You are on page 1of 26

NEC TOOLKIT

®NEC 2022
CONTENTS

INSTRUCTIONS FOR USE 3 CHOOSING THE RIGHT NEC CONTRACT 19


……………………………. ……...

WHAT IS NEC 4 NEC CONTRACT FORMS 20


…………………………………............ ……………………………..

WHY NEC EXISTS 5 NEC CONTRACT STRUCTURE 22


………………………………………. ……………………...

INDUSTRY ADOPTION AND 7 WHERE NEC IS USED 23


RECOGNITION .. ………………………………….

NEC BEST PRACTICE 8 NEC COMMUNITY 24


………………………………….. ……………………………………..

WHY CHOOSE NEC 9 NEC SUPPORT 25


………………………………….... ………………………………………
®NEC 2022
INSTRUCTIONS FOR USE
The purpose of this NEC Toolkit is to help inform all users of the NEC, whether
first time or experienced users, when making executive decisions on the
procurement and contract strategy.

It can be used to help understand what influences the decision for any of the
following and more:

 whether to choose the NEC over other forms of contract


 which NEC contract to use
 the appropriate allocation of pricing risk – main Options
 the appropriate allocation of liability and other risks
 considering Secondary Options
 whether design and construct or construct only

Additional resources can be accessed by clicking the buttons


throughout this toolkit.

The NEC suite of contracts has differing terms for the organisation providing the
works/services, etc., as well as for the role of administering the contract, this toolkit refers to
them as ‘the contracted provider’ and ‘the Client’s contract manager’.

®NEC 2022
WHAT IS NEC
Play the Introduction
The NEC (New Engineering Contract) is an evolving family of
to NEC4 video
procurement contracts that were originally launched in the UK in 1993 and
developed as a modern-day alternative to traditional construction contracts.
The NEC is currently in its 4th edition (NEC4).

It aims to be a worldwide benchmark for best practice in the procurement


and delivery of work, services and supplies and it is successfully supporting
the delivery of thousands of projects worldwide.

It is a contract built around proven best practice in project management and Play the Introduction
it engenders a collaborative approach to management and delivery.
to NEC4 FMC video
Find out more about the NEC family of contracts by clicking on the video thumbnails

Evolution of NEC NEC Glossary of


Contracts Terms
®NEC 2022
WHY NEC EXISTS
NEC offers a sophisticated and
comprehensive solution built
on three main principles of, Fair and sustainable Choice of optional contract
Choice of pricing and delivery
clarity & simplicity, flexibility, models allocation of risk clauses
and to be a stimulus to good
management. Requirement to act in spirit of Alignment of all sub-contracts
mutual trust and co-operation Alignment of interests
Enabling organisations that Options for multi-party
collaboration or alliance
Options for sharing risk & reward
are willing to work in
collaboration to realise major Early identification of risk Options for dispute avoidance
Early warning procedure
benefits such as to the project inspections

demonstrating value for


Process for resolution of
money through utilising the Process to deal with early warnings Timely implementation of compensation events
effective project management Senior representatives of parties change
Formal adjudication procedure
deal with most disputes
procedures and best practice
in procurement. Regular updates of delivery One source of truth on All parties agree each update of
programme and anticipated final project status and costs the delivery programme
costs

Increased confidence of
Delivering better outcome
project outcomes

®NEC 2022
Procurement processes and project goals can differ significantly from one
another, meaning there may be many variables that can impact on delivery,
commercials outcomes and resources.

The NEC promotes and enhances collaborative working and if used in this manner
helps achieve greater cost certainty, delivery to agreed timescales and
appropriate quality standards.

The NEC is intended to be used and referred to throughout the project lifecycle, from preparing
the business case to operation and maintenance of an asset. It incorporates robust real-time
approach to change management that allows parties to deal with change quickly, effectively and
in a collaborative manner, helping to avoid or reduce the impact on the overall cost and
programme.

