HADHAB MARMUL

INTERNATIONAL CONT. CO
Assets Mobilization Plan For
Oil & Gas Qarn-Alam
Actual VS target, Assets chart to fulfill requirements
with 4 crews for Re-sheeting & Repairing works

Available Assets HMI Hire Bdn Required Assets Shortage


 Dozer Nu : 02 01 01 00  Dozer Nu: 02 Nu : 00
 Shovel Nu : 03 02 01 01 HMI  Shovel Nu : 04 Nu : 01
 Grader Nu : 04 02 02 00  Grader Nu : 05 Nu : 01
 Roller Nu : 04 03 01 00  Roller Nu : 04 Nu : 00
 Water Tanker Nu : 11 05 06 03 HMI 1 Hire  Water Tanker Nu : 12 Nu : 01
 Prime mover Nu : 11 05 06 02 HMI 1 Hire  Prime Mover Nu : 13 Nu : 01
 Tipper Nu : 04 04 00 00  Tipper Nu : 08 Nu : 04
 Coaster Bus Nu : 02 01 01 00  Coaster Bus Nu : 03 Nu : 01
  Pick-up Nu : 06 Nu : 04
Pick-up NU : 03 03 00 00
  3 Ton Nu : 02 Nu : 01
3 Ton Nu : 01 01 0 00
  Low Bed Nu : 01 Nu : 00
Low Bed Nu : 01 01 00- 00
 Total Nu : 46 28 18 06 HMI 02Hire Total Nu : 60 Total Nu : 14

Percentage 76.67 % 60.87 % 39.13 % 17.39%Bdn 82.61 W Percentage 100% Req Percentage 23.33%