S. Capital Work Ant.

Name of the Project Status


No. (Rs Cr) Progress Completion Date
3 Maheshpur SILO 76.19 15% 05.10.2023 1. 2.5 km land out of 3.5 km route length is not available.
Siding, 3.45 Rkm Earthwork and Blanketing done in 0.70km.
(PMC) 2. Work of Major Bridge No.1 at CH:395 is in progress.
Girder will arrive at site in May 2022.
3. Excavation of foundation of Br. No. 3 is started after
receiving Forest Clearance.

ISSUES-
 Formation work from CH:450.00 to CH:1350m could not
be started for want of diversion of village road.
 Formation work beyond SILO (1.5Km) could not be
taken-up as back filling of Shatabdi OCP has not been
started till date.
Milestones Progress TDC
Earthwork 90% 31.07.2022
Major/Minor Bridges 80% 31.08.2022
Supply of P. Way Material 70% 30.09.2022
P. Way Linking 60% 31.10.2022
Commissioning 50% 30.11.2022
-----
S. No. Name of the Project Capital Status
(Rs Cr)

4 Dania to Kedla 5.31  FSR prepared by M/s RITES has been approved by Railway
Washery New (RITES in March 2021.
Railway Siding Fee etc.) Subsequent to final location survey work, Draft DPR has
(Approx 15 Rkm) been submitted by RITES to CCL on 04 st October. 2021 and
(FSR & DPR) 370 (DPR deliberations were held on Draft DPR on 19th October 2021
Cost) for firming up of route alignment.
 After various meetings, site visits and compliance of all
observations / remarks raised by CCL, the DPR submitted
by RITES to Railway 23.02.2022.
 Expected date to receive the In-principle approval of DPR
from Railway by MAY, 2022.

Milestones Progress TDC


Earthwork 90% 31.07.2022
Major/Minor Bridges 80% 31.08.2022
Supply of P. Way Material 70% 30.09.2022
P. Way Linking 60% 31.10.2022
Commissioning 50% 30.11.2022
-----