NEC can also help save on legal fees. NEC4 provides a set of standard ready to use contracts
which are designed to work best when they have not been amended – although they do of
course provide the option for appropriate amendments to be made to suit specific circumstances
and/or requirements, such as country specific laws.

How NEC can help NEC delivering better


NEC Risk Allocation
your business value
INDUSTRY ADOPTION AND RECOGNITION
The NEC was the first contract to introduce a collaborative
approach to risk and contract management, include an
adjudication process and written in plain language.

In 1994 Sir Michael Latham’s report, ‘Constructing the Team’,


highlighted and recommended the use of the NEC:

“The NEC is capable of being a common contract for the whole industry.”

“The New Engineering Contract contains virtually all of these


assumptions of best practice, and others, which are set out in the
Core Clauses, the main and secondary options.”

“Public and private sector clients should begin to use the NEC, and phase out "bespoke" The NEC has received
documents” Government Endorsement by the
Government Construction Board,
“Use of the NEC by private sector clients should be strongly promoted by client and industry
bodies.”
Cabinet Office UK and the
Development Bureau, HKSAR
Government, further instilling
This allowed NEC to be adapted and adopted across all industries often
confidence in its use on public
becoming the contract of choice for both small, low risk to large and
sector projects.
®NEC 2022 complex projects internationally.
NEC BEST PRACTICE

NEC4 contracts:
Provide clear Allow to forecast the
documentation and Promotes active Ensure an
adequate and fair real effect of any
outline of roles, management
compensation change on time and
responsibilities and cost
processes model

Instil a level of Support and Help minimise


Define timescales certainty of the encourage chances of formal
for all activities project outcomes collaborative disputes occurring
working

®NEC 2022
WHY CHOOSE NEC

When an organisation is looking to carry out


construction or any other project work, they need to
decide on the appropriate form of contract – often with the
guidance of professional advisors.

They and their advisors may have some experience of


certain forms of contract, and be wary about using NEC
either because they know little about it or, because of the
many misconceptions that exist about it.

The following high-level guidance on NEC contracts will


provide decision makers and key business stakeholders,
with critical information necessary to make an assessment as to
which form of contract is right for their business and it is hoped,
instil confidence in the philosophy behind the NEC contract.
The guidance shows how the NEC contracts deal with issues of concern at
various parts of an organisation – board oversight, finance, legal, procurement
and operational.

®NEC 2022
GUIDANCE - BOARD OF DIRECTORS
Confidence in the proposed Certainty of outcome
contract outcomes
NEC contracts have been
Governance process The contract restricts changes
used since 1993 with users to time and price to a set of
reporting positive The Client appoints people specific grounds and clearly
experience to manage the contract and defined processes – there are
monitor performance - no provisions for global
Governmental approval of controlling cost, time and claims of additional cost
the use of these contracts quality - on its behalf and/or extension of time
has been given in UK, Hong
Kong and South Africa The Client’s contract There are strict change and
manager has the authority risk management procedures
Many clients who have to instruct a change to the with clear timescales for
adopted NEC contracts use Scope where necessary, e.g. action and sanctions for
them repeatedly for their if the Client’s requirements failures to act
work change
If there is an entitlement to
A range of digital contract Except where the conditions change the price or
management systems exist allow, the contract cannot programme, it is
which support the contract be changed without written implemented at the time of
administration and provide agreement of both Parties the event, giving the Parties
accessibility and visibility of knowledge of cost outcome
the contract processes and projected completion of
work
GUIDANCE - BOARD OF DIRECTORS (continued)

