Professional Documents
Culture Documents
© 2014
© 2014
Pearson
Pearson
Education,
Education,
Inc.Inc. 3-1
Outline
► The Importance of Project Management
► Project Planning
► Project Scheduling
► Project Controlling
► Project Management Techniques: PERT
► A Critique of PERT
Planning Scheduling
► Establishing objectives
► Defining project
► Creating work breakdown structure
► Determining resources
► Forming organization
© 2014 Pearson Education, Inc. 3-6
Project Planning
Project Organization
► Often temporary structure
► Uses specialists from entire company
► Headed by project manager
► Coordinates activities
► Monitors schedule
and costs
► Permanent structure called
‘matrix organization’
© 2014 Pearson Education, Inc. 3-7
Project Planning
A Sample Project Organization
President
Human Quality
Resources Marketing Finance Design Production
Mgt
Project 1
Project 2
Project 3
Project 4
© 2014 Pearson Education, Inc. 3-9
Project Planning
The Role of Project Manager:
1. All necessary activities are finished in order
and on time
2. The project comes in within budget
3. The project meets quality goals
4. The people assigned to the project receive
motivation, direction, and information
1. Project
2. Major tasks in the project
3. Subtasks in the major tasks
4. Activities (or “work packages”)
to be completed
© 2014 Pearson Education, Inc. 3 - 12
Work Breakdown Structure
Develop Windows 8
Level 1 1.0
Operating System
Compatible with
Level 4 1.1.2.1
Windows 7
(Work packages)
Compatible with
1.1.2.2
Windows Vista
► Techniques
► Gantt chart
► Critical Path Method
(CPM)
► Program Evaluation
and Review Technique
(PERT)
Activity
Sequence
Project Duration
© 2014
© 2014
Pearson
Pearson
Education,
Education,
Inc.Inc. 3 - 18
Project Control Reports
► Detailed cost breakdowns for each task
► Total program labor curves
► Cost distribution tables
► Functional cost and hour summaries
► Raw materials and expenditure forecasts
► Variance reports
► Time analysis reports
► Work status reports
3.0
A 2.0 A and B must both be
(b) 2.5 C completed before C can start
B
2.5
3.0 B
B and C cannot begin until A is
(c) A 2.0
completed
3.0 2.0
A C C and D cannot begin until A and
B have both been completed
(d) 2.5 3.5
B D
© 2014 Pearson Education, Inc. 3 - 25
PERT: AON Convention
Activity on Activity
Node (AON) Meaning
3.0 2.0
A C C cannot begin until both A and B
are completed; D cannot begin until
(e) 2.5 3.5 B is completed.
B D
2 3
C F
2
4 2
A
E H
Start
3 4 5
B D G
Total 42 E G
Start
4 9
C D
© 2014 Pearson Education, Inc. 3 - 33
Deterministic PERT Analysis
6 3
(1) What is the critical path?
B F
8 What are the critical activities?
A 11 1 (2) What is the duration of the
E G project?
Start (3) Are there any path slacks?
4 9 If so, how long is each of the
C D slacks?
Start – A – B – F – G 8+6+3+1=18 2
Start – A – E – G 8+11+1=20 0
Start – C – D – G 4+9+1=14 6
LS LF
© 2014 Pearson Education, Inc. 3 - 40
PERT: Forward Pass
Begin at starting event and work forward
Earliest Start Time Rule:
EF = ES + Activity time
E H
Start 13 15
3 4 5
B D G
0 3 3 7 8 13
LS = LF – Activity time
0 2 C F
2
0 0 A 4 4 8 2
0 0 4 8
E H
Start 13 15
3 4 5 13 15
B D G
0 3 3 7 8 13
1 4 4 8 8 13
© 2014 Pearson Education, Inc. 3 - 46
PERT: Slack time & Critical
activity
After computing the ES, EF, LS, and LF times
for all activities, compute the slack time for
each activity, and identify the critical activity.
Slack = LS – ES = LF – EF
B G Slack = 0
D
0 3 3 7 8 13
1 4 4 8 8 13
© 2014 Pearson Education, Slack
Inc. =1 Slack = 1 Slack = 0 3 - 49
PERT: Critical Activity (Example 3.4)
Critical activities: A, C, E, G, H
Project duration is 15 weeks. Slack = 0 Slack = 6
2 4 4 7
Slack = 0 2 4 10 13
2 3
0 2
C F
Slack = 0 0 2 2
0 0 A 4 4 8 2
0 0 4 8
E H
Start Slack = 0 13 15
3 4 5 13 15
B D G Slack = 0
0 3 3 7 8 13
1 4 4 8 8 13
© 2014 Pearson Education,Slack
Inc. =1 Slack = 1 Slack = 0 3 - 50
Note
▶ Activity slack time:
▶ PERT Algorithm
▶ Example 3.4
▶ Path slack time:
▶ Deterministic PERT Analysis
▶ Example 3.3, 3.2
Start
End
3 9 5
B C F
© 2014 Pearson Education, Inc. 3 - 52
PERT: Example 3.5
Step 1: Use forward pass to calculate ES and EF
ES EF
LS LF
0 7 12 17 17 19
7 5 2
0 0 A D E
19 19
Start 3 9 5 End
B C F
0 3 3 12 12 17
3 5
M N End
Start
8 7
K O