Source to Batching Plant Activity Flowchart

(Construction Material Management Process Flow)

(Final Storage Zone) (Temporary Storage Zone)


Rectification as applicable Issue MIRF with following
Approved & Routine
(Cleaning, Screening, attachment(s):
 Delivery Notes (Copy)
Quality Checked Material Washing, etc.)  Test Forms
 MTC (Cement, Admixture, Re-bar
etc. as applicable )
(Wait for Routine Quality Test if
5Batching Plant 4 Pass 3 Pass/Re-inspection necessary)
Fail 3
1

Sample to Laboratory for Test


Approved Source to Secondary or
Temporary Storage
Note:
1. Use Separate Stock-pile respect to aggregate type and size.
2. Use Name Boards to mark or notify Approved/ Unapproved Stock-
pile to avoid segregation and contamination.
3. Course Aggregate shall be available Minimum 7days prior to use.
2
Site Laboratory

Out from the Site