Deliver social outcomes Protect reputational risk


Interfaces between the contracted Anti-corruption provisions are
provider and any third parties to included, with stated consequences
the contract which may be needed if any corruption is found to have
to achieve the project objectives, taken place
can be specified by the Client and
identified in the contract The Parties are prevented from
disclosing any information obtained
Key performance indicators can be in connection with the work except
incorporated into the contract as necessary to their duties under
which can be used to incentivise the contract
social outcomes by rewarding for
achievement or improvements The contracted providers can only
publicise the work if the Client
Provision to include climate change agrees
requirements and set targets with
financial incentives for achieving or The contracted providers use of
improving on them can be included Client material is restricted to that
necessary for providing the work

®NEC 2022
GUIDANCE - FINANCE DIRECTOR
Reporting and integration
Financial controls
The contract requires the
The contract makes available a
contracted provider and the
wide range of commercial,
pricing and risk options to suit Client’s contract manager to
prepare regular updates of the The Client’s contract manager
all circumstances, from lump provides regular reports as
forecast outturn cost in
sum to cost reimbursable prescribed by the Client in the
consultation with each other on
The contract specifies a list of cost reimbursable and target Scope of the contract between
The liabilities of the Parties and them
events which can give rise to a based contracts
the types of insurances required
change in the cost and timing of to cover these liabilities are A value engineering clause has
The Client specifies its
the work stated in the contract been added to the unabridged
requirements and standards for
Changes to the cost and timing financial reporting by the contracts which shares the
A Project Bank Account option is benefits of any accepted
of the work are assessed at the contracted provider within the
available for UK contracts, proposals
time of a specified event scope, this enables integration
allowing for faster payment
through a process designed to with the Client’s systems
whilst also providing security of Target contracts contain a
encourage the agreement of the payment for the supply chain mechanism for sharing financial
effects of the change, with the gains as well as over spends
aim of reducing the chance of Open book accounting provides against the final amended
disputes transparency and helps forecast target price
as well as authenticate cost
when the cost reimbursable and
®NEC 2022
target options are used
GUIDANCE
GUIDANCE - LEGAL
- LEGAL COUNSEL
COUNSEL
Confidence in legal outcome Risk management Liabilities
The NEC has been in use since 1993 by Risks carried by the Client are clearly The Parties liabilities, including those for
repeat clients. Its adoption was identified under core clause 6 as damage or injury and the corresponding
recommended by Sir Michael Latham compensation events. There is a clear allocation of costs, are clearly set out in
and it has been endorsed by and strict process for determining the core clause 8 of the contract
Governments effect on both time and cost should an Liability for third party risks are allocated
event occur in the contract under core clauses 2, 6, 8
There have been only a limited number A mandatory early warning procedure and additionally through the inclusion of
of legal cases referred to the Courts with requires the early identification of all secondary option Y(UK)3.
no significant adverse findings risks to time, cost and quality, followed Contract includes options for requiring
by a review of the options for avoiding or the contractor to provide a performance
Clear dispute escalation and resolution
reducing the effects, recording the bond or ultimate holding company
processes and options involving Senior
actions which should be taken and by guarantee
Representatives of the Parties,
whom; the contract manager facilitates
adjudication or a dispute board can be Option for undertakings to others
the process and takes the final decision
followed by either arbitration or a Court (warranties)
process Client requirements for managing risks,
including health and safety and the Client states any limits to the liability of
Country specific Secondary Options are protection of data are stated in the Scope the contractor
available for inclusion with provisions Procedures for termination and
Contract procedures oblige co-operation
which incorporate legislative consequent liabilities stated in the
and encourage the agreement of change,
requirements contract
aiming to reduce the chance of disputes 
Contract manager cannot relieve
®NEC 2022
Contractor of its responsibilities
GUIDANCE – PROCUREMENT/COMMERCIAL DIRECTOR
Procurement options
A wide range of contracts to suit all types of
work and contracting arrangements including
alliancing, management contracting, design
build and operate, as well as more traditional Secondary Options provide great flexibility
forms available in long and short versions to select appropriate provisions to meet
procurement requirements, allocate risk,
Different pricing options provided to allow introduce sectional completion, incorporate
the selection of preferred pricing methods an information model (BIM) among other
and risk allocation including, lump sum needs
contracts, measured contracts, target
contracts (sharing potential cost Option for early contractor involvement –
savings/overrun), cost reimbursable contracts before design finalised - to work with the
Client in completing design, assessing risks
The contract includes an option for and incorporating buildability, etc.
identifying Conditions and Key Dates which
enables the co-ordination of multiple Design responsibility is by default retained
contractors working on the same project to by the Client but can be transferred in full
work collaboratively or in part to the contracted provider

