The objective is to ensure that all defence works and services – capital,
revenue and maintenance – are completed within time frame and in a
cost-effective manner compatible with the efficient functioning of the
Defence Services..”
BASIC PRINCIPLE OF UNDERTAKING DWP
PREVIEW
Cl Of Wks
Minor Wks – Up to 1 Lakh
Rev Wks – Up to 2 Lakhs
LBCW – 2 Lakhs to 15 Lakhs
AMWP – Above 15 Lakhs
Cl Of Wks
Original Wks
Minor Wks – Up to 5 Lakhs New Original wks
Rev Wks – 5 Lakhs to 10 Lakhs Authorized wks
LBCW – 10 Lakhs To 45 Lakhs Special Works/items
AMWP – Above 45 Lakhs
Note. The Listing Of LBCW Works Less Than Rs 45 Lakhs Shall Be Done By Comd HQ And
The Apvd List To Be Submitted To Mod For Monitoring.
Repairs
Ordinary repair Wks
Petty Repairs
Periodical services
Replacements & renewal –Upto 4.5 Lakhs for each item
Repairs, Renewals & Replacement of E&M – upto 6 lakhs
each item
Special Repair – Repair,renewal, replacement beyond ordinary repair
Note. Spl repair treated as Original wks budgeted under Revenue Head, not permitted or
repeated within 5 yrs in same portion of building/assests.
PARA 10(A) Spl Repair
“Spl repairs will not be permitted in a bldg/ portion of bldg/ asset within five
yrs of completion of the original wk. Also spl repairs will not be permitted
to be repeated within five yrs in the same portion of bldg/ asset”
Demand for and Plg of New Wks Demand for and Plg of New Wks
AMWP.
PARA 18(B)
Apvl of this AMWP by govt will be Approval of this AMWP by govt will be
considered as approval in
principle of the implementation of considered as Approval in Principle (AIP)
the wks pgme in respect of those for the implementation of the wk pgme
wks who’s bps and rough
estimates have already been and Acceptance of Necessity (AON) for
scrutinized by CEA and adm & incurring expdr towards preliminary
associated fin auth. This apvl will
however be subject to adequate activities. AoN and Adm apvl for each
allocation of funds. This will wk will be obtained as described. This
enable the engrs to obtain a ‘go
ahead’ sanction from CFA approval will however be subject to
wherever considered essential adequate allocation of funds. A bulk go-
not exceeding 5% of the approx
cost estimate in a specific case. ahead sanction upto 2% of the AMWP
In such of the cases where bps ceiling amt will be sanctioned along
and rough estimates have not
been scrutinized as mentioned with apvl of AMWP list. This will
above, inclusion of these cases in facilitate adv/ concurrent plg and exec
MWP/AWP will provisional
subject to these being scrutinized of prep/ pre-investment wks.
subsequently.
PARA 17
The annual wks pgme for maj capital wks (excluding special proj)
should be prepared and submitted by 31st Aug.
Apvd by the govt before 31st Oct of the previous fin yr.
Pre adm plg can be completed and Adm approval can be issued
from 01st Apr of the fin yr.
PARA 20
Minor wks should not be carried over and should be completed during
the same fin yr.
Demands for new Major Capital works services will be submitted in the form of a
Statement of Case to the Competent Financial Authority for consideration and
approval. The SoC will inter alia explain :-
(a) The need for and scope of the works proposed.
CONTENTS OF SoC
(ii) Tenders will be issued only after obtaining cert of encumbrance free
def land/ site from the Stn Cdr. In case of Spl Projs/ wks executed by CCEs
where provn of issue of tender before receipt of Administrative Approval
exists, tenders will be recd only after obtaining cert of encumbrance free
def land/ site from the Stn Cdr.
In case of new wks proposals requiring AA of a CFA of the level of Service Headquarters/ Govt, such
proposals may be submitted to the CFA along with both Board Proceedings and AEs for obtaining AoN
and AA at the same time.
(a) In case of new wks proposals requiring AoN and AA of a CFA of the level of Service
Headquarters/ Govt, such proposals may be submitted to the CFA along with both Board
Proceedings and AEs for obtaining AoN and AA at the same time.
(b) For wks to be executed in ph the apvl will be given on the basis of AEs for Phase I and RIC for
subsequent ph.
PARA 29(C)
Contingencies will be provided at 3% of the estimates. Establishment ch will not be incl for
MOD establishment wks but will be incl for deposit wks. Establishment ch, if any, may be
incl in the estimates after recording reasons there for in each case, but will not exceed 2%
of the estimates. In addition, consultancy ch not exceeding 3% may be incl in the
estimates. Any addl expdr on consultancy will require the apvl of concerned CFA.
Contingencies will be provided at 3% of the estimates. In addn the fwg charges may also be incl in
the estimates(AE) as per reqmts: -
(i) Establishment Ch. Establishment ch, if any, may be included in the estimates not exceeding 2%
of the estimates for deposit wks.
(ii) Consultancy Ch. The amt of consultancy ch not exceeding 3% of the estimates may be incl
in the estimates which is catered out of bulk Go-ahead sanction with proper justification in the
Engr Appreciation. However for wks where bulk Go-ahead has not been provided, Consultancy
charges not exceeding 3% of the estimates with proper justification in the engr appreciation, may be
incl in the estimates separately. Where consultancy services of specific nature are envisaged
for large projs, provn as reqd (with due justification) may be incl separately.
(iii) Supervisory Ch. When services for supervision of wk are to be hired/ outsourced, an addl
2% of the estimates will be added as a supervisory ch. The reqmt should however be fully
justified in the Engr Appreciation which forms part of the BPs.
