects are completed in time, a “time is of the
essence” clause is added to the contract
In the absence of such a clause, courts evaluate whether a project was completed
within a reasonable amount of time
In case the contractor delays a project, the owner can file a claim against the
contractor to recover damages
Four types of delays occur on construction projects:
1) Noncompensable excusable
2) Compensable excusable
3) Nonexecusable
4) Concurrent
CHANGE ORDERS AND CLAIMS
Construction Delay Claims
Are caused by owners and result in both a time extension and compensation being
provided to contractors. Compensable excusable delays result from circumstances such
as
Defective design/specifications
Nonexcusable Delays
manner
Poor workmanship
Lack of resources
Concurrent Delays
When more than one event delays a project, it is said to have been delayed by concurrent delays
Concurrent delays are delays that occur, at least to some degree, during the same time period and
that impact the critical path of a planned sequence of events
The term “ concurrent delay ” refers to the situation that arises when an excusable compensable
delay and a nonexcusable delay occur during overlapping time periods
One example of a concurrent delay would be when a contractor cannot commence work on the
second phase of a project because the owner has failed to obtain a necessary right-of-way, and
simultaneously, the contractor is prevented from commencing the second phase by its own
failure to timely complete antecedent first - phase work
CHANGE ORDERS AND CLAIMS
Exculpatory Clause – No damages for Delay
In an effort to relieve owners from liability for delay damages on construction projects,
many contracts now contain a ‘no damages for delay’ clause
This is an exculpatory clause (clears someone from an alleged fault)
It purports (claims) to excuse an owner from contractual liability for damages due to delays
caused by the owner
Such clauses are not always enforceable by law
To make this clause more enforceable, the owner should specifically list various types of
delays for which damages will not be paid
To counter this clause, the contractor can try and convince the court that enforcing this
clause will result in unconscionable (unreasonable) result and that the delays were not
foreseeable and claim that active interference, fraud and unreasonable delays occurred on
the project
CHANGE ORDERS AND CLAIMS
Exculpatory Clause – No damages for Delay
Advantages
Fiscalstability in terms of confirmed bid prices
Eliminates the need for lengthy delay claim litigation
Contractors would not try to delay the project willfully
Disadvantages
High cost of delay contingencies in bids
Less contractor turnout on bidding
Enforcement can cause contractor losses/defaults
Litigation might increase
CHANGE ORDERS AND CLAIMS
Evaluation of partial suspension or partial delays
Owners can result in delaying a project by creating hindrances from time to time on a project
Contractor can use the CPM schedule to demonstrate the involvement of the owner in causing
this delay on the project
In order to establish that the entire project was delayed by partial delays, it need to be shown
that:
Evidence that original duration and person loading estimates were accurate
Evidence that partial delay impacted the project
Evidence that the resources that were present on the project were capable of completing the work in
accordance with the original schedule
Float in a CPM schedule is considered as a resource and depending upon the type of contract,
can be used by any of the parties to a contract
A delay to the activities on the critical path amounts to a claim for damages
CHANGE ORDERS AND CLAIMS
Baseline for delay claim analysis
There are three different times to consider for analyzing a delay claim
Evaluating delays when the events that are causing subsequent delays occur (estimate or
project forward to assess delay)
Evaluating delays concurrently with ongoing delays or just after they are completed
Evaluating delays after projects are completed
Any delays (intentional) by the owner beyond this agreed completion date will
entitle the contractor to recover damages provided the contractor can prove the
adequacy of his performance plan
The types of delay damages that are awarded will vary from project to project
The categories of damages that could be recovered when a delay occurs are
Labor and/or material escalation
Increased engineering and supervision
Loss of productivity and loss of efficiency
Interests
Equipment costs
Impact costs
Field and/or main office overhead
Insurance
Bonding/Loss of Bonding
CHANGE ORDERS AND CLAIMS
Owner Damages for Delay
When delays are caused by contractor, owner is entitled to damages for such delays
These damages may consist of actual damages for the losses incurred, or liquidated
damages.
The following are damages for delays that could be awarded to owners:
Loss of use
Additional damages related to loss of use (increased financing cost, additional fees)
Increased Interest
Additional professional fees for architects and engineers
CHANGE ORDERS AND CLAIMS
Minimizing Delay Claims – Appropriate Clauses in Specifications
Liquidated damages – must be reasonable and the contract should provide the
mechanism on how these would be calculated