®NEC 2022
GUIDANCE – PROCUREMENT/COMMERCIAL DIRECTOR (continued)

Progressive finalisation and


agreement of the audited cost in cost
reimbursable and target contracts

Assessment of the final payment is


conclusive evidence of the final
Contract controls amount due unless either Party refers
it to the dispute process
The Client’s contract manager is in Change to cost and time determined at
control of cost, time and quality the time of the event Bonus for early completion and/or
delay damages can be included within
Change control is managed by the A wide range of incentives can be the contract to motivate timely
Client’s contract manager, with an included in the contract, through the completion
option to seek alternative assessments inclusion of Secondary Options for KPIs,
that provide an appropriate balance of sharing of benefits for cost savings, No change can be made to the scope
time, quality and cost which meet the whole life cost improvements, meeting of work without an instruction by the
Parties needs environmental targets, etc. contract manager

®NEC 2022
GUIDANCE - OPERATIONS DIRECTOR
Change control
Contract management The contract lists the The early warning process
events which could give not only identifies
Active management of An early warning register The contracted provider is rise to a change in cost or potential risks to the
the contract by the is maintained to identify required to operate a completion of works and project but also what
Client’s contract manager and mitigate the risk to quality management services actions to take and by
allows the timely time, cost, quality and system which complies whom
agreement and disruption to the Clients with the Client’s Change in cost and/or
instruction of Tasks operational activities requirements completion established at The decision of the
the time of the event contract manager is final
A regularly updated The contract manager
programme/plan shows subject only to the
controls the acceptance Some of the contracts
future work and forecast dispute resolution
of subcontractors and key include acceleration
dates to meet contract process
people provisions.
requirements
The procedures
The change event process
allows continuous encourage collaboration
updating of forecast and the agreement of
outturn cost and time to change, aiming to reduce
complete work the chance of disputes

®NEC 2022
GUIDANCE - OPERATIONS DIRECTOR (continued)

Staffing requirements
The contract can be The Client’s contract
managed by the Client using manager is responsible for
internal staff or contracted the successful completion of
out to a specialist the contract and will need to
organisation have the appropriate skills

The Client has a limited Training in the use of the


contractual role compared to contract including NEC
that of the Client’s contract accreditations, is available
manager. The Client’s either in-house or in open
contract manager needs to courses to ensure that
have a thorough people have the appropriate
understanding of how the skills
contract is operated

®NEC 2022
DIFFERENCES BETWEEN THE FULL AND
SHORT CONTRACTS
When to Use | Risk Level | Management

Full Contract Short Contract


Short contracts are an abridged version from the
Complex Projects full contract and are used where sophisticated
No restriction on value management techniques are not required, the
work is straightforward and imposes only low risk
on both Parties.
High risk transfer
Manage Early Warning Register
Straightforward Work
No restriction on value
Sophisticated management tools
Complex programme /plan requiring acceptance
Low risk transfer
No Early Warning Register

Low administration burden


No Accepted Programme

®NEC 2022
CHOOSING THE RIGHT NEC CONTRACT
PSC & PSS
HIGH

ECC & ECS The NEC suite of contracts caters for a


wide range of works and services. The
SC
ed
principal NEC4 contracts, short
g
rid FM & FMS & FMSC contracts and subcontracts can be
a b broadly grouped into
n
Complexity & Risk

TSC & TSS


U works services supply
ALC
as shown in the matrix. The choice of
DBO contract depends on the type of project
PSSC and its complexity and levels of risk.