(iv) An amt of 3% may be added towards consultancy for dwgs and design wherever Design
and Build/ EPC methodology/ Turnkey projs are adopted. No other ch towards consultancy will
be added in such cases.
PARA 29(G)
In case of wks sch to be completed within two yrs, no escalation, except statutory increases, will be
allowed in the contracts for exec of such works. AEs for such works will be prepared accordingly.
(i) In case of wks with Job Planned Date of Completion (Job PDC) less than two years, no
escalation will be catered for in the AEs. Further, the contract shall also not incl any escalation
clause except statutory increases.
(ii) In case of wks with Job PDC of more than two years, escalation will be allowed only in
contract but not in AEs.
TIME FRAME FOR PRE-ADM APPROVAL
PLANNING
Sr No
Propose
Activity (in weeks)
1 Initiation of Demand for new works with SoC, RIC & Engineer Appreciation
6
2 Listing of AMWP
3
3 BPs with Aes
12
Para 34 to Para 36
(a) Para 34 : if for urgent military reasons delay involved in the issue of AA based on AEs
cannot be accepted, the CFA is empowered to order commencement of work on essential items
of required work such as collection of store, site clearance, external service, prelim wks etc.
prior to the issue of AA.
(b) Para 35 : Circumstances may arise from unforeseen operational necessity or urgent medical
grounds or out of natural disasters.
(d) Para 36: Again in the case of imminent danger to buildings, roads etc, or of a breakdown of
supply from an E&M or water supply installation, when delay would be seriously detrimental to the
public service
(e) Para 37:The procedures outlined in Paras 34 to 36 above do not dispense with the necessity for the
issue of AA by the CFA. Such works can be started without waiting for specific allotment of funds for the
project.
Scope of work shall be finalized by BOO and BPs shall be kept ready before receipt of
tenders for main tender. Issue of covering AA shall be prioritized and issued within 6
months from the date of submission. If delayed beyond six months the AA will be issued
by the next higher CFA.
PARA 39
APPOINTMENT OF CONSULTANTS
(a) Engr authorities would be authorised to engage consultancy services for plg of wks relating
to formulation of civ wks projs, prep of feasibility and proj reports incl svy and site investigation
wks as well as for plg, prep of structural/ architectural dwgs and designs, development of
specifications, prep of bill of quantities, cost estimates and constr managements of the proj.
(b) In case of Govt/ semi Govt agencies, the consultancy services may be entered into through
Limited/ selective tendering. Limited tendering amongst private consultants may also be
adopted in cases where the cost of consultancy services is upto Rs. 25 lakhs.
(c) For sanctioned wks, expdr incurred on the consultancy services will be debited to
“consultancy ch” as catered for in AA based on due justification, or to cgy items, where
“consultancy ch” are not incl in the AA.
(d) The expdr towards consultancy services will not gen exceed 3% of cost of the proj.
(f) CE/ CWE is auth to invite Engrs/ Architects/ Management professionals and other specialists
to review imp projs designs and schemes for spl projs/ specialist wks. The expdr shall be made
out of the consultancy ch or proj contingencies
PARA 55(C)
PMG
In case of all projs/wks costing more than Rs. one cr, a representative of the User will be nominated
as Project Officer to coordinate functional aspects of the User’s reqmt with the engrs from the
commencement to the completion of such wks.
PMG
(i) In case of all projects/ works costing more than Rs. 1.50 cr, a representative of the User will be
nominated as Project Officer to coordinate plg and functional aspects of the User’s reqmt with the
engrs from the commencement to the completion of such wks.
(ii) Project Management Group (PMG) to be detailed for projs exceeding Rs. 5 cr by the Stn
Cdr and wks above Rs. 10 cr by the Comd HQ.
(iii) During the exec of the wks, as far as possible, any demand for change in scope of wk or
retrofitting of designs and/ or specifications will be discouraged as it leads to interference
with wks pgmes and delay in completion of the projs.
(iv) Guidelines to be formulated and issued by respective Service HQ with the approval of
MoD regarding the Role, Responsibility and Accountability of PMG in monitoring/ review of
projs. There shall be no cross-interference in functions and responsibilities of Engineer
Authorities and Administrative Authorities.
ENHANCED FIN POWERS
POWERS OF AoN & AA
To be executed without IFA’s To be exercised with IFA’s
Remarks
CFA Concurrence Concurrence
Auth Wks Spl Wks Auth Wks Spl Wks
Govt of India Full Full Full Full
COAS 400.00 40.00 5000.00 250.00 These powers
shall be vested
(120.00) (20.00) (1500.00) (75.00) with equivalent
QMG 240.00 25.00 3000.00 150.00 appointments in
(-) other ests.
(-) (50.00) (2.00)
GOC-in-C 160.00 16.00 2000.00 100.00 Figures as
(75.00) amended by Def.
(7.00) (500.00) (30.00) (Fin)
Corps Cdr/ Area Cdr (Lt 80.00 8.00 1000.00 50.00
Gen)/ Comdt Cat ‘A’ Est (Lt
Gen) (37.00) (3.75) (300.00) (15.00)
Div Cdr/ Indep Sub Area 40.00 4.00 500.00 25.00 () – Figs as per
Cdrs/ CIF RR/ Cdr Indep Bde DWP 2007
Gp/ GOC Sub Area, Comdt (22.00) (0.75) (200.00) (8.00)
Cat ‘A’&‘B’ Est, Trg Centre
(Maj Gen)
Stn Cdr of rank of Brig/ Bde/ 25.00 2.50 250.00 10.00
RR Sectors/ Comdt Regtl
Centres & Cat ‘B’ Est (5.00) (0.50) (-) (-)
CO/ OC – below the rank of 8.00 1.00 50.00 2.00
Brig
INTO BATTLE WITH RESOLVE