ECSC & ECSS

ort
Sh
SSC
LOW

TSSC Choosing the right


contract
FC
Contracts
Other

DRSC

Business Case Design Delivery Operation


*to identify the acronyms, please hover over the relevant text and click the hyperlinks
NEC CONTRACT FORMS

Professional Service Engineering & Supply Contract Facilities Management Term Service Contract
Contract Construction Contract Contract
Used to for the Used to employ a
Used to employ a Used to employ a procurement of high Used by a Client to supplier for a period of
consultant to undertake contractor to undertake value goods and related appoint a Service time to manage and
any kind of professional any kind of construction service including design Provider for a period of provide a service
service work including design time to manage and
responsibility provide any type of
facilities management
®NEC 2022
services.
Alliance Contract Design Build & Operate Framework Contract Dispute Resolution
Contract Service Contract
Used to employ a Used for the
contractor to undertake Used to for the appointment of one or Used for the
any kind of construction appointment of a more suppliers over a appointment of an
work including design contractor for design, set term to carry out adjudicator or dispute
responsibility construction or work or provide a avoidance board
modification and service or goods on an member to resolve
operation of assets ‘as instructed ’ basis disputes under NEC4
using NEC4 contracts. contracts
®NEC 2022
NEC CONTRACT STRUCTURE

Contracts are designed modular,


consisting of core clauses, main and
secondary contract options, dispute resolution and
jurisdiction-specific options, and additional contract
conditions.

NEC uses consistent language across all its contract


suite. Roles such as Project Manager and Supervisor
will vary with contracts. For example, TSC, PSC and
DBOC use Service Manager and have no Supervisor.
The obligation however remains constant.
WHERE NEC IS USED

 Construction  Hospitality  Pharmaceutical


 Infrastructure  MMC  Water View all the NEC Case
Studies here
 Energy  Oil & Gas  Waste

NEC can be used anywhere in the world. It is written in plain English, supporting ease of use and translation. Optional Y
Clauses allow specific provisions of local law to be incorporated into contracts. It is in use in the UK, Hong Kong, South
Africa, New Zealand, Australia, France, Germany, Ireland, the Netherlands, USA and the UAE. In 2019 NEC delivered the
venues and facilities for the Pan-American and Parapan Games in Peru.
NEC can also be used in any sector. The contract was first developed in the construction sector under the leadership of the
Institution of Civil Engineers, one of the world’s most respected professional bodies. Over the last three decades its use has
spread into sectors as diverse as oil & gas, infrastructure, facilities management, software, telecoms and pharmaceuticals.

®NEC 2022
NEC COMMUNITY

Online space to bring


together the NEC user Dedicated hubs for
community particular NEC topics

Connect, share expertise Access exclusive NEC


and best practice Users’ Group content
®NEC 2022
NEC SUPPORT
NEC IS WITH YOU THROUGHOUT YOUR FULL PROJECT
LIFECYCLE
Consultancy

NEC provides expert support to companies


Training
and individuals working on projects using
NEC offers a broad range of training products NEC forms of contract. We can:
to help your teams manage NEC effectively
and efficiently
Help you select the right contract for your
From a number of introductory courses project
allowing you to learn and understand each
contract and how it can be used Give specialist guidance on projects or to a
team on the use of NEC and its processes
To our practical courses that focus on Provide tender document review
successful preparing and managing of the
contract Advise on and review of the additional
conditions of the contract (Z clauses)
In addition, our advanced courses will allow
your team to excel in their contract roles and
NEC Competency demonstrate their knowledge and skills by
achieving our gold standard accreditation
Framework

®NEC 2022
GET IN TOUCH

Contact information

t +44 (0)20 7665 2446


e info@neccontract.com
w www.neccontract.com

Talk to one of our team to help


start your NEC journey!

®NEC 2022

